IR 05000352/2019010

From kanterella
Jump to navigation Jump to search
Temporary Instruction 2515/191 Inspection Report 05000352/2019010 and 05000353/2019010
ML19207A083
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 07/26/2019
From: Matt Young
NRC/RGN-I/DRP/PB6
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Young M
References
IR 2019010
Download: ML19207A083 (10)


Text

July 26, 2019

SUBJECT:

LIMERICK GENERATING STATION, UNITS 1 AND 2 - TEMPORARY INSTRUCTION 2515/191 INSPECTION REPORT 05000352/2019010 AND 05000353/2019010

Dear Mr. Hanson:

On June 13, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Limerick Generating Station, Units 1 and 2 and discussed the results of this inspection with Mr. Matthew Bonanno, Director Site Operations and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Matthew R. Young, Chief Reactor Projects Branch 6 Division of Reactor Projects

Docket Nos. 05000352 and 05000353 License Nos. NPF-39 and NPF-85

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000352 and 05000353

License Numbers:

NPF-39 and NPF-85

Report Numbers:

05000352/2019010 and 05000353/2019010

Enterprise Identifier: I-2019-010-0020

Licensee:

Exelon Generation Company, LLC

Facility:

Limerick Generating Station, Units 1 and 2

Location:

Sanatoga, PA

Inspection Dates:

June 10, 2019 to June 14, 2019

Inspectors:

C. Cahill, Senior Reactor Analyst

S. Haney, Senior Project Engineer

C. Lally, Operations Engineer

G. Stock, Resident Inspector

Approved By:

Matthew R. Young, Chief

Reactor Projects Branch 6

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction (TI) 2515/191 inspection at Limerick Generating Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 2515/191 - Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & Emergency

Preparedness (EP) Info Request March 12, 2012 (1 Sample)

(1) The inspectors verified plans for complying with NRC Orders EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, (ADAMS Accession No. ML12056A045) and EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, (ADAMS Accession No. ML12054A679) are in place and are being implemented by the licensee. Additionally, the inspection verified implementation of staffing and communications information provided in response to the March 12, 2012, request for information letter (ADAMS Accession No. ML12053A340) and multi-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013 (ADAMS Accession No. ML12339A262).

1. Based on samples selected for review, the inspectors verified that the licensee

satisfactorily implemented appropriate elements of the Diverse and Flexible Coping Strategies (FLEX) as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession No. ML18113A334) and determined that the licensee is in compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. The inspectors verified the licensee satisfactorily:

a. Developed and issued FLEX Support Guidelines (FSGs) to implement the FLEX strategies for postulated external events b. Integrated their FSGs into their existing plant procedures such that entry into and departure from the FSGs were clear when using existing plant procedures c. Protected FLEX equipment from site-specific hazards d. Developed and implemented adequate testing and maintenance of FLEX equipment to ensure their availability and capability e. Trained their staff to assure personnel proficiency in the mitigation of beyond-design basis events f.

Developed the means to ensure the necessary off-site FLEX equipment would be available from off-site locations

2. Based on samples selected for review, the inspectors verified that the licensee

satisfactorily implemented appropriate elements of the FLEX strategy as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession No. ML18113A334) and determined that the licensee is in compliance with NRC Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (ADAMS Accession No.

ML12054A679). The inspectors verified the licensee satisfactorily:

a. Installed the spent fuel pool (SFP) instrumentation sensors, cabling, and power supplies to provide physical and electrical separation as described in the plant specific submittals and safety evaluation b. Installed the SFP instrumentation display in the location, environmental conditions, and accessibility as described in the plant specific submittals c. Trained their staff to ensure personnel proficiency with the maintenance, testing, and use of the SFP instrumentation d. Developed and issued procedures for maintenance, testing, and use of the reliable SFP instrumentation

3. The inspectors reviewed information provided in the licensees multi-unit dose

submittal and in response to the NRCs March 12, 2012, request for information letter (ADAMS Accession No. ML12053A340),and verified that the licensee satisfactorily implemented enhancements pertaining to Near-Term Task Force Recommendation 9.3 response to a large scale natural emergency event that results in an extended loss of all AC power to all site units and impedes access to the site. The inspectors verified the following:

a. The licensee satisfactorily implemented required staffing changes to support a multi-unit extended loss of AC power (ELAP) scenario b. EP communications equipment and facilities are sufficient for dealing with a multi-unit ELAP scenario c. The licensee implemented multi-unit dose assessment capabilities (including releases from SFPs) using the licensees site-specific dose assessment software and approach

The inspectors verified that non-compliances with requirements and standards identified during the inspection were entered into the licensee's corrective action program as appropriate.

