IR 05000272/2025005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2025005 and 05000311/2025005)
ML25239B581
Person / Time
Site: Salem  
Issue date: 08/28/2025
From: Nicole Warnek
Division of Operating Reactors
To: Mcfeaters C
Public Service Enterprise Group
References
IR 2025005
Download: ML25239B581 (1)


Text

August 28, 2025

SUBJECT:

UPDATED INSPECTION PLAN FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (REPORT 05000272/2025005 AND

05000311/2025005)

Dear Charles McFeaters:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Salem Nuclear Generating Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the Reactor Oversight Process (ROP) is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.

In addition to baseline inspections, the NRC conducted Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, Phase 4 at your facility earlier this month.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-6954 with any questions you have regarding this letter.

Sincerely, Nicole S. Warnek, Chief Projects Branch 3 Division of Operating Reactor Safety

Docket Nos. 05000272 and 05000311 License Nos. DPR-70 and DPR-75

Enclosure:

Salem Inspection Plan

cc w/encl: Distribution via ListServ NICOLE WARNEK Digitally signed by NICOLE WARNEK Date: 2025.08.28 06:46:37 -04'00'

ML25239B581

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DORS RI/DORS

NAME JBresson NWarnek

DATE 8/27/2025 8/27/2025

Site Inspection Activity Plan Salem 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count RP REMP 71124.07 SAL

1,2 7/7/2025 7/7/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program RP REMP 71124.07 Completion SAL

1,2 7/14/2025 7/17/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program License Renewal Phase 4 - Salem Units 1 & 2

1,2 8/11/2025 8/15/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Salem Requal Inspection with P/F Results

1,2 9/14/2025 9/19/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP Instrumentation 71124.05 SAL

1,2 11/10/2025 11/20/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation Age Related Degradation Inspection - Salem

1,2 11/17/2025 11/21/2025 IP 71111.21N.04 001832 Age-Related Degradation 1,2 11/24/2025 11/28/2025 IP 71111.21N.04 001832 Age-Related Degradation 1,2 12/1/2025 12/5/2025 IP 71111.21N.04 001832 Age-Related Degradation RP PI Verification 71151 SAL

1,2 11/17/2025 11/21/2025 IP 71151 000746 Performance Indicator Verification Commercial Grade Dedication - Salem

1,2 1/12/2026 1/16/2026 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2 1/26/2026 1/30/2026 IP 71111.21N.03 001808 Commercial Grade Dedication Sec - Access Control, Training, SPR, PI Verification - Salem

1,2 3/9/2026 3/13/2026 IP 71130.02 000734 Access Control 1,2 3/9/2026 3/13/2026 IP 71130.07 000739 Security Training 1,2 3/9/2026 3/13/2026 IP 71130.09 001656 Security Plan Changes 1,2 3/9/2026 3/13/2026 IP 71151 001338 Performance Indicator Verification Inservice Inspection - Salem Unit 2

2 4/13/2026 4/24/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Cyber Security - Salem

1,2 6/8/2026 6/12/2026 IP 71130.10 000741 Cybersecurity 1,2 6/22/2026 6/26/2026 IP 71130.10 000741 Cybersecurity 2026 Salem Initial Operator Licensing Exam

1,2 6/8/2026 6/12/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 7/13/2026 7/17/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Prepared on 7/28/2025 2:07:25 PM 1 of 2

Site Inspection Activity Plan FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - SL/HC

1,2 8/3/2026 8/7/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 8/24/2026 8/28/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Material Control and Accounting - Salem

1,2 9/14/2026 9/18/2026 IP 71130.11 000742 Material Control and Accounting (MC&A)

Inservice Inspection - Salem Unit 1

1 10/12/2026 10/23/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

EP Exercise Inspection - Salem

1,2 11/16/2026 11/20/2026 IP 71114.01 000716 Exercise Evaluation 1,2 11/16/2026 11/20/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 11/16/2026 11/20/2026 IP 71151 001397 Performance Indicator Verification RP 71151 PI Verification - Salem

1,2 11/16/2026 11/19/2026 IP 71151 000746 Performance Indicator Verification Sec - AA, Access Control, Equipment Testing and Maintenance, FFD, SPR, PI - SHC

1,2 2/1/2027 2/5/2027 IP 71130.01 000733 Access Authorization 1,2 2/1/2027 2/5/2027 IP 71130.02 000734 Access Control 1,2 2/1/2027 2/5/2027 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 2/1/2027 2/5/2027 IP 71130.08 000740 Fitness-For-Duty Program 1,2 2/1/2027 2/5/2027 IP 71130.09 001656 Security Plan Changes 1,2 2/1/2027 2/5/2027 IP 71151 001338 Performance Indicator Verification EP Program Inspection - Salem

1,2 3/22/2027 3/26/2027 IP 71114.02 000717 Alert and Notification System Testing 1,2 3/22/2027 3/26/2027 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 3/22/2027 3/26/2027 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 3/22/2027 3/26/2027 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 3/22/2027 3/26/2027 IP 71151 001397 Performance Indicator Verification RP 71124.08 RM Handling/Storage/Trans Salem

1,2 4/12/2027 4/16/2027 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Comprehensive Engineering Team Inspection

1,2 5/3/2027 5/7/2027 IP 71111.21M 000713 Comprehensive Engineering Team Inspection 1,2 5/17/2027 5/21/2027 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Prepared on 7/28/2025 2:07:25 PM 2 of 2