IR 05000206/1991008

From kanterella
Jump to navigation Jump to search
Mgt Meeting Repts 50-206/91-08,50-361/91-08 & 50-362/91-08 on 910301.Major Areas Discussed:Unit 1 Design Basis Documents,Single Failure Analysis,Restart issues,on-line Maint & Implications & mid-loop Operations.Viewgraphs Encl
ML13329A153
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 03/29/1991
From: Johnson P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML13329A152 List:
References
50-206-91-08-MM, 50-206-91-8-MM, 50-361-91-08, 50-361-91-8, 50-362-91-08, 50-362-91-8, NUDOCS 9104170062
Download: ML13329A153 (51)


Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION V

Report No /91-08, 50-361/91-08, 50-362/91-08 Docket No, 50-361, 50-362 License No DPR-13, NPF-10, NPF-15 Licensee:

Southern California Edison Company Irvine Operations Center 23 Parker Street Irvine, California 92718

-

Facility Name:

San Onofre Units 1, 2, and 3 Meeting at:

Region V Office, Walnut Creek, CA Conference Date:

March 1, 1991 Prepared by:

David L. Proulx, Project Inspector Approved By:

~J S329-9RI P. H. Johnson, Chief Date Signed Reactor Projects Section 3 Summary A management meeting was held on March 1, 1991 to discuss Unit 1 design basis documents, single failure analysis, and restart issues; on-line maintenance and ilts implications; mid-loop operations; and the results of the recent NRC setpoint methodology team inspectio PDR ADOCK 05000206 G

PDR

DETAILS 1. Meeting Participants

,uom rU-Q.aLcuY Commission J. B. Martin, Regional Administrator R. P. Zimmerman, Director, Division of Reactor Safety and Projects S. A. Richards, Chief, Reactor Projects Branch D. F. Kirsch, Chief, Reactor Safety Branch P. H. Johnson, Chief, Reactor Projects Section 3 C. W. Caldwell, Senior Resident Inspector C. W. Townsend, Resident Inspector, San Onofre D. G. Acker, Reactor Inspector D. L. Proulx, Project Inspector Southern California Edison Company H. B. Ray, Senior Vice President, Nuclear B. Katz, Manager, Nuclear Oversight J. T. Reilly, Manager, Nuclear Engineering and Construction R. W. Waldo, Operations Manager M. P. Short, Technical Manager K. L. Johnson, Controls Discipline Manager F. R. Nandy, Manager, Nuclear Licensing L. D. Brevig, Supervisor, Onsite Nuclear Licensing 2. Background On March 1, 1991, a management meeting was held at the Region V office in Walnut Creek, California. The purpose of this meeting was to discuss Unit 1 design basis documents, single failure analysis, and restart issues; on-line maintenance and its implications; mid-loop operations; and the results of the recent NRC setpoint methodology team inspectio The meeting was convened at 12:30 p.m. A copy of slides used during the licensee's presentations is enclose. Introduction Mr. Zimmerman opened the meeting by explaining the purpose of the meeting and went over the agenda briefly. He also stated that the issues to be discussed during the meeting were of interest to the NRC and expressed a desire for open dialogue between the NRC and the licensee on the issue. Discussion of Unit 1 Design Basis Documents (DBD)

Mr. Reilly opened the licensee's presentation with a discussion of SCE's progress in updating the design basis documentation for Unit 1. He stated that six DBD updates had been completed for Unit 1 in 1990 (Nuclear Instruments, Nitrogen System, Load Sequencing, Component Cooling Water, Salt Water Cooling, and Environmental Qualification).

-2 The discussion then focused on SCE's efforts to update the DBD for the Safety Injection System (SIS).

Mr. Reilly summarized the progress made to review the SI He noted that SCE had reperformed the small break loss of coolant accident (LOCA) analysis and had found that the original analysis was very conservative. The calculated peak clad temperature fell from about 2150 degrees F under the old analysis to about 1450 degrees F with the new analysis. Mr. Reilly stated that the completion of the SIS DBD effort was coordinated with system modifications scheduled for the cycle 12 refueling outage, however SCE considered that their review of the system was sufficiently complete to provide a high level of assurance that no significant deficiencies remain undetecte Mr. Reilly completed the discussion in this area by outlining SCE's schedule for the completion of other DBD. Discussion of Unit 1 Main Feed Pump (MFP) Restart Delay

.

SCE had recently identified a timing delay in the restart of the MFPs under certain accident conditions. The MFPs also function as the safety injection pump Mr. Reilly stated that the analyses performed for the Unit 1 accidents that the MFP delay could affect consisted of (1) a simultaneous break and loss of power (LOP) for a large break loss of coolant accident (LOCA), (2) a loss of power at the time of reactor trip, and (3) a simultaneous break and LOP for a small break LOC Mr. Ray stated that the 11-second time delay associated with the restart of the MFP's was a known factor. Mr. Ray's opinion was that SCE's error was in not considering the order in which the LOP or the SIS actuation could occu Mr. Caldwell then asked the licensee to explain what SCE considered to be the worst case scenario for Unit Mr. Ray explained that the actual worst case accident consisted of a break with SIS actuation, with-the loss of power occurring at just the proper time frame (including all time delays) which gives the worst-case results. He referred to this scenario as a SIS with a "smart LOP". He contended that although the SIS with a smart LOP had the worst outcome of any possible situation, SCE is not required to analyze for this type of accident. Mr. Ray then stated that SCE considers that the intent of the regulation for the SIS/LOP scenarios involves a loss of power that is dependent upon other perturbations that logically follow in the sequence of events. He summarized his discussion by stating that SCE had made the necessary design change to eliminate this problem and that SCE has a high level of confidence that no significant weaknesses exist in their analyses at this time that could hinder Unit 1 restar Mr. Townsend then commented that the analysis takes credit for the charging pumps during the injection phase of the design basis acciden He perceived this as an apparent weakness in SCE's DBD because the charging pumps have lockout relays that prevent restarting of these pumps until the logic is reset. Mr. Reilly responded by stating that this was true, but the analysis only takes credit for the charging pumps

-3 after the logic is reset. He further added that the charging pump lockout relays were being remove Mr. Pay then summarized some preliminary results of the Main Steam Line Break analysis, and stated that the final results should be available for the NRC in March 199 Mr. Martin then concluded the discussion in this area by expressing general satisfaction with the licensee's efforts to update DBDs and to find-and correct engineering problems. Mr. Martin questioned whether the licensee's efforts to update their understanding of the plant design was of value and Mr. Reilly indicated that it wa. Discussion of Single Failure Analysis for Unit I Mr. Reilly discussed the licensee's efforts in completing the Single Failure Analysis (SFA) for Unit 1. He stated that SCE had noted nine modifications that needed to be performed as a result of the SFA, and that eight of these were already complete. The remaining modification (dealing with Vital Bus Transfers) will be completed during the cycle 12 refueling outage. He added that once all of the modifications are complete, there will be a 2% decrease in the calculated core melt frequenc Mr. Caldwell agreed that the Unit 1 SFA was a significant effort, but he felt that some items used in contemporary SFAs were not considered by SCE in their analysis. He then stated that check valves and relief valves are considered by the industry to be active components, and that SCE's SFA may not be valid without considering these component Mr. Ray replied that they considered check valves and relief valves to be passive components because SCE assumed that Unit 1 was licensed by an analysis that considered these valves to be passiv Mr. Caldwell pointed out that the modification that installed valve 1100-E downstream of the Volume Control Tank (VCT) left the charging system in a state in which it still has the potential for a common mode failure. He stated that the two VCT discharge valves limit shut rather than torque shut so there is a potential.for a common mode failure of both valves if there is significant leakage. He then questioned if the VCT modification actually meets SCE's inten Mr. Reilly agreed that a torqued valve would work better, but explained that this has minimal safety significance so it does not need to be remedied in an expeditious manner. He added that SCE would probably make these minor modifications during the cycle 12 refueling outag. Discussion of the Misalignment of CV-518 Mr. Reilly discussed the role of CV-518 in the Unit 1 integrated Emergency Core Cooling System (ECCS) response to a LOCA. He then presented the results of SCE's investigation into the cause of the valve misalignment, along with the status of SCE's planned corrective actions

-4 for the event, per the attached slides. Mr. Reilly, along with Mr. Ray, noted a missed opportunity to have discovered that CV-518 was out of alignment when CV-517 was found similarly misaligned. It was also pointed out that the CV-518 event had some similarities to the event in wihch the steam trap for the turbine driven auxiliary feed pump in Unit 2 was isolated for an extended period of tim Mr. Reilly then presented the licensee's position on the safety signifi cance of the CV-518 event per the attached slides. SCE considers this event to be of minimal safety significance because operators would have noted the anomalies in flow during the recirculation phase of an accident and concluded that CV-518 was misaligned. They would, however, depend on non-safety grade instrument air to provide the motive force for any desired repositioning of the valv Several NRC representatives at the meeting questioned whether operators could exhibit such troubleshooting under the duress of an accident. Mr. Reilly noted that if the operators could not determine the status of the valve, they would probably alternate running the Refueling Water Pumps, which would provide adequate flow to mitigate the even Mr. Ray stated that there is no certainty that a LOCA coupled with this event would have been mitigated by operator action, however SCE concluded that the training operators receive made operator intervention very likely. He then stated that a full root cause analysis will be completed shortly for this issu B. Discussion of Unit 1 Sodium Silicate Blockage of Containment Spray Rings Mr. Reilly first presented background information and a brief explanation of the problem with sodium silicate blockage of the Unit 1 containment spray rings, per the attached slides. He stated that this event had no safety significance because an evaluation by SCE has determined that with a conservative evaluation, only 39 of 70 nozzles needed to be available. (Only seven nozzles were actually blocked.)

Mr. Ray added that SCE will write an informational Licensee Event Report (LER) for the sodium silicate blockage proble. Discussion of Performing Maintenance During Plant Operation Mr. Waldo opened the discussion about performing maintenance during plant operations (on-line maintenance) by reiterating the lessons learned and corrective actions resulting from the recent escalated enfiorcement action that dealt with the mispositioned containment sump valve and the inoperability of the turbine driven auxiliary feed pum Mr. Ray added that SCE is committed to performing less on-line maintenance, which will require extending outages in the future. M Waldo then outlined SCE's new policy for work on safety-related systems, per the attached slides. Mr. Ray stated that SCE was not presently in agreement with the INPO guidelines for minimizing outage time by performing maintenance while the plant is operatin Mr. Martin stated that if SCE had a good Reliability Centered Mainten ance (RCM) program, there would be better reliability of safety-related systems and less corrective maintenance would be required. He then requested that SCE briefly explain the status of the SONGS RCM progra Mr. Ray responded that the full analysis of RCM at the site has not yet been completed, but SCE will issue a report of the results of the analysis. Mr. Katz added that about 50% of the analyses were currently complet Mr. Martin requested that SCE provide the data on the unavailability of the High Pressure Safety Injection (HPSI) system, the Auxiliary Feed water (AFW) system, and the Emergency Diesel Generators (EDGs). M Waldo presented the requested system unavailability data, which is enumerated in the attached slide *

Mr. Martin commented that the original intent of the technical specifications action statements was not to provide for routine on line maintenance to allow for shorter refueling outages. Mr. Martin encouraged the licensee to ensure that the performance of on line maintenance was well thought out when performe Mr. Ray then briefly discussed SCE's boundary of the week program, and stated that this program can be a useful tool in planning work if properly employe. Discussion of SCE's Probabilistic Risk Assessment (PRA)

Mr. Katz discussed SCE's PRA efforts with particular emphasis placed upon its impact on performing on-line maintenance. He also gave a brief presentation of the licensee's uses-of PRA, per the attached slides. He added that SCE plans to use on-line risk assessments using a computer code prepared in Great Britain (with NRC approval).

In addition SCE would like to employ risk-based technical specifications in the futur Mr. Martin stated that he was pleased that SCE is using PRA in rendering decisions about plant operations and maintenance. He added that the industry must have a rational basis for removing safety-related systems from service; and he expressed concern that the general trend in the industry of minimizing outage time by maximizing on-line maintenance may not be based on sound safety analysis. He then recommended that SCE maintain an open dialogue with NRR regarding the use of PR.