This TI is considered closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On June 13, 2019, the inspectors presented the TI 2515/191 inspection results to Mr. Matthew Bonanno, Director Site Operations and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2515/191

Calculations

LM-0710

Refueling Floor Air Space Transient Temperature Profile

following ELAP

Corrective Action

Documents

03990423, 03995403, 04111121, 04144866, 04178941,

217474, 04224354, 04229319, 04233213

Corrective Action

Documents

Resulting from

Inspection

256267, 04256357, 04256547

Drawings

SK-C-378

Site Plan Flooding Control Areas

Engineering

Changes

  1. 13-00414

Westinghouse Spent Fuel Pool Instrumentation System

(SFPIS) Documents

Engineering

Evaluations

617968

Determine Time to Boil for High Heat Load/Low Volume

Periods

Miscellaneous

LLOW1901FLEX

Limerick Licensed Operator Requalification

PES-P-006

Diesel Fuel Oil

Purchase Order

10564072

Diesel Fuel Oil

TI0191

BDBEE Mitigating Strategies (FLEX) Spent Fuel Pool Level

Instrument Staffing and EP Communications

June 10,

2019

Procedures

ARC-MCR-112 I5

Fuel Pool Storage Hi/Lo Level,

ARC-MCR-212 I5

Fuel Pool Storage Hi/Lo Level

CC-LG-118

Site Implementation of Diverse and Flexible Coping

Strategies (FLEX), Spent Fuel Pool Instrumentation and

Hardened Containment Vent (HCVS) Program

CC-LG-118-1002

Congested Area Flight Plan for Limerick Generating Station

CC-LG-118-1003

Limerick Generating Station Units 1 and 2 Final Integrated

Plan Document

E-1

Loss of all AC Power (Station Blackout)

E-10/20

Loss of Offsite Power

EP-AA-110-201

On-Shift Dose Assessment

EP-AA-112-400-

F-10

Security Coordinator (EOF) Checklist

H

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EP-AA-124-F-03

FLEX Communications Equipment Testing and Inventorying

of the Site and Site-Specific EOF Fixed and Portable Satellite

Systems

C

IC-11-00339

Calibration and Testing of Guided Wave Radar Spent Fuel

Pool Level Instruments

M-097-009

Limerick Generating Station Cask Pit Gate Removal,

Installation, Maintenance and Movement of Fuel Pool Gates

Between Storage/Repair Locations

MA-LG-716-026-

1001

Additional Guidance for In-Plant/Yard Storage and

Housekeeping at Limerick

NF-LG-310-2000

Spent Nuclear Material and Core Component Movement

ON-125

Loss of Fuel Pool Cooling

OP-LG-102-102-

1001

Augmented Operator Field Rounds

OP-LG-115-1004

Transfer of Fuel To/From the FLEX Building Storage Tank

(00-T527)

OU-LG-104

Shutdown Safety Management Program

PSTG-T-103-SCC Exelon Nuclear Limerick Generating Station Plant Specific

Technical Guideline Secondary Containment Control

S15.3A

Inflation of Reactor Well, Fuel Pool Gate, Fuel Pool Stop Log

  1. 15, Cask Handling Pit Gate and Steam Dryer and Separator

Stop Log Seals

S20.10.B

Ordering and Accepting Delivery of Fuel Oil

S53.0A

Normal Makeup/Response to Low Level in Fuel Storage Pool

or Reactor Well

T-300 Appendix 1

Godwin HL 130M Flex Pump Operation Hard Card

T-301 U1

RPV Injection from Spray Pond

T-301 U2

RPV Injection from Spray Pond

T-322 U1

SFP Makeup and Spray from Spray Pond

T-322 U2

SFP Makeup and Spray from Spray Pond

T-346

Refuel Floor Alignment for SFP Makeup Spray and

Ventilation

T-364

Communication Systems Alternate Power

T-365

SFP Level Instrumentation Backup Power

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

T-370 U1

Primary and Alternate Instrumentation During ELAP

T-370 U2

Primary and Alternate Instrumentation During ELAP

TSG-1.3

FLEX Event Resource Management Guidelines

Work Orders

04840087

FLEX Generator Fuel Oil Tank Heater Not Controlling

Properly

04920434

Perform Maintenance on Portable Diesel Pump

0