MONTHYEARIR 05000445/20240032024-10-30030 October 2024 Integrated Inspection Report 05000445/2024003 and 05000446/2024003 IR 05000445/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000445/2024404 and 05000446/2024404 (Public) IR 07200074/20244012024-10-10010 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200074/2024401 Public 05000445/LER-2024-002-01, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-10-0303 October 2024 Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions 05000446/LER-2024-001-01, Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-09-30030 September 2024 Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications CP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024 License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel ML24031A6322024-09-11011 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4), Final Safety Analysis Report Update Schedule (EPID L-2023-LLE-0023) - Letter ML24243A0152024-09-0303 September 2024 – Notification of Comprehensive Engineering Team Inspection (05000445/2025012 and 05000446/2025012) and Request for Information ML24194A1332024-08-28028 August 2024 Issuance of Amendment Nos. 190 and 190, Respectively, Revision to Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24228A2252024-08-22022 August 2024 Relief to Use Later Code Edition for Inservice Inspection Program ML24179A0772024-08-20020 August 2024 Issuance of Amendment Nos. 189 and 189, Respectively, Extension of Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24232A2262024-08-19019 August 2024 Information Request, Security IR 2024404 ML24232A2412024-08-19019 August 2024 Information Request, ISFSI Security IR 2024401 CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000445/20240052024-08-15015 August 2024 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2024005 and 05000446/2024005) CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality IR 05000445/20240022024-07-31031 July 2024 Units 1 and 2 - Integrated Inspection Report 05000445/2024002 and 05000446/2024002,and Independent Spent Fuel Storage Installation Inspection Report 07200074/2024001 IR 05000445/20244032024-07-16016 July 2024 Security Baseline Inspection Report 05000445/2024403 and 05000446/2024403 (Full Report) ML24187A0372024-07-15015 July 2024 Withdrawal of Requested Licensing Action Exemption from Select Requirements of 10 CFR Part 55, Operators Licenses ML24192A1862024-07-10010 July 2024 Notification of Inspection (NRC Inspection Report 05000445/2024003 and 05000446/2024003) and Request for Information ML24185A1382024-07-0202 July 2024 Inservice Inspection Request for Information CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 IR 05000445/20244012024-06-26026 June 2024 MC&A Program Inspection Report 05000445-2024401 and 05000446-2024401 Public-Final CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 IR 05000445/20240122024-06-17017 June 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2024012 and 05000446/2024012 ML24120A3632024-06-10010 June 2024 Issuance of Amendment Nos. 187 and 187, Respectively Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants 05000445/LER-1924-002, (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-06-0303 June 2024 (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator 05000446/LER-2024-001, (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-05-13013 May 2024 (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications 05000445/LER-2024-001, Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning2024-05-0606 May 2024 Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning ML24120A3042024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Sylestine, R, Alabama-Coushatta Tribe of Texas ML24120A2902024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Bunch, J, United Keetoowah Band of Cherokee Indians ML24120A2912024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cooper, D, Apache Tribe of Oklahoma ML24120A3032024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-SpottedBird, L, Kiowa Indian Tribe ML24107B1012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cernek, J, Coushatta Tribe of Louisiana ML24120A3022024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Pierite, M, Tunica-Biloxi Tribe of Louisiana ML24120A2922024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Dotson, Delaware Nation ML24120A2952024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Johnson, L.J., Seminole Nation of Oklahoma CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters ML24120A3052024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Woommavovah, M, Comanche Nation ML24120A3072024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Yargee, W, Alabama-Quassarte Tribal Town ML24120A2932024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Garza, Jr, Juan, Kickapoo Traditional Tribe of Texas ML24120A3002024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Morrow, R K, Thlopthlocco Tribal Town ML24120A2942024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Gonzalez, B, Caddo Nation ML24120A3012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Parton, T, Wichita and Affiliated Tribes ML24120A2972024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Martin, R, Tonkawa Tribe of Oklahoma ML24120A2962024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Kaskaske, D, Kickapoo Tribe of Oklahoma 2024-09-30
