MONTHYEARIR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24088A3052024-03-25025 March 2024 Fws to NRC, Agreement with Nlaa Determination for Tricolored Bat for Oconee Lr 05000270/LER-2023-001, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee2024-02-29029 February 2024 Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee 05000287/LER-2023-002, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications2024-02-29029 February 2024 Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML24045A3042024-02-16016 February 2024 Ltr. to Lisa M. Collins Chief the Wassamasaw Tribe of Varnertown Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A0052024-02-16016 February 2024 Ltr. to Brian Harris, Chief, Catawba Indian Nation; Re., Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2942024-02-16016 February 2024 Ltr. to Carolyn Chavis Bolton Chief Pee Dee Indian Nation of Upper Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2962024-02-16016 February 2024 Ltr. to David Hill Principal Chief Muscogee Creek Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2992024-02-16016 February 2024 Ltr. to Eric Pratt Chief the Santee Indian Organization Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3082024-02-16016 February 2024 Ltr. to Ralph Oxendine Chief Sumter Tribe of Cheraw Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3022024-02-16016 February 2024 Ltr. to Joe Bunch United Keetoowah Band of Cherokee Indians in Ok Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3072024-02-16016 February 2024 Ltr. to Pete Parr Chief Pee Dee Indian Tribe Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3032024-02-16016 February 2024 Ltr. to John Creel Chief Edisto Natchez-Kusso Tribe of Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3012024-02-16016 February 2024 Ltr. to Harold Hatcher Chief the Waccamaw Indian People Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2952024-02-16016 February 2024 Ltr. to Chuck Hoskin, Jr, Principal Chief Cherokee Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2972024-02-16016 February 2024 Ltr. to Dexter Sharp Chief Piedmont American Indian Assoc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3052024-02-16016 February 2024 Ltr. to Louis Chavis Chief Beaver Creek Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3062024-02-16016 February 2024 Ltr. to Michell Hicks, Principal Chief Eastern Band of Cherokee Re Oconee Nuclear Station Units 1,2, and 3 Section 106 ML24019A1442024-02-13013 February 2024 Letter to Reid Nelson, Executive Director, Achp; Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24011A1532024-02-13013 February 2024 Letter to Tracy Watson EPA-Oconee Nuclear Sta, Unites 1, 2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants ML24030A5212024-02-13013 February 2024 Letter to Elizabeth Johnson, Director, SHPO; Re Oconee Nuclear Stations Units 1, 2, and 3 Section 106 ML24011A1482024-02-13013 February 2024 Letter to Steven M. Snider-Oconee Nuclear Sta, Unites 1,2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants IR 05000269/20230042024-02-13013 February 2024 Integrated Inspection Report 05000269/2023004, 05000270/2023004, and 05000287/2023004; and Inspection Report 07200040/2023001 ML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staff’S Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds 2024-08-26
[Table view] |
Inspection Report - Oconee - 2011001 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION rch 4, 2011
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 (REPORT 05000269/2011001, 05000270/2011001, AND 05000287/2011001)
Dear Mr. Gillespie:
On February 9, 2011, the NRC completed its end-of-cycle performance review of Oconee Nuclear Station (ONS) Units 1, 2, and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2010, through December 31, 2010. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined the performance at ONS Units 1, 2, and 3 for the most recent quarter was within the Degraded Cornerstone Column of the NRCs Reactor Oversight Process (ROP)
Action Matrix based on one inspection finding being classified as having substantial safety significance (Yellow) in the Mitigating Systems Cornerstone related to the failure to ensure the Standby Shutdown Facility (SSF) Reactor Coolant Makeup (RCM) subsystem for all three units remained operable as required by Technical Specifications. Additionally, ONS Units 2 and 3 had one inspection finding classified as having low to moderate safety significance (White) in the Mitigating Systems Cornerstone related to a failure to identify and correct ONS Unit 2 and Unit 3 SSF RCM letdown line degradation in a timely manner after similar degradation was identified on ONS Unit 1. On December 17, 2010, the NRC completed a supplemental inspection in accordance with Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area. Based on the results of this inspection, the NRC determined that your staff adequately addressed the causes for both of these findings. Therefore, both findings are considered closed and ONS Units 1, 2, and 3 transitioned to the Licensee Response Column of the NRCs ROP Action Matrix on January 1, 2011.
The NRC identifies substantive cross-cutting issues (SCCIs) to communicate a concern with licensee performance in a cross-cutting area and to encourage the licensee to take appropriate actions before more significant performance issues emerge. The NRC identified a cross-cutting theme in the Work Practices component of the Human Performance cross-cutting area.
DEC 2 Specifically, four NRC-identified violations were identified as having the cross-cutting aspect of procedure use (H.4.(b)). While we recognize that the high level of activities at your site may be a contributor to this theme, the NRC determined that an SCCI exists because the NRC has a concern with your staffs scope of effort and progress in addressing the cross-cutting theme.
Your staff previously identified procedure use and adherence cross-cutting area as needing improvement in 2007, 2008, and 2009. However, your staffs efforts to correct this cross-cutting area were narrowly focused and ineffective as demonstrated by the four NRC-identified findings related to this cross-cutting aspect. The SCCI will remain open until the NRC has confidence that your corrective actions are sufficient, based in part on a reduction in the number of findings below the SCCI threshold. The NRC will monitor your staffs effort and progress in addressing the SCCI by a focused problem identification annual sample to evaluate the planned corrective actions and a review during the biennial Problem Identification and Resolution inspection to verify the effectiveness of the corrective actions.
The enclosed inspection plan lists the inspections scheduled through June 30, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. We also plan on conducting several infrequently performed inspections which include: Inspection Procedure 52003, Digital Instrumentation and Control Modification Inspection; initial reactor operator licensing examinations; and Temporary Instruction 2515/179, Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in the National Source Tracking System Pursuant to Title 10, Code of Federal Regulations, Part 20.2207 (10 CFR 20.2207). Additionally, the staff will continue its review of issues associated with fire, tornado, and high energy line break mitigation. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Jonathan Bartley at (404) 997-4607 with any questions you have regarding this letter.
Sincerely,
/RA/
Victor M. McCree Regional Administrator Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55 cc w/Encl: (See page 3)
Enclosure: Oconee Inspection/Activity Plan (03/01/2011 - 6/30/2012)
_ML110630322___ G SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP RII:ORA RII:ORA SIGNATURE CWR /RA/ JHB /RA/ RXC /RA/ LDW /RA/ VMM /RA/
NAME CRapp JBartley RCroteau LWert VMcCree DATE 03/01/2011 03/01/2011 03/02/2011 02/28/2011 03/03/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
DEC 3 cc w/encl: County Supervisor of Oconee County Division of Radiological Health 415 S. Pine Street TN Dept. of Environment & Conservation Walhalla, SC 29691-2145 Electronic Mail Distribution W. Lee Cox, III David A. Baxter Section Chief Vice President, Nuclear Engineering Radiation Protection Section Duke Energy Carolinas, LLC N.C. Department of Environmental Electronic Mail Distribution Commerce & Natural Resources Electronic Mail Distribution Kent Alter Regulatory Compliance Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution Sandra Threatt, Manager Nuclear Response and Emergency Environmental Surveillance Bureau of Land and Waste Management Department of Health and Environmental Control Electronic Mail Distribution Scott L. Batson Station Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution Terry L. Patterson Safety Assurance Manager Duke Energy Carolinas, LLC Electronic Mail Distribution Charles Brinkman Director Washington Operations Westinghouse Electric Company, LLC Electronic Mail Distribution Tom D. Ray Engineering Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
DEC 4 Letter to T. Preston Gillespie, Jr. from Victor M. McCree dated March 4, 2011 SUBJECT: ANNUAL ASSESSMENT LETTER FOR OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 (REPORT 05000269/2011001, 05000270/2011001, AND 05000287/2011001)
Distribution w/encl:
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMOconee Resource ROP Reports Institute of Nuclear Power Operations (INPO)