March 11, 2025
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR PEACH BOTTOM ATOMIC POWER
STATION, UNITS 2 AND 3 (REPORTS 05000277/2024006 AND
Dear David Rhoades:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2024, through December 31, 2024. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Peach Bottom, Units 2 and 3, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e.,
Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2026.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. In addition to baseline inspections, the NRC plans to conduct aninspection ofyour modification of instrumentation and control systems to digitalin accordance with Inspection Procedure 52003, Digital Instrumentation and Control Modification Inspection.Thespecific schedule to be used for thisinspection is being developed by NRC staffto coincide with specific milestonesand activitiesin your project plan. NRC staff willcommunicate the specific schedulewithyouas it is identified.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 610-337-6916 with any questions you have regarding this letter.
Sincerely, Sarah H. Elkhiamy, Chief Projects Branch 4 Division of Operating Reactor Safety
Docket Nos. 05000277 and 05000278 License Nos. DPR-44 and DPR-56
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
SARAH ELKHIAMY Digitally signed by SARAH ELKHIAMY Date: 2025.03.11 11:07:59 -04'00'
SUNSI Review
X Non-Sensitive Sensitive
X Publicly Available Non-Publicly Available
OFFICE RI/DORS RI/DORS
NAME SHaney SElkhiamy
DATE 3/6/2025 3/7/2025
Site Inspection Activity Plan Peach Bottom 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count Material Control and Accounting - Peach Bottom
2,3 2/3/2025 2/7/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
EP Program Inspection - Peach Bottom
2,3 2/24/2025 2/28/2025 IP 71114.02 000717 Alert and Notification System Testing 2,3 2/24/2025 2/28/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2,3 2/24/2025 2/28/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2,3 2/24/2025 2/28/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness 2,3 2/24/2025 2/28/2025 IP 71151 001397 Performance Indicator Verification PB Requal Inspection with P/F Results
2,3 3/24/2025 3/28/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 2,3 3/24/2025 3/28/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Commercial Grade Dedication - Peach Bottom
2,3 4/21/2025 4/25/2025 IP 71111.21N.03 001808 Commercial Grade Dedication 2,3 5/5/2025 5/9/2025 IP 71111.21N.03 001808 Commercial Grade Dedication 2025 Peach Bottom Initial Operator Licensing Exam
2,3 4/21/2025 4/25/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
2,3 5/19/2025 5/23/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
RP - 71124.05 Rad. Instruments
2,3 5/5/2025 5/9/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation RP - SAFSTOR - PBU1
1 5/12/2025 5/16/2025 IP 37801 000009 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors
5/12/2025 5/16/2025 IP 40801 000010 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors
5/12/2025 5/16/2025 IP 64704 000018 Fire Protection Program at Permanently Shutdown Reactors
5/12/2025 5/16/2025 IP 71801 000023 Decommissioning Performance And Status Review At Permanently Suhutdown Reactors
5/12/2025 5/16/2025 IP 83750 000035 Occupational Radiation Exposure at Permanently Shutdown Reactors
5/12/2025 5/16/2025 IP 84750 000040 Radioactive Waste Treatment and Effluent And Environmental Monitoring
5/12/2025 5/16/2025 IP 86750 000045 Solid Radioactive Waste Management And Transportation Of Radioactive Materials Access Control, Protective Strategy, TSR, SPR, PIs - PB
2,3 5/19/2025 5/23/2025 IP 71130.02 000734 Access Control 2,3 5/19/2025 5/23/2025 IP 71130.05 000737 Protective Strategy Evaluation Prepared on 2/18/2025 8:32:00 PM 1 of 3
