{{#Wiki_filter:* . - . . . . U. S. NUCLEAR REGULATORY COMMISSICN OFFICE OF INSPECTION AND ENFORCEMENT
REGION IV
IE Inspection Report No. 50-313/76-13 Docket No. 50-313 Licensee: Arkansas Power and Light Company (AP&L) License No. DPR-51 Sixth and Pine Streets Pine Bluff, Arkansas 71601 Category C Facility: Arkansas Nuclear One (ANO-1) Location: Russellville, Arkansas Type of License: PWR, Power Reactor Type of Inspection: Routine, Unannounced, Radiation Protection, and Analytical Measurements Dates of Inspection: October 6-8, 1976 s Dates of Previous Radiological Inspection: Au;ust 17-19, 1976 Inspector: i de llAb(A#) [O!O [[ ~ Blaine Murray, Radiatio pecialist 'Date.
" Accompanying Personnel: None ( / 0!A7//[. Reviewed by: i e , Glen D. Brown, Chief, Fuel Facility Date ' and Material Safety J , 8004IIo$f7
. - - - - - . -. _ -.-. .~-. . -.
. .
. . G - . -2-i S1' WARY OF FINDINGE I.
Enforcement Action ' A.
Items of Noncompliance identified by The Inspector None.
B.
Items of Noncompliance Identified by The Licensee None.
- i II.
Licensee Action on Previously Identified Enforcement Matters Two items of noncompliance were noted in IE Inspection Report No. 50-313/76-10. The licensee's corrective action was reviewed and found adequate to correct the previously identified enforcement items.
These items are considered closed.
III.
New Unresolved Items None.
IV.
Status of Previously Identified Unresolved Items , j ,76/08-1, Radiochemistrv QC Program t.
The proposed radiochemistry QC procedure has not been approved.
This item remains open.
(See DETAILS, paragraph C.2.a.)
76/04-1 Stack Monitor The status of this item was not reviewed during this inspection.
This item remains open.
(See DETAILS, paragraph C.2.b.)
' 74/14-03, Radiation Levels in Reactor Containment ' There are certain areas inside containment where radiation levels exceed design basis.
This item remains open.
(See DETAILS, parag- -h C.2.e.)
. ,, -- w, ,, , - _,, -, -..,,. - --- - - - - -. -, , - -,, - -, -, -, -.,,,. -,
. _ _ . . . - D !- -3- . 75/05-2. Air Sampler Flow Rates Air sampler flow rates have been measured.
This item is considered closed.
(See DETAILS, paragraph C.2.c.)
76/10-1. Whole Ecdy Counting Results Whole body data has been reduced into units of body burdens.
This item is considered closed.
(See DETAILS, paragraph C.2.g.)
76/10-2, Operation Checks of Constant Air Monitors A procedure has not been written that establishes an operation check frequency for Constant Air Monitors.
This item remains open.
(See DETAILS, paragraph C.2.h.)
76/10-3, Health Physics Staff Training x A formal training program has not been developed for new Health Physics personnel.
This iten remains open.
(See DETAILS, paragraph C.2.1.)
76/10-4, Plant Housekeeping The licensee has improved housekeeping conditions.
This item is considered closed.
(See DETAILS, paragraph C.2.j.)
, 76/10-5, Radiological Retraining The status of this item was not reviewed during this inspection.
This item remins open.
(See DETAILS, paragraph C.2.k.)
75/09-3, Whole Body Counter Calibration Procedures
Calibration procedures have not been approved for the whole body counting system.
This item remains open.
(See DETAILS, paragraph C.2.d.)
, i
e ,,,, ,, - - - -, - - _ _ __- ,_ _7, _
_ _.
... . _ . - . . . .-
s_- . -4-
75/05-5, Laboratory Counting Equipment Calibration Procedures Calibration procedures have not been approved for laboratory counting equipment used to analyze Health Physics air and contamination surveys.
This item remains open.
(See DETAILS, paragraph C.2.f.)
V.
Unusual Occurrences None.
