Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] |
Text
ary 30, 2012
SUBJECT:
NORTH ANNA POWER STATION, UNITS 1 AND 2 - NRC SECURITY INSPECTION REPORT 05000338/2011201 AND 05000339/2011201
Dear Mr. Lane:
On December 8, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at the North Anna Power Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on December 8, 2011, with Mr. Fred Mladen, Director - Station and Licensing, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's
"Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Garmon West, Chief Security Training and Support Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos. 50-338, 50-339 License Nos. NPF-4, NPF-7 Enclosure: Inspection Report 05000338/2011201 and 05000339/2011201 w/Attachments:
Supplemental Information