IR 05000321/2020401

From kanterella
Jump to navigation Jump to search
Security Baseline Inspection Report 05000321/2020401, 05000366/2020401, and 07200036/2020401 (U)
ML20346A090
Person / Time
Site: Hatch, 07200036  Southern Nuclear icon.png
Issue date: 12/10/2020
From: James Shehee
NRC/RGN-II
To: Mcgavin S
Southern Nuclear Operating Co
References
IR 2020401
Download: ML20346A090 (4)


Text

December 10, 2020

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 - SECURITY BASELINE INSPECTION REPORT 05000321/2020401, 05000366/2020401, AND 07200036/2020401 (U)

Dear Mr. McGavin:

On November 20, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Edwin I. Hatch Nuclear Plant, Units 1 and 2 and discussed the results of this inspection with Mr. Christopher Byrd and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low security significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low security significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Edwin I. Hatch Nuclear Plant, Units 1 and 2.

The following cross cutting aspect was assigned to a finding using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: [P.6] - Self-Assessment. If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Edwin I.

Hatch Nuclear Plant, Units 1 and 2.

The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).

Sincerely,

/RA/

James C. Shehee, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 05000321, 05000366, and 07200036 License Nos. DPR-57 and NPF-5 Enclosure:

As stated cc w/o encl: See Page 3 cc:

Edwin D. (Sonny) Dean Southern Nuclear Operating Co., Inc.

Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 Christopher Byrd Site Security Manager Southern Nuclear Operating Co., Inc.

Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 Lisa B. Hogg Fleet Security Project Manager Southern Nuclear Operating Co., Inc.

P. O. Box 1295 Birmingham, AL 35201-1295 Erin Garrison Fleet Security Project Manager Southern Nuclear Operating Co., Inc.

P. O. Box 1295 Birmingham, AL 35201-1295 Steven M. Shipman Fleet Security Project Manager Southern Nuclear Operating Co., Inc.

P. O. Box 1295 Birmingham, AL 35201-1295 ML20346A090 Entire Report: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DRS/PSB RII/DRP/PB2 RII/DRS/PSB NAME J. Justice A. Blamey J. Shehee DATE 12/10/2020 12/08/2020 12/10/2020