Site Inspection Activity Plan 2,3 5/19/2025 5/23/2025 IP 71130.09 001656 Security Plan Changes 2,3 5/19/2025 5/23/2025 IP 71130.14 000743 Review of Power Reactor Target Sets 2,3 5/19/2025 5/23/2025 IP 71151 001338 Performance Indicator Verification PI&R Biennial Team Inspection - Peach Bottom
2,3 9/8/2025 9/12/2025 IP 71152B 000747 Problem Identification and Resolution 2,3 9/22/2025 9/26/2025 IP 71152B 000747 Problem Identification and Resolution RP -71124.08 Rad Waste and Part 37
2,3 9/15/2025 9/19/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation RP - 71124.06 RETS
2,3 10/6/2025 10/10/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Inservice Inspection - Peach Bottom Unit 3
3 10/13/2025 10/24/2025 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
3 10/27/2025 10/31/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls ISFSI - IP 60859 License Renewal, Peach Bottom
2,3 11/3/2025 11/4/2025 IP 60859 Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection RP-71151 PI Verification (Remote)
2,3 11/17/2025 11/19/2025 IP 71151 000746 Performance Indicator Verification Access Control, AA, FFD, Sec Plan Review, PI, ISFSI - PB
2,3 1/5/2026 1/9/2026 IP 71130.01 000733 Access Authorization 2,3 1/5/2026 1/9/2026 IP 71130.02 000734 Access Control 2,3 1/5/2026 1/9/2026 IP 71130.08 000740 Fitness-For-Duty Program 2,3 1/5/2026 1/9/2026 IP 71130.09 001656 Security Plan Changes 2,3 1/5/2026 1/9/2026 IP 71151 001338 Performance Indicator Verification 2,3 1/5/2026 1/9/2026 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations 2,3 2/23/2026 2/27/2026 IP 71130.01 000733 Access Authorization 2,3 2/23/2026 2/27/2026 IP 71130.08 000740 Fitness-For-Duty Program Age Related Degradation - Peach Bottom
2,3 1/26/2026 1/30/2026 IP 71111.21N.04 001832 Age-Related Degradation 2,3 2/2/2026 2/6/2026 IP 71111.21N.04 001832 Age-Related Degradation 2,3 2/9/2026 2/13/2026 IP 71111.21N.04 001832 Age-Related Degradation Cyber Security - Peach Bottom
2,3 3/16/2026 3/20/2026 IP 71130.10 000741 Cybersecurity 2026 Peach Bottom Initial Operator Licensing Exam
Prepared on 2/18/2025 8:32:00 PM 2 of 3
Site Inspection Activity Plan 2,3 4/13/2026 4/17/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
2,3 5/11/2026 5/15/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
RP - 71124.03 Resp. Protection and 71124.04 Occupational Dose
2,3 4/20/2026 4/24/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 4/20/2026 4/24/2026 IP 71124.04 000728 Occupational Dose Assessment EP Exercise Inspection - Peach Bottom
2,3 4/27/2026 5/1/2026 IP 71114.01 000716 Exercise Evaluation 2,3 4/27/2026 5/1/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2,3 4/27/2026 5/1/2026 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - PB
2,3 5/11/2026 5/15/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2,3 6/1/2026 6/5/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing RP - SAFSTOR - PB U1
1 5/25/2026 5/29/2026 IP 37801 000009 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors
5/25/2026 5/29/2026 IP 40801 000010 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors
5/25/2026 5/29/2026 IP 64704 000018 Fire Protection Program at Permanently Shutdown Reactors
5/25/2026 5/29/2026 IP 71801 000023 Decommissioning Performance And Status Review At Permanently Suhutdown Reactors
5/25/2026 5/29/2026 IP 83750 000035 Occupational Radiation Exposure at Permanently Shutdown Reactors
5/25/2026 5/29/2026 IP 84750 000040 Radioactive Waste Treatment and Effluent And Environmental Monitoring
5/25/2026 5/29/2026 IP 86750 000045 Solid Radioactive Waste Management And Transportation Of Radioactive Materials RP - 71124.07 REMP
2,3 9/14/2026 9/18/2026 IP 71124.07 000731 Radiological Environmental Monitoring Program Inservice Inspection - Peach Bottom Unit 2
2 10/19/2026 10/23/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
2 10/26/2026 10/30/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls RP - 71151 PIV
2,3 11/16/2026 11/18/2026 IP 71151 000746 Performance Indicator Verification Prepared on 2/18/2025 8:32:00 PM 3 of 3