Discussion of Mid-Loop Operations Mr. Martin stated that the use of mid-loop operations contains a high risk factor, especially when coupled with complicated work item Mr. Ray stated that a better mode of operation for an outage would be to use nozzle dams. He added that SCE is planning to off-load the entire core during the next refueling outage, and does not currently intend to exercise the mid-loop operation option. He noted that the tendency in the nuclear industry of late is to forego mid-loop operation in favor of

off-loading the core. He added that a full safety analysis needs to be done prior to widespread use of this mode of operatio Mr. Martin reiterated the increased risk associated with shutdown operations, and cautioned the licensee that the NRC will be focusing on this issue in the near future. He explained that hydraulic phenomena associated with boiling media during mid-loop operations was much worse than previously thought. In addition, he said, if utilities off-load the entire core, much flexibility can be attained in planning an outag However, he stated that if it is unreasonable to off-load the core, (e.g. brief outage for steam generator tube repair) then licensees will be obligated to go to mid-loop operation. He noted, however, that special care must be taken, particularly during periods of high decay heat loa.

Discussion of the Setpoint Methodology Team Inspection Mr. K. Johnston discussed the SCE position on the findings and conclusions of the NRC team inspection of the Unit 2 and 3 instrument setpoint methodologies. Mr. Ray noted that SCE did not agree with some of the conclusions reached by the team, and did not agree that some of the NRC's findings were representative of recent wor Mr. Richards replied that he attended the exit meeting and that the licensee attendees were substantially in agreement with the findings of the team. He then reiterated the team's findings and conclusions and stated that these findings appeared to be technically justifie Mr. Ray stated that since SCE and the NRC could not reach a consensus on the team inspection issues at this time, SCE would like to meet with the NRC concerning these issues at another dat Mr. Kirsch agreed, and stated that arrangements will be made for another meeting concerning the Setpoint Methodology Team Inspectio.

Discussion of the Control of Switchyards Mr. Martin discussed a problem at another nuclear power plant in which an outside organization working in the switchyard caused an event. He then requested that SCE describe how switchyard work is handled at SONG Mr. Waldo replied that the policy at SONGS is that switchyard workers contact the control room prior to entering the switchyard. He added that one half of the switchyard is owned by SCE, and the other half is owned by SDG&E. He noted that there have been isolated incidents in which SDG&E personnel have entered the switchyard without the knowledge of the control room operators, but there have been no problems associated with these minor events. However, he stated, SCE will closely monitor switchyard activities to ensure no major problems aris SII

-7 Mr. Martin concluded this discussion by cautioning the licensee that thcy shculd have a high degree of confidence regarding switchyard work, to prevent problems which could adversely affect the plan.

Discussion of SCE Erosion-Corrosion Modeling Mr. Martin questioned whether comtemporary methods issued by the Electric Power Research Institute (EPRI) would have predicted certain pipe failures at SONGS. He also stated that Region V was discussing this issue with NRR management. He questioned whether SCE planned to meet with EPRI and make a presentation to NRR to demonstrate the techniques SCE is employing in evaluating erosion-corrosio Mr. Ray replied that SCE will endeavor to meet with EPRI and will meet with INPO and NRR on this issue in the near futur.

Closing Remarks Mr. Martin thanked everyone, and adjourned the meeting at 4:45 II

DESIGN BASES DOCUMENTATION PROGRAM STATUS DBDs COMPLETED SIX DBDs COMPLETED IN 1990. ALL UNIT * NUCLEAR INSTRUMENTATION SYSTEM

  • SAFEGUARD LOAD SEQUENCING
  • COMPONENT COOLING WATER
  • SALTWATER COOLING
  • ENVIRONMENTAL QUALIFICATION

DESIGN BASES DOCUMENTATION PROGRAM STATUS DBD SCHEDULE 1991 1992 1993 1994 1995 UNIT 1 DBDs

7

4

UNITS 2&3 DBDs

6

5

UNITS 1, 2&3 DBDs

6

-

TOTAL

19

9

FEEDWATER PUMP RESTART DELAY FOLLOWING LOP/SIS BACKGROUND UNIT 1 SAFETY ANALYSIS EVENT SEQUENCE CONSIDERED:

SIMULTANEOUS BREAK AND LOP FOR LARGE LOCAs FOLLOWED RAPIDLY BY A SIS SIGNA *

LOP AT THE TIME OF REACTOR TRIP FOR SMALL BREAKS (INCLUDING SGTR).

