IR 05000413/2010402

From kanterella
Jump to navigation Jump to search
Submittal of NRC Security Inspection Report 05000413/2010402 and 05000414/2010402
ML100610296
Person / Time
Site: Catawba  Duke energy icon.png
Issue date: 03/01/2010
From: Christensen H
Division of Reactor Safety II
To: Morris J
Duke Energy Carolinas
References
IR-10-402
Download: ML100610296 (3)


Text

rch 1, 2010

SUBJECT:

CATAWBA NUCLEAR STATION - NRC SECURITY INSPECTION REPORT 05000413/2010402 AND 05000414/2010402

Dear Mr. Morris:

On January 28, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Catawba Nuclear Station, Units 1 and 2. The enclosed inspection report documents the inspection results, which were discussed on January 28, 2010, with you and other members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commission=s rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents one finding of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process). The finding is NRC identified. The deficiency was corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspector left the site. The finding had a cross-cutting aspect in the area of Human Performance. H.4(b). Additionally, licensee-identified violations, which were determined to be of very low safety significance, are listed in this report. However, because of the very low safety significance and because they are entered into your corrective action program, the NRC is treating these violations as non-cited violation(s) (NCVs) consistent with Section VI.A.1 of the NRC Enforcement Policy. If you disagree with the characterization of any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001; with copies to the Regional Administrator Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, D.C. 20555-Enclosure(s) transmitted herewith contains(s) SUNSI. When separated from enclosure(s)

this transmittal document is decontrolled. DEC, LLC 2 0001; and the NRC Resident Inspector at the Catawba Nuclear Station. The information you provide will be considered in accordance with Inspection Manual Chapter 0305.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter=s enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this letter, please contact us.

Sincerely,

/RA/

Harold O. Christensen, Deputy Director Division of Reactor Safety Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52 Enclosure: Inspection Report 05000413/2010402 and 05000414/2010402 w/Attachment: Supplemental Information ( )

cc: See Page 3 DEC, LLC 3 cc w/encl: DPC 3 cc w/encl: Susan E. Jenkins Randy D. Hart Director, Division of Waste Management Regulatory Compliance Manager Bureau of Land and Waste Management Duke Power Company, LLC S.C. Department of Health and d/b/a Duke Energy Carolinas, LLC Environmental Control CN01RC 2600 Bull Street 4800 Concord Road Columbia, SC 29201 York, SC 29745-9635 Elizabeth McMahon Lisa F. Vaughn Assistant Attorney General Associate General Counsel S.C. Attorney General's Office Duke Energy Corporation P.O. Box 11549 526 South Church Street-EC07H Columbia, SC 29211 Charlotte, NC 28202 Vanessa Quinn Kathryn B. Nolan Federal Emergency Management Agency Senior Counsel 500 C Street, SW Duke Energy Corporation Room 840 526 South Church Street-EC07H Washington, DC 20472 Charlotte, NC 28202 Peggy Force R. L. Gill, Jr. Assistant Attorney General Manager State of North Carolina Nuclear Regulatory Issues and Industry P.O. Box 629 Affairs Raleigh, NC 27602 Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC North Carolina MPA-1 526 South Church Street Suite 600 Charlotte, NC 28201-0006 P. O. Box 29513 Raleigh, NC 27525=0513 cc w/o encl:

David A. Repka Steve Weatherman, Operations Analyst Winston Strawn LLP North Carolina Electric Membership Corp.

1400 L Street NW P. O. Box 27306 Washington, DC 20005 Raleigh, NC 27611-7306 County Manager of York County York County Courthouse York, SC 29745 Piedmont Municipal Power Agency 121 Village Drive Greer, SC 29651