Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2018006 and 05000388/2018006)
ML19060A196
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 03/04/2019
From: Jon Greives
Reactor Projects Region 1 Branch 4
To: Berryman B
Susquehanna
Greives J
References
IR 2018006
Download: ML19060A196 (6)


Text

rch 4, 2019

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (REPORTS 05000387/2018006 AND 05000388/2018006)

Dear Mr. Berryman,

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Susquehanna Steam Electric Station (Susquehanna), Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2018, through December 31, 2018. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Susquehanna, Units 1 and 2 during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e.,

Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2020. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections). Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. Furthermore, all the inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In addition to baseline inspections, the NRC will conduct Temporary Instruction 2515/191, Inspection of Licensees Responses to Order EA-12-049, EA-12-051, and Emergency Preparedness Info Request, in June 2019; Inspection Procedure 60855.1, Operation of an ISFSI at Operating Plant, in September 2019; and Inspection Procedure 71003, Post Approval Site Inspection for License Renewal, (Unit 1) in April 2020. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5337 with any questions you have regarding this letter.

Sincerely,

/RA/

Jonathan E. Greives, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 50-387 and 50-388 License Nos. NPF-14 and NPF-22 Enclosure:

Inspection Plan cc w/encl: Distribution via ListServ

ML19060A196 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME GCroon via email JGreives DATE 2/28/19 3/4/19

IP 22 Inspection Activity Plan Report Susquehanna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count 4th Quarter Site Support 10 1, 2 10/01/2018 02/12/2019 IP 71152 000748 Problem Identification and Resolution 1, 2 10/01/2018 02/12/2019 IP 71153 000749 Followup of Events and Notices of Enforcement Discretion ACCESS CONTROL, EQUIP PERF, TRAINING 3 1, 2 02/11/2019 02/15/2019 IP 71130.02 000734 Access Control 1, 2 02/11/2019 02/15/2019 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 02/11/2019 02/15/2019 IP 71130.07 000739 Security Training 1, 2 02/11/2019 02/15/2019 IP 71151 001338 Performance Indicator Verification HP 1 1, 2 02/25/2019 03/01/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 02/25/2019 03/01/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls INSERVICE INSPECTION - UNIT 2 1 2 03/31/2019 03/31/2019 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

HP 1 1, 2 04/08/2019 04/12/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/08/2019 04/12/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls REMP 1 1, 2 05/20/2019 05/24/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program TI-191 FUKUSHIMA LESSONS-LEARNED 3 1, 2 06/24/2019 06/28/2019 TI 2515/191 000509 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 SUSQUEHANNA INITIAL OL EXAM 4 1, 2 07/28/2019 08/02/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2 08/25/2019 09/06/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

ISFSI OPERATIONAL INSPECTION 2 1, 2 09/09/2019 09/13/2019 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants DESIGN BASES ASSURANCE INSP - TEAMS 6 1, 2 09/15/2019 09/21/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.

2/13/2019 2:18:26 PM Enclosure

IP 22 Inspection Activity Plan Report Susquehanna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count DESIGN BASES ASSURANCE INSP - TEAMS 6 1, 2 09/29/2019 10/05/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

EP PROGRAM INSPECTION 2 1, 2 10/21/2019 10/25/2019 IP 71114.02 000717 Alert and Notification System Testing 1, 2 10/21/2019 10/25/2019 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 10/21/2019 10/25/2019 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 10/21/2019 10/25/2019 IP 71151 001397 Performance Indicator Verification HP 1 1, 2 11/04/2019 11/08/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 11/04/2019 11/08/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 11/04/2019 11/08/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 11/04/2019 11/08/2019 IP 71124.04 000728 Occupational Dose Assessment 1, 2 11/04/2019 11/08/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 11/04/2019 11/08/2019 IP 71151 000746 Performance Indicator Verification SQ REQUAL INSP WITH P/F RESULTS 2 1, 2 11/17/2019 11/22/2019 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

1, 2 11/17/2019 11/22/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

Radwaste 1 1, 2 03/09/2020 03/13/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation License Renewal Phase 1 - Unit 1 1 1 04/05/2020 04/11/2020 IP 71003 000687 Post-Approval Site Inspection for License Renewal ISI - UNIT 1 1 1 04/05/2020 04/11/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

HP 1 1, 2 04/13/2020 04/17/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/13/2020 04/17/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.

2/13/2019 2:18:26 PM

IP 22 Inspection Activity Plan Report Susquehanna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count Access Control, Protective Strategy, TSR 4 1, 2 06/15/2020 06/19/2020 IP 71130.02 000734 Access Control 1, 2 06/15/2020 06/19/2020 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 06/15/2020 06/19/2020 IP 71130.14 000743 Review of Power Reactor Target Sets 1, 2 06/15/2020 06/19/2020 IP 71151 001338 Performance Indicator Verification HP 1 1, 2 07/06/2020 07/10/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 07/06/2020 07/10/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 07/06/2020 07/10/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 07/06/2020 07/10/2020 IP 71124.04 000728 Occupational Dose Assessment 1, 2 07/06/2020 07/10/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation PI&R Biennial Team Inspection 4 1, 2 07/13/2020 07/17/2020 IP 71152B 000747 Problem Identification and Resolution 1, 2 07/27/2020 07/31/2020 IP 71152B 000747 Problem Identification and Resolution TRIENNIAL FIRE PROTECTION 4 1, 2 09/21/2020 09/25/2020 IP 71111.05T 000696 Fire Protection (Triennial)

1, 2 10/05/2020 10/09/2020 IP 71111.05T 000696 Fire Protection (Triennial)

RETS 1 1, 2 10/05/2020 10/09/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment SUSQUEHANNA EP EXERCISE INSPECTION 5 1, 2 10/19/2020 10/23/2020 IP 71114.01 000716 Exercise Evaluation 1, 2 10/19/2020 10/23/2020 IP 71151 001397 Performance Indicator Verification HP 1 1, 2 12/14/2020 12/18/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 12/14/2020 12/18/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 12/14/2020 12/18/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/14/2020 12/18/2020 IP 71124.04 000728 Occupational Dose Assessment 1, 2 12/14/2020 12/18/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.