Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-438/84-21 & 50-439/84-21
ML20127F823
Person / Time
Site: Bellefonte  
Issue date: 04/22/1985
From: Verrelli D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML20127F827 List:
References
NUDOCS 8505200603
Download: ML20127F823 (1)


Text

p

.

APR 221985 Tennessee Valley Authority ATTN: Mr. H. G. Parris Manager of Power and Engineering 500A Chestnut Street Tower II Chattanooga, TN 37401 Gentlemen:

SUBJECT: REPORT NOS. 50-438/84-21 AND 50-439/84-21 Thank you for your supplemental response of April 10, 1985, to our Notice of Violation issued on October 30, 1984, concerning activities conducted at your Bellefonte facility. We have evaluated your response and found that it meets the requirements of 10 CFR 2.201.

We will examine the implementation of your corrective actions during future inspections.

We appreciate your cooperation in this matter.

Sincerely, ORictNAL SIGNED BY DAVID M. VERRELLI David M. Verre111, Chief Reactor Projects Branch 1 Division of Reactor Projects cc:

E. A. Condon, Bellefonte Nuclear Plant Engineering Coordinator A. M. Qualls, Plant Manager J. W. Anderson, Manager Office of Quality Assurance K. W. Whitt, Chief, Nuclear Safety Staff W. R. Brown, Jr., Bellefonte Nuclear Plant Project Manager D. L. Williams, Jr., Supervisor Licensin; Section K. D. Mali, Project Engineer L. S. Cox, Construction Project Manager bec: NRC Resident Inspector Document Control Desk State of Alabama RII RI AIgn n s:jw SWeise 4//$/85 4/d/85 8505200603 850422 L