rch 26, 2008

SUBJECT:

KEWAUNEE POWER STATION NRC SECURITY TEMPORARY INSTRUCTION 2201/002 INSPECTION REPORT 05000305/2008403(DRS)

Dear Mr. Christian:

On February 22, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a temporary instruction inspection at your Kewaunee Power Station. The inspection covered the transition from a contract to a proprietary security force. The enclosed inspection report documents the inspection results, which were discussed on February 22, 2008, with Mr. M. Crist and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-305 License No. DPR-43 Nonpublic Enclosure: Inspection Report 05000305/2008403(DRS)

w/Attachment: Supplemental Information cc w/encl: D. Riffle, NSIR/DSO/DDSO cc w/o encl: S. Scace, Site Vice President T. Webb, Director, Nuclear Safety and Licensing C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin