December 3, 2008
SUBJECT:
KEWAUNEE POWER STATION
TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000305/2008006(DRS)
Dear Mr. Christian:
On November 21, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Kewaunee Power Station. The enclosed report documents the results of the inspection, which were discussed on November 21, 2008, with Mr. S. Scace and other members of your staff.
The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commission=s rules and regulations, and with the conditions of your operating licenses.
Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.
Based on the results of this inspection, no findings of significance were identified. The team concluded that, in general, you had implemented the Site Specific B.5.b Phase 2 and 3 Mitigating Strategies as described in your submittals and the associated Safety Evaluation Report.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Enclosures Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety
Docket No. 50-305 License No. DPR-43
Nonpublic Enclosure: Inspection Report 05000305/2008006(DRS)
w/Attachment: Supplemental Information
cc w/encl:
D. Nelson, NRR/DPR/PSPB
E. Bowman, NRR/DPR/PSPB
cc w/o encl:
S. Scace, Site Vice President
M. Wilson, Director, Nuclear Safety and Licensing
C. Funderburk, Director, Nuclear Licensing and
Operations Support
T. Breene, Manager, Nuclear Licensing
L. Cuoco, Senior Counsel
D. Zellner, Chairman, Town of Carlton
J. Kitsembel, Public Service Commission of Wisconsin
P. Schmidt, State Liaison Officer