, VI.
Other Significant Findings None.
VII.
Management Interview At the conclusion of the inspection, the inspection findings were discussed with the following AP&L personnel: s Mr. J. W. Anderson, Plant Superintendent Mr. C. E. Halbert, Technical Support Engineer Mr. R. G. Carrol, Health Physics Supervisor Mr. M. M. Nichols, Health Physics Foreman Mr. L. Alexander, QC Engineer The items discussed and the licensee's position with respect to these items. as applicable, follow: A.
Scope of Inspection , The inspector outlined the areas covered during the inspection.
B.
Items of Noncompliaace The inspector stated that no iteus of noncompliance were identified.
C.
Status of Previously Reported Unresolved Items The licensee provided a status report on open unresolved items.
(See DETAILS, paragraph C.2.)
D.
Plant Housekeeping The inspector noted that general plant housekeeping conditions had improved since the last inspection.
(See DETAILS, paragraph C.2.)
s - - - - _ __- - -
...._......_.. _ _ ____.._._____ _. ~. - _ _. _ _ _ _ _ _ _ - _.. _ _ _ _ _ _ _ - _ _ _ _.. _ _. - _ _ _ _ _ _ _ _ _. _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ -. - -. _. _. _ _ - - -. __ . . . I
. . ! - . e !' I. O - ' , 5- ,
. E.
Plant Safety Cormittee Meetina (PSC)
- -
Several Health Physics matters reported to the PSC were discussed.
' (See DETAILS, paragraph C.)
! i
J , q , .. l
\\ i
- O
a ! ! , , I
i , i . < , , I f t ' !- } ! - I f ! I i - i < ' . ,- t i - i ! O i . I a, ,,w-,-_ -e---w.ee-+ssw,-s-e--w-_-m _ - w erw, h me dw e= -ees w ww---- - wv m-- e* ---m-$~v.-c.+w4--, - -%_was:,ww---<---vw---+-ewwe e va-m w- + e -, - --7st+ P-- ww m e v 7* s~revme="***'"rNT
_ . U(h-6-DETAILS A.
Persons Contacted AP&L Mr. J. W. Anderson, Plant Superintendent Mr. C. H. Halbert, Technical Support Engineer Mr. R. G. Carrol, Health Physics Supervisor Mr. M. M. Nichols, Health Physics Foreman Mr. S. J. McWilliams, Planning and Scheduling Coordinator Mr. J. L. Bates, Radiochemistry Supervisor Mr. L. Alexander, QC Engineer B.
Scope of Inspection The purpose of this inspec:icn was to complete the Radiation Protection inspection that began on August 17,1976.1/ ) C.
Licensee Action on Previcusly Reported Items 1.
Items of Noncompl'.ance Corrective action for the two items of noncompliance noted in IE Inspection Report No. 50-313/76-10 was reviewed.
The licensee's corrective action was reviewed and found adequate to correct the items of noncompliance.
These items are considered closed.
' 2.
Unresolved Items a.
76/08-1, Radiochemistry QC Program This item was reported in IE Inspection Report No. 50-313/ 76-08 and involved the completion of written procedures for the QC program. A draft procedure has been completed.
, This item remain open pending approval of the draft procedure.
1/ IE Inspection Report No. 50-313/76-10 i . -. - - . . _, _. .- -
_ _ _ _ _ _ _ _ __ . .
. . , -7- . b.
76/04-1, Stack Monitor , This item was reported in IE Inspection Report No. 50-313/ 76-04 and involved designating which stack monitor system is to be used during an emergency situatien. The status of this item was not examined during this inspection. This item remains open.
c.
75/05-2, Air Sampler Flow Rates This item was reported in IE Inspection Report No. 50-313/ 75-05 and involved measuring the flow rates of various air samplers. The licensee has established flow rates for the air samplers.
This item is considered closed.
. d.
75/05-3, Calibration Procedures for Whole Body Counter This item was reported in IE Inspection Report No. 50-313/ - 75-05 and invcived the development of a written procedure for calibration of the whole body counting system. A draft procedure has been written.
This item remains open pending approval of the procedure.
e.
74/14-3. Radiation Levels Inpfde Reactor Containment This item was reported in RO Inspection Report No. 50-313/ 74-14 and involved radiation levels in containment that ' exceed design basis. Corrective 3.ction for this item is scheduled to be completed during the first refueling outage.
f.
75/05-5. Calibration Procedures for the Laboratory Counting Equipment This item tras reported in IE Inspection Report No. 50-313/ 75-05 and involved the development of a written procedure for calibration of laboratory counting equipment used to analyze Health Physics air and contamination surveys. A l draft procedure has been written.
a This item remains open pending approval of the procedure.
O , I l . . . _ . . . ... . .. . . .. _, _., _.... _ _ _... _ _.. _. _ __
. - -. - . . . m . ' -8-
! g.
76/10-1. Whole Body Counting Results This item was discussed in IE Inspection Report No. 50-313/ 76-10 and involved recording whole body counting results in unit of body burdens. Whole body raw data hava been reduced into units of body burdens.
This item is considered closed.
h.
76/10-2. Operation Checks of Constant Air Monitors l This item was discussed in IE Inspection Report No. 50-313/ 76-10 and involved routine operational checks for constant air monitors. A licensee representative stated thr.c Health Physics procedures will be modified to include routine check , of constant air monitors.
This item remains open pending approval of the proposed procedure change.
1.
76/10-3. Health Physics Staff Training i
This item was discussed in IE Inspection Report No. 50-313/ ~ 76-10 and involved the development 4f a training program i for new Health Physicists. A licensee representative ' stated that a draft program has been developed.
This item remains open pending approval of the proposed training program.
= j.
76/10-4. Plant "ouskeeping This item was discussed in ;Z Inspection Report No. 50-313/ 76-10 and involved poor housekeeping conditions.
It was noted that general plant housekeeping conditions have improved.
A licensee representative stated that it is their intention to maintain good housekeeping condie*'ns.
This item is considered closed.
' k.
76/10-5 Radiological Retraining This item was discussed in IE Insitetion Report No. 5G-313/ .! 76-10 and involved establishing a traquency for rsdiological - ' retraining. This item was not reviewed during this inspec- . tion.
This item remains open.
I l ! ! _ _ _. -.. 1.
_ _ _ _ _ _ _ _ . [ '
. _ _ _ - _ - _ -__ _____ - . . . O . -9-D.
Radioactive Materials Control The licensee's radioactive materials program was reviewed to determine compliance with: 10 CFR 20.205 10 CYR 20.203.e 10 CFR 20.203.f Technical Specification 3.12 Technical Specification 4.14 The following licensee documents and procedures were examined: Procedure H.P. 1602.29, " Radioactive Material Accountability" l Procedure H.P. 1602.34, " Leak Test of Sealed Sources" l Unsealed Source Log Sealed Source Log i Radioactive Materials Receipt Log No discrepancies were rated.
E.
Respiratory Program The licensee respiratory program was reviewed to determinc compliance with Technical Specification 6.8.
< The respiratory program is outlined in procedure H.P. 1602.03 titled: "ANO Respiratory Protection Program."
1.
Inventory
The following is an approximate respirator inventory: Tyge Quantity Full Face Canister 130 Airline Mask
SCBA
, 2.
Training Respirator training is provided to those individuals whose normal job duties require frequent access into controlled areas.
The Training Coordinator is responsible for identifying and . scheduling those person that are to receive training. The
s Health Physics staff conducts the training courses. Each training course consists of a two hour classroom lecture plus ' another two hour fitting and derostraticn period.
. _,. _ _ _ _ _. _ _ _ _ _ _ _. _, _ _ _ _ _ _ _ _ _ ., _.. _ ... .
- - - .. - . . . . -10-Training courses are given about once each quarter. A licensee representative stated that all designated personnel have received training. It was noted that material from the following docu-ments were included in the training program: ANSI Z88.2 WASH 1287 Technical Specification 6.8 l Nc discrepancies were noted.
F.
PVP/SWP Program The licensee's Radiation Work Permit (RWP) and Special Work Permit (SWP) program is outlined in H. P. Procedure 1602.04 titled: "SWP/RWP Procedure." A RWP is usually written to cover routine main-tenance activities in areas having radia tion levels of less than one Rem /hr. A RWP can cover a period up to one year.
Special Work Permits are issued for a specific job and must ce renewed if the job lasts ' longer than two weeks.
. Selected RWPs and SWPs issued between June 1, 1975, and October 6, 1976, were examined.
No discrepancies were noted.
G.
Plant Safety Committee Meetings (PSC) Plant Safety Committee meetinge minutes were reviewed for the period
between January 1, 1976, and September 13, 1976. Particular attention was given to those meetings involving Health Physics activities.
It was noted that on August 6, 1976, the Health Physics supervisor submitted a memo to the PSC for review and comments. The memo contained several examples of unsatisfactory health physics conduct by certain plant personnel. It appeared that the PSC's September 9, 1976, reply did not clearly outline proper corrective action.
The initial memo and the PSC's response were discussed during the management interview.
\\ i l ~_-l l l f ' . ---
- -,,., * - - - - -.,., -, ,,, -- ,.-,-,,y,-*:, , - -- - - - - * ~ -
. . ... _ _ _ _ _ _ _. - . ._ __ .. . ' - . . i -
)
-11-i , H.
Advanced Planning and Preparation Health Physics involvement during the planning stages of proposed maintenance work was reviewed with the Planning and Scheduling ' Coordinator. The position of Planning and Scheduling Coordinator was only recently astablished. According to the Planning and Scheduling Coordinator, copies of planned maintenance activities will be routed through the Health Physics Department in order to allee an early radiological evaluation.
I.
Reportable Occurrence Reports The following 1976 Reportable Occurrence reports having Health Physics significance were aramined: 1.
50-313/76-6, " Fuel Handling Area Ventilation System," dated May 5, 1976.
The above report involved a wording change for Technical Specification 3.15.
2.
50-313/76-2, " Control Room Ventilation System," dated May 6, 1976.
i i The above report involved the failure of the ventilation system to close in three seconds as required in FSAR IV, page 9.49.
i l Corrective action completed.
3.
50-313/76-11. " Overflow of Sodium Thiosulfate Tank" dated . June 12, 1976.
, The above report involved a 9500 gallon overflow containing 262 aci.
Corrective action completed.
4.
50-313/76-9, " Control Room Emergency Ventilation System" dated July 22, 1976.
- i The above item involved a surveillance test that did not meet the requirements of Technical Specification 4.10.
Corrective action completed.
O l , . - .-. ..,, - ,, - -.. _ _ -, _. - - -. - - - - - , _, - - , -, -, - -, - - - - - - _ _ - - - - -., - -. - - -
. ._ ._ . _ _ _. _ _ _ _ - . . . -12- ' 5.
50-313/76-1, " Quarterly Liquid Release of More Than 2.5 curies," dated August 14, 1976.
The above report was made as required by Technical Specification 2.4.1.2.
J.
Analytical Measurements Verification measurements were performed on the following samples: 1.
Liquid waste 2.
Gaseous waste , 3.
Stack particulate filter 4.
Stack charcoal filler The verification tests consist of comparing measurements made by the licensee and NRC's reference laboratory, Idaho Health Services Laboratory (IHSL).
IHSL's measurements are referenced to the National Bureau of Standards by laboratory intercomparisons.
Verification comparisons are only made for those nuclides identiited by IHSL as being present in concentrations greater than 10% of the respactive MPC's for liquid and gas samples.
Stack charcoal acl particulate filter comparisons are based on total activity per sample.
Attachment No. 1 contains the criteria used to compare results.
. The following table shows the comparisons.
Liquid (Monitor Tank T-16, Collected July 23, 1976) a.
Nuclide NRC Measurement ANO-1 Measurement Decision Gross Beta 3.33!0.07E-3 uC1/ml 3.07E-3 uCi/ml Agreement 3U 1.12 0.02E-2 uCi/mi 1.31E-2 uCi/mi Agreement 57Co 3.410.7E-6 uC1/mi 1.10E-6 uCi/ml Disagreement 131I 5.7 IE-5 uC1/mi 6.52E-5 uC1/mi Agreement 134Cs 8.2IO.2E-4 uCi/ml 7.69E-4 uCi/mi Agreement 137Cs 2.69 0.08E-3 uCi/ml 2.46E-3 uCi/mi Agreement 58 o 2.76 0.08E-4 uCi/ml 2.67E-4 uCi/ml Agreement C 54Mn 5.7 0.2E-5 uC1/ml 5.39E-5 uCi/mi Agreement 110 mag 6.7 0.2E-5 uC1/ml 6.57E-5 uC1/ml Agreement 59,
1,9 0.8E-6 uCi/mi 1.39E-6 uCi/mi Agreement
, 60Co 3.610.1E-5uCi/ml 3.45E-5 uC1/mi Agreement G . - - ~... .. -. .,..,, _ -,....,, ..,.,, ~n . -., _, - -.e ,._--
v .,
. . s . -13-b.
Cas (Waste Gas Decay Tank T-18, Collected July 22, 1976) Nuclide NRC Measurement ANO-1 Measurement Decision 133 e 0.08E-1 uCi/cc 3.81E-1 uCi/cc Agreement 133mXe 2.71+f0.25E-3uC1/cc X 2.23 1.77E-3 uCi/cc Agreement
3.5!0.2E-3 uCi/cc 3.21E-3 uCi/cc Agreement Kr c.
Stack Particulate Filter (Collected July 22, 1976) Nuclide concentrations identified by IHSL were less than statistical reliability limits. No comparison made.
d.
Charcoal Filters (Collected July 22, 1976) No. 1 Nuclide NRC Measurement ANO-1 Measurement Decision 131I 9.24!0.4E-4 uCi/ sample 1.19E-3 uCi/ sample Agreement No. 2 O Nuclide NRC Measurement ANO-1 Measurement Decision 137Cs 3.7710.7E-5 uC1/ sample (Not identified) Disagreement .:g
e . -
. _ _ _ _ . . . , , ATTACEMENT NO. 1 . , Criteria for Comparing Analytical Measurements The following is the criteria used in comparing the results of capability tests and verification measurements. The criteria are based on an empirical relationship established through prior experience and this program's analyt-i ical. requirements.
In these criteria, the judgement limits vary in relation to the comparison of the resolution.
Resolution = NRC Value NRC Uncertainly Ratio = Licensee Value j NRC Value ' Comparisons are made by first determining the resolution and then reading across the same line to the corresponding ratio. The following table shows the acceptance values.
l RESOLUTION RATIO Possible Possible Agreenent Agreement A Agreement B .
0.4 - 2.5 0.3 - 3.0 No comparison 4-7 0.5 - 2.0 0.4 - 2.5 0.3 - 3.0 8 - 15 0.6 - 1.66 0.5 - 2.0 0.4 - 2.5 16 - 50 0.75 - 1.33 0.6 - 1.66 0.5 - 2.0 51 - 200 0.80 - 1.25 0.75 - 1.33 0.6 - 1.66 200 0.85 - 1.1E 0.80 - 1.25 0.75 - 1.33 "A" criteris are applied to the following analyses: ,
Gamma Spectrometry where principal gamma energy u sed for identification is greater than 250 Kev.
I i Tritiue analyses of liquid samples.
j Iodine on adsorbers.
, "B" criteria are applied to the following analyses: Gamma Spectrometry where principal garna energy used for identification is less than 250 Kev.
89Sr and 90 r Determinations.
S Gross Beta where samples are counted on the same date using the same . reference nuclide.
-. - - - }}