  • SIMULTANEOUS BREAK AND LOP FOR SL NOTE: SLB WAS EVALUATED WITH AND WITHOUT LO IN SAFETY ANALYSIS, LOP IS A CONSEQUENCE OF EITHER THE EVENTS (LOCA, SLB, OR SGTR) OR REACTOR TRIP. THAT IS, LOP IS NOT AN INDEPENDENT EVEN FEEDWATER PUMP RESTART DELAY FOLLOWING LOP/SIS PROBLEM LOP/SIS TEST IDENTIFIED TWO UNANTICIPATED INTERACTIONS:

OBSERVED DELAY IN FEEDWATER PUMP STAR *

LOCK-OUT OF CHARGING PUMP FEEDWATER PUMP RESTART DELAY FOLLOWING LOP/SIS SIGNIFICANCE

LOP/SIS UNDERVOLTAGE CIRCUITRY

-

NOT APPLICABLE FOR DESIGN BASIS LARGE AND SMALL BREAK LOCAs SINCE LOP DOES NOT PRECEDE SIS BY MORE THAN 11.5 SECOND WILL NOT IMPACT VERY SMALL LOCA OR STGR

-

MSLB PRELIMINARY ASSESSMENT--REMAINS WITHIN DESIGN BASI *

CHARGING PUMP LOCKOUT DURING LOPSIS CONDITIONS HAS NO IMPACT ON SAFETY ANALYSI NO IMPACT--CHARGING PUMPS ARE NOT CREDITE FEEDWATER PUMP RESTART DELAY FOLLOWING LOP/SIS CORRECTIVE ACTION UNDERVOLTAGE AND LOCKOUT FEATURES BYPASSED BY SI FINALIZE MSLB EVALUATIO SINGLE FAILURE ANALYSIS RELATIVE TO UNDERVOLTAGE CIRCUITRY

SFA CORRECTLY IDENTIFIED UNDERVOLTAGE PROTECTION SCHEME, OPERATIONAL FEATURES

SFA CONSIDERED INDIVIDUAL COMPONENT FAILURE WITHIN THE UNDERVOLTAGE PROTECTION CIRCUIT

EFFECTS OF THE UNDERVOLTAGE PROTECTION CIRCUITS WERE EVALUATED ON THE BASIS OF SIMULTANEOUS SIS AND LOP CONSISTENT WITH THE DESIGN BASIS AND LICENSING BASIS

SONGS 1 ECCS SINGLE FAILURE ANALYSIS BACKGROUND PREVIOUS ANALYSIS

1976 ECCS SINGLE FAILURE ANALYSIS

1987 ESF/RPS SINGLE FAILURE ANALYSIS (PERFORMED IN RESPONSE TO PT-459 FAILURE)

SONGS 1 ECCS SINGLE FAILURE ANALYSIS BACKGROUND NEW ANALYSIS

1990 ECCS SINGLE FAILURE ANALYSIS (PERFORMED PER COMMITMENT IN CYCLE 10 RESTART REPORT)

LOW SAFETY SIGNIFICANCE

CONFIRMS EXPECTATION OF CYCLE 10 RESTART REPORT THAT ANY FUTURE ISSUES WOULD HAVE LOW SAFETY SIGNIFICANCE

SONGS 1 ECCS SINGLE FAILURE ANALYSIS HIGHLIGHTS SFA METHODOLOGY

MEETS MODERN SFA STANDARDS

FAILURE MODES AND AFFECTS ANALYSES

EVENT SPECIFIC/TIME DEPENDENT EVALUATIONS

APPROXIMATELY 3,000 INTERACTIONS EVALUATED NINE MODIFICATIONS

EIGHT COMPLETED THIS OUTAGE

ONE (VITAL BUS XFER) SCHEDULED FOR CYCLE 12 C

SONGS 1 ECCS SINGLE FAILURE ANALYSIS HIGHLIGHTS VALIDATION OF ASSUMPTIONS (VERIFY PLANT CONFIGURATION ASSUMED IN SFA)

NEW CALCULATIONS, ADDITIONAL IST, PROCEDURE REVISIONS OVERALL SAFETY SIGNIFICANCE

INDIVIDUALLY/COLLECTIVELY LOW SAFETY SIGNIFICANCE

INCREASED OVERALL SONGS 1 CORE DAMAGE FREQUENCY BY APPROXIMATELY 2%

SONGS 1 ECCS SINGLE FAILURE ANALYSIS SUMMARY

LOW SAFETY SIGNIFICANCE OF SFA ISSUES, CONSISTENT WITH EXPECTATION IN SCE.CