IR 05000348/2008010

From kanterella
Jump to navigation Jump to search
Ti 2515/171 Verification of Implementation of B.5.b Phase 2 and 3 Mitigating Strategies Inspection Report 05000348-08-010 and 05000364-08-010
ML090200072
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 01/20/2009
From: Scott Shaeffer
NRC/RGN-II/DRP/RPB2
To: Jerrica Johnson
Southern Nuclear Operating Co
References
TI 2515/171 IR-08-010
Download: ML090200072 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 January 20, 2009 Mr. J. Randy Johnson Vice President - Farley Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319 SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT TI 2515/171 VERIFICATION OF IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITGATING STRATEGIES INSPECTION REPORT 05000348/2008010 AND 05000364/2008010

Dear Mr. Johnson:

On December 11, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of your Joseph M. Farley Nuclear Plant, Units 1 and 2. The enclosed inspection report documents the inspection results, which were discussed on December 11, 2008, with yourself and other members of your staff.

The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the condition of your operating license. Within these areas, the inspection involved examination of selected procedures and records, observation of activities, and interviews with station personnel. Based on the results of this inspection, no findings of significance were identified.

In accordance with 10 CFR (Code of Federal Regulations) 2.390 of the NRC Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of the NRC Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). SNC, INC. 2 However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket No.: 50-348, 50-364 License No.: NPF-2, NPF-8 Enclosure: Inspection Report 05000348/2008010 and 05000364/2008010 w/Attachment: Supplemental Information cc w/encl: (See page 3) ____________________x SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRS RII:DRP HQ:NRR HQ:NRR RII:DRS SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/

NAME SSANDAL NSTAPLES SSHAEFFER TSHEDLOSKY DNELSON DATE 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO SNC, INC. 3 cc w/Encl: cc w/o Encl:

B. D. McKinney Dr. D. E. Williamson Licensing Services Manager State Health Officer B-031 Alabama Dept. of Public Health Southern Nuclear Operating Company, Inc. RSA Tower - Administration 42 Inverness Center Parkway Suite 1552 Birmingham, AL 35201-1295 P.O. Box 303017 Montgomery, AL 36130-1701 General Manager Farley Plant Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295 Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295 William D. Oldfield Quality Assurance Supervisor Southern Nuclear Operating Company P.O. Box 470 Ashford, AL 36312 Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc.

Bin B-022 P.O. Box 1295 Birmingham, AL 35201-1295 David H. Jones, Vice President Engineering Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295 4 Letter to J. Randy Johnson from Scott M. Shaeffer dated January 20, 2009 SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT TI 2515/171 VERIFICATION OF IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITGATING STRATEGIES INSPECTION REPORT 05000348/2008010 AND 05000364/2008010 Distribution w/encl:

R. Martin, NRR C. Evans, RII EICS (Part 72 Only)

L. Slack, RII EICS (Linda Slack)

B. Westreich, NSIR (hard copy w/ encl)

E. McNiel, NSIR (hard copy w/ encl)

S. Shaeffer, DRP E. Crowe, Farley SRI S. Sandal, Farley RI D. Nelson, NRR E. Bowman, NRR D. Riffle, NSIR RIDSNRRDIRS OE Mail (email address if applicable)

PUBLIC Distribution w/o encl:

A. Barrett, Farley OA Region II Docket Room (with concurrences)

ROPreports@nrc.gov