IR 05000244/2016403; 03/07/2016 - 03/11/2016; R. E. Ginna Nuclear Power Plant; Security Training Letter Only
ML16097A116
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/05/2016
From: Raymond Mckinley
Plant Support Branch 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2016403 IR 2016403
Download: ML16097A116 (4)


Text

pril 5, 2016

SUBJECT:

R. E. GINNA NUCLEAR POWER PLANT, - NRC BASELINE SECURITY INSPECTION REPORT 05000244/2016403

Dear Mr. Hanson:

On March 11, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your R. E. Ginna Nuclear Power Plant. On March 11, 2016, the NRC inspectors discussed the results of this inspection with Mr. Joseph Pacher, Site Vice President, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.

NRC inspectors documented one finding of very low security significance (Green) in this report.

This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest this violation or its significance, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555 0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC resident inspector at the Ginna Nuclear Power Plant.

One cross-cutting aspect was assigned to the finding in the area of Human Performance, Training, because Exelon failed to provide training and ensure knowledge transfer to maintain a knowledgeable workforce. (H.9). If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I; and the NRC resident inspector at the Ginna Nuclear Power Plant.

Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from Enclosure, the transmittal documented is decontrolled. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR §2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's ADAMS.

If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information -

Withhold From Public Disclosure Under 10 CFR §2.390 in accordance with 10 CFR

§2.390(d)(1) and follow the instructions for withholding in 10 CFR §2.390(b)(1). In accordance with 10 CFR §2.390(b) (1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,

/RA/

Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-244 License No. DPR-18 Enclosure:

Inspection Report No. 05000244/2016403 w/Attachment: Supplemental Information cc w/o encl; w/o OUO-SRI: Distribution via ListServ cc w/encl; w/OUO-SRI:

J. Scalzo, Director of Security A. Peterson, State Liaison Office Designee, NY State Energy, Research & Development Authority