UNITE D S TATES NUC LEAR REGULATOR Y C OMMIS SI ON ber 14, 2010
SUBJECT:
GRAND GULF NUCLEAR STATION - NRC SECURITY INSPECTION REPORT 05000416/2010405
Dear Mr. Douet:
On November 19, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Grand Gulf Nuclear Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on November 19, 2010, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
This report documents one NRC identified finding of very low security significance (i.e., Green as determined by the physical protection significance determination process). This deficiency was promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspector left the site. However, because of the very low security significance, and because this violation was entered into your corrective action program, the NRC is treating this violation as a noncited violation (NCV) consistent with Section 2.3.2 of the NRC Enforcement Policy. If you contest this noncited violation, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington, D.C. 20555-0001;with copies to the Regional Administrator, Region IV, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Entergy Operations, Inc. -2-Suite 400, Arlington, Texas, 76011-4125; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at Grand Gulf Nuclear Station.
Additionally, the finding had a crosscutting aspect in the area of Human Performance associated with Work Practices, because an armed security response officer failed to effectively use human error prevention techniques commensurate with the requirements for fitness for duty H.4(a)
(Section 3S05). If you disagree with the crosscutting aspect assigned to the finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at Grand Gulf Nuclear Station.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, ADAMS.
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information-Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Michael P. Shannon, Chief Plant Support Branch-1 Division of Reactor Safety Docket No.: 50-416 License No.: NPF-29 Nonpublic Enclosure:
NRC Inspection Report 05000416/2010405 w/Attachment: Supplemental Information Entergy Operations, Inc. -3-cc w/o enclosure:
Senior Vice President Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Senior Vice President and COO Entergy Operations, Inc P.O. Box 31995 Jackson, MS 39286-1995 Vice President, Oversight Entergy Operations, Inc P.O. Box 31995 Jackson, MS 39286-1995 Manager, Licensing Sr. Site Executive Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Senior Manager, Nuclear Safety & Licensing Licensing /Regulatory Affairs Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Manager, Licensing Entergy Operations, Inc Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150 Associate General Counsel Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Entergy Operations, Inc. -4-Joseph A. Aluise Associate General Council - Nuclear Entergy Services, Inc 639 Loyola Avenue New Orleans, LA 70113 Entergy Operations, Inc. -5-Distribution w/enclosure:
Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Clay Johnson, (Clay.Johnson@nrc.gov), NSIR/DSO/DDSO/SPEB, TWFN 3D43 Branch Chief, RI DRS (James.Trapp@nrc.gov)
Branch Chief, RII DRS/PSB2 (Michael.Ernstes@nrc.gov)
Branch Chief, RIII DRS/PSB (Richard.Skokowski@nrc.gov)
Senior Resident Inspector (Rich.Smith@nrc.gov)
Electronic distribution by RIV:
Distribution w/o enclosure:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Vacant)
Resident Inspector (Andy.Barrett@nrc.gov)
Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov)
Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov)
Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov)
GG Administrative Assistant (Alley.Farrell@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Balwant.Singal@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource OEDO RIV Coordinator (Geoffrey.Miller@nrc.gov)
DRS/TSB STA (Dale.Powers@nrc.gov)
Security Related Complete Report - OUO:
SUNSI Review Completed: JLB ADAMS: : Yes Initials: JLB
- Non-Publicly Available : Sensitive-Security- Related-Periodic Review Required Letter Only:
SUNSI Review Completed: JLB ADAMS: : Yes Initials: JLB
- Publicly Available : Non-Sensitive PSI:PSB1 PSI:PSB1 C:PSB1 C:PBC C:PSB1 JBuchanan JRollins MShannon VGaddy MShannon
/RA/ /RA/ /RA/ /RA/ /RA/
12/13/2010 12/14/2010 12/14/2010 12/14/2010 12/14/2010 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax