IR 05000390/2020011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000390/2020011 and 05000391/2020011
ML20294A260
Person / Time
Site: Watts Bar  
Issue date: 10/20/2020
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Jim Barstow
Tennessee Valley Authority
References
IR 2020011
Download: ML20294A260 (11)


Text

October 20, 2020

SUBJECT:

WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000390/2020011 AND 05000391/2020011

Dear Mr. Barstow:

On September 24, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Watts Bar Nuclear Plant, Units 1 and 2 and discussed the results of this inspection with Mr. Anthony Williams and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety

Docket Nos. 05000390 and 05000391 License Nos. NPF-90 and NPF-96

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000390 and 05000391

License Numbers:

NPF-90 and NPF-96

Report Numbers:

05000390/2020011 and 05000391/2020011

Enterprise Identifier: I-2020-011-0042

Licensee:

Tennessee Valley Authority

Facility:

Watts Bar Nuclear Plant, Units 1 and 2

Location:

Spring City, TN

Inspection Dates:

August 31, 2020 to September 24, 2020

Inspectors:

P. Carman, Senior Reactor Inspector

M. Greenleaf, Reactor Inspector

N. Morgan, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Watts Bar Nuclear Plant, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19),inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a. Evaluated whether the sampled POVs are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b. Evaluated whether the sampled POVs are capable of performing their design-basis functions.

c. Evaluated whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d. Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1)1-FCV-1-51-S, Turbine-Driven Auxiliary Feedwater Pump Trip and Throttle Valve (2)1-FCV-67-67-B, Diesel Generator Heat Exchanger 1B1/1B2 Essential Raw Cooling Water Supply Header 1B Isolation Valve (3)1-FCV-72-2-B, Containment Spray Header (Train B) Isolation Valve (4)2-FCV-63-93-A, Residual Heat Removal to Cold Leg 2 & 3 Injection Isolation Valve (5)2-FCV-68-332-B, Pressurizer Power-Operated Relief Valve (PORV) Block Valve (6)2-LCV-62-135-A, Refueling Water Storage Tank Chemical and Volume Control System Supply Header Isolation Valve (7)1-FCV-1-22-T, Main Steam Loop 3 Isolation Valve (8)1-PCV-1-5-T, Steam Generator Loop 1 PORV Valve (9)2-FCV-1-25-B, Steam Generator 3 Blowdown Isolation Valve

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 24, 2020, the inspectors presented the design basis assurance inspection (programs) inspection results to Mr. Anthony Williams and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.02 Calculations

048-018-MSS

System Level Review for Watts Bar Main Steam

Supply System Air Operated Valves

Rev. 1

048-018-PIL

Evaluation of Required Thrust for MSIVs and SG-

PORVs (Pilot-Operated Balanced Disk Globe

AOVs) at Watts Bar Nuclear Power Station

Rev. 1

25402-011-V1E-SS00-

00001-002

EPRI MOV PPM Analysis for 4 Butterfly MOVs for

Compliance with GL 89-10 MOV Program

Requirements for Units 1 and 2, Document No.

2914C

Rev. 2

CGACQ1304

Weak Link Analysis for 8-150# Posi Seal Butterfly

Valves Mark# 17W586-1

Rev. 1

EDQ00099920070002

AC Auxiliary Power System Analysis

Rev. 73

EPMCPH060292

Documentation of MOV Design Basis Review and

Thrust/Torque Requirements and Valve and

Actuator Capability Assessment for Valve 1-FCV-

2-2

Rev. 6

EPMDTN051192

Documentation of Design Basis Review, Required

Torque Calculations, and Valve and Actuator

Capability Assessment for Valve 1-FCV-67-67

Rev. 6

EPMTSS117091

Generic Letter 89-10 MOV Population at Watts Bar

(Unit 1)

Rev. 28

EPTMSS100292

Documentation of Design Basis Review, Required

Thrust/Torque Calculations, and Valve and Actuator

Capability Assessment for Valve 1-FCV-01-051

Rev. 7

MDN-000-999-2011-

0178

WBN Probabilistic Risk Assessment - Risk Ranking

of Motor Operated Valves

Rev. 2

MDN-000-999-2011-

0179

WBN Probabilistic Risk Assessment - Risk Ranking

of Air Operated Valves (AOV)

Rev. 1

MDQ00099920010063

Categorization of the Air Operated Valves (AOVs)

Rev. 7

MDQ00100120020072

Component Level Review Calculation for Watts Bar

Main Steam Supply (MSS) System Pilot-Operated

Balanced Disk Globe Air Operated Valves (AOVs)

Rev. 5

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MDQ00199920100167

Watts Bar Nuclear Plant JOG MOV Periodic

Verification Classification

Rev 5

MDQ0020622008-0226

Documentation of Design Basis Review Required

Thrust/Torque Calculations and Valve and Actuator

Capability Assessment for Valve 2-LCV-62-135

Rev. 5

MDQ0020632008-0244

Documentation of Design Basis Review, Required

Thrust/Torque Calculations and Actuator Capability

Assessment for Valve 2-FCV-63-093

Rev. 9

MDQ0020682008-0274

Documentation of Design Review Basis Review,

Required Thrust/Torque Calculations and Valve and

Actuator Capability Assessment for Valve 2-FCV-

68-332

Rev. 4

MDQ0029992009-0310

Generic Letter 89-10 MOV Population for Watts Bar

(Unit 2)

Rev. 10

MDQ0029992015000687 Watts Bar Nuclear Plant Unit 2 JOG MOV Periodic

Verification Classification

Rev. 0

QDC0029992014000504

Material Aging Calculation for Unit 1 and 2

Mechanical Equipment Qualification (Binder WBN-

MEQ-001)

Rev. 11

WAT-D-8584

Maximum Allowable Thrusts

06/25/1991

WBN-EM-59

Essentially Mild Calculation for Limitorque Actuators Rev. 9

WBNOSG4159

Thermal Transient of Target Rock Solenoid Valves

Located in the Valve Vaults During a MSLB

Rev. 6

WBT-D-4037

Summary of Seismic Analysis of 8GM78FN Built to

Drawing 115E012 at Watts Bar Unit 2

08/29/2012

Corrective Action

Documents

CRs 1093165, 1195979,

1601458, 1624132,

25963

Corrective Action

Documents

Resulting from

Inspection

CR 1639485

20 NRC POV Inspection - PM frequency change

needed

09/23/2020

CR 1634592

20 NRC POV Inspection - procedure typo in

rev.log reference

09/03/2020

CR 1634666

20 NRC POV Inspection - Correct reference in

Section 7.1.9 of calculation EPMDTN051192

09/03/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR 1634871

20 NRC POV Inspection - Administrative Error in

EDQ00099920070002 Appendix 10.9

09/03/2020

CR 1635223

20 NRC POV Inspection - Calculation

EPMTSS100292 reference omission and input

clarification

09/08/2020

CR 1636100

20 POV NRC Inspection - Correct typographical

error for Reference 3 on pdf page 730 (actual calcul

09/08/2020

CR 1636444

20 NRC POV Inspection - Document critical

thinking associated with Section XI repairs

09/14/2020

CR 1637673

20 NRC POV Inspection - Additional

Documentation of Critical Thinking for Section XI

Repairs.

09/17/2020

CR 1638837

20 NRC POV Inspection - MOV PV thrust test

data for 1-FCV-1-51 suspected unreliable

09/21/2020

CR 1639066

20 NRC POV Inspection - missing

evaluation/justification of not obtaining AF torque

values

09/21/2020

CR 1639626

20 NRC POV Inspection - QMDS requirements

do not match Vendor Manual

09/23/2020

CR 1639697

20 NRC POV Inspection Performance Deficiency

09/24/2020

CR 1639749

20 NRC POV Inspection - Delete o-ring

replacement

09/24/2020

Drawings

0-47W845-1

Mechanical Flow Diagram-Essential Raw Cooling

Water System

Rev. 19

1-47A595-3

Set-Up Parameters for Air Operated Valves Setup

Box for 1-FCV-001-0022-T

Rev. 2

1-47A8910-72-01

Mechanical Table of Motor-Operated Valve

Requirements

Rev. 3

1071240-7

Solenoid Operated Valve Energize to Open (FC) -

ON/OFF 2 1/2 - 4 Inch

Rev. G

1167E80

Motor Op Gate Valve, MOD 10000GM82FBB00B

Rev. 903

2-47W813-1

Flow Diagram Reactor Coolant System

Rev. 39

2607

Electrical Assy

Rev. E

O-47W803-2

Rev. 9

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

ESBU/WOG-96-022

Summary of January 4 & 5, 1996 Pressure Locking

& Thermal Binding (PLTB) Task Team Meeting

(MUHP-6050)

01/19/1996

SDD-N3-1-4002

Main Steam System

Rev. 22

SDD-N3-15-4002

Steam Generator Blowdown System Unit 1 / Unit 2

Rev. 19

SDD-N3-3B-4002

Auxiliary Feedwater System

Rev. 30

SDD-N3-68-4001

Reactor Coolant System

Rev. 43

WB-DC-30-15

Motor Operated Valve Thermal Overload and

Torque Switch Bypass

Rev. 6

WBN-SDD-N3-63-4001

Safety Injection System (Unit 1 / Unit 2)

Rev. 36

WBN-SDD-N3-67-4002

Essential Raw Cooling Water System, System 67

Rev. 38

WBN-VTD-C994-0010

Equipment Inaccuracy Summary for Motor

Operated Valves

Rev. 7

WBN-VTD-T020-0520

Target Rock Technical Manual for Calve Models

2AB-001-4BB, 82AB-001-5BB

Rev. 1

WBN-VTD-T401-0010

Teledyne Test Services Quiklook II Valve

Diagnostic Test Equipment Description, Safety

Related Status, Accuracy & Calibration Periodicity

Summary

Rev. 1

WBNEQ-MOV-003

Limitorque Actuators with Class B Motors

Rev. 37

WBNEQ-SOL-002

Target Rock Solenoid Valves

Rev. 40

WBNMEQ-001-53006

Mechanical Equipment Qualification Package

Rev. 2

WOG-05-87

Addendum to Verification of Pressure Locking

Analysis Program - PRESLOK (CN-SEE-01-141)

2/28/2005

Procedures

0-TI-100.006

Inservice Testing Program

Rev. 9

1-SI-1-906-A

Main Steam Valves Position Indication Verification -

Train A

Rev. 13

1-SI-3-902

Turbine Driven Auxiliary Feedwater Pump 1A-S

Quarterly Performance Test

Rev. 59

2-SI-68-901-B

Valve Full Stroke Exercising During Plant

Operation: Reactor Coolant B-Train

Rev. 3

2-TRI-0-4

Month B Train MOV Thermal Overload Relay

Bypass Circuit Functional Test

Rev. 7

DS-M18.2.21

Motor Operated Valve Thrust and Torque

Rev. 25

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

G-50

Torque, Thrust and Control Switch Settings for

Motor-Operated Valves

Rev. 12

NPG-SPP-09.26.13

Air Operated Valve Program

Rev. 0

NPG-SPP-09.26.14

Motor Operated Valve Program

Rev. 4

Work Orders

114900760, 115264274,

116646007, 116986101,

117325065, 117404329,

117758092, 117625369,

117943531, 118294730,

118720661, 119064218,

119064767, 119473916,

119475391, 119526855,

119528673, 120241095,

20241347, 120295031,

20295726, 120498998,

20555952, 120557231,

20850611, 120850804,

21027350