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000445/20233012023-08-21021 August 2023 NRC Examination Report 05000445/2023301 and 05000446/2023301 ML23156A2302023-06-0606 June 2023 NRC Initial Operator Licensing Examination Approval 05000445/2023301 and 05000446/2023301 IR 05000445/20213012021-10-19019 October 2021 NRC Examination Report 05000445/2021301 and 05000446/2021301 ML21236A3332021-08-25025 August 2021 CP2021301-Revised Exam Approval Ltr ML18207A9422018-08-0101 August 2018 NRC Examination Report 05000445/2018301, 05000446/2018301 IR 05000445/20173012017-07-11011 July 2017 NRC Examination Report 05000445/2017301; 05000446/2017301 IR 05000445/20163012016-09-23023 September 2016 NRC Examination Report 05000445/2016301; 05000446/2016301 IR 05000445/20153022015-06-26026 June 2015 Er 05000445/2015302; 05000446/2015302; on 06/01/2015 - 06/23/2015; the Comanche Peak Nuclear Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000445/20143012014-06-27027 June 2014 Er 05000445-14-301; 05000446-14-301; on June 9-16, 2014; the Comanche Peak Nuclear Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000445/20133012013-04-24024 April 2013 Er 05000445-13-301 & 05000446-13-301, 03/04/2013 - 04/22/2013, Comanche Peak Nuclear Power Plant, Units 1 and 2, Initial Operator Licensing Examination Report IR 05000445/20123012012-08-23023 August 2012 Er 05000445-12-301, & 05000446-12-301, June 11 Through July 23, 2012, Comanche Peak Nuclear Power Plant, Units 1 and 2, Initial Operator Licensing Examination Report IR 05000445/20113012011-07-0808 July 2011 Initial Operator Licensing Examination Report 05000445/2011301; 05000446/2011301 IR 05000445/20103022010-07-30030 July 2010 Er 05000445-10-302 on 07/07/10 07/08/10 for Comanche Peak Nuclear Power Plant, Unit 1 & 2, Initial Operator Licensing Examination Report IR 05000445/20093012009-05-0808 May 2009 Er 05000445-09-301, 05000446-09-301 on 03/30/09 - 04/14/09 for Comanche Peak, Units 1 and 2 IR 05000445/20053022005-11-0909 November 2005 Er 05000445-05-302; 05000446-05-302; 09/26/2005; Comanche Peak Steam Electric Station; Retake Operator Licensing Examination Report ML0409200332004-03-30030 March 2004 Generic Fundamentals Section of the Written Operator Licensing Examination 2023-08-21
[Table view] |
Text
ber 9, 2005
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION - NRC EXAMINATION REPORT 05000445/2005302, 05000446/2005302
Dear Mr. Blevins:
On September 12, 2005, a U. S. Nuclear Regulatory Commission (NRC) written examination retake was completed at the Comanche Peak Steam Electric Station. The enclosed report documents the examination findings, which were discussed on September 26, 2005, with Mr. E. Thomas, Operations Training Coordinator.
The examination included the evaluation of one applicant for an operator license. The written examination was developed using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9. The NRC license examiner determined that the applicant satisfied the requirements of 10 CFR Part 55, and the appropriate license has been issued.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Anthony T. Gody, Chief Operations Branch Division of Reactor Safety Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89
TXU Power -2-
Enclosure:
NRC Examination Report 05000298/2005302
REGION IV==
Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89 Report No.: 05000445/2005302; 05000446/2005302 Licensee: TXU Power Facility: Comanche Peak Steam Electric Station Location: Glen Rose, Texas Date: September 26, 2005 Examiner: Thomas F. Stetka, Senior Operations Engineer, Operations Branch Approved By: Anthony T. Gody, Chief Operations Branch Division of Reactor Safety-1- Enclosure
SUMMARY OF FINDINGS
ER 05000445/2005302; 05000446/2005302; 09/26/2005; Comanche Peak Steam Electric
Station; Retake Operator Licensing Examination Report.
The NRC examiner evaluated the competency of one applicant for an operator license at Comanche Peak Steam Electric Station. The licensee developed the examination using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9.
The written examination was administered by the facility to the applicant on September 12, 2005. The NRC examiner determined that the applicant satisfied the requirements of 10 CFR Part 55, and the appropriate license has been issued.
NRC-Identified and Self-Revealing Findings
None.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Initial Operator License Examination)
1. Operator Knowledge and Performance
a. Examination Scope
This examination was a retake of the written examination portion of an operator licensing examination that was administered on March 24, 2005. The applicant for that examination passed the operating test portion of examination but failed the written portion of that examination. On August 25, 2005, the applicant applied for a retake of the written examination and requested a wavier of the operating test. This wavier was granted by the NRC on September 6, 2005.
On September 12, 2005, the licensee administered the examination to the applicant.
The licensee staff graded the examinations, analyzed the results, and presented their analysis to the NRC on September 13, 2005.
b. Findings
No findings of significance were identified.
2. Initial Licensing Examination Development
a. Examination Scope
The licensee developed the examination in accordance with NUREG-1021, Revision 9.
All licensee facility training and operations staff involved in examination preparation and validation were on a security agreement. The facility licensee submitted the written examination outline on June 24, 2005. The chief examiner reviewed the outline against the requirements of NUREG-1021, Revision 9, and provided comments to the licensee on June 30, 2005. The facility licensee submitted the draft examination on August 1, 2005. The chief examiner reviewed the draft examination against the requirements of NUREG-1021, Revision 9, and provided comments to the licensee on the examination on August 30, 2005. The licensee satisfactorily completed comment resolution on August 30, 2005.
b. Findings
The NRC approved the initial examination outline and advised the licensee to proceed with examination development.
The chief examiner determined that the examination initially submitted by the licensee was within the range of acceptability expected for a proposed examination.
No findings of significance were identified.
3. Examination Security
a. Examination Scope
The examiners reviewed examination security and plans for applicant control with licensee personnel with respect to NUREG-1021 requirements.
b. Findings
No findings of significance were identified.
4OA6 Meetings, Including Exit
The chief examiner presented the examination results to Mr. E. Thomas, Operations Training Coordinator, on September 26, 2005. The licensee acknowledged the results presented.
The licensee did not identify any information or materials used during the examination as proprietary.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
-2- Enclosure
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- W. Gross, Training Instructor
- E. Thomas, Operations Training Coordinator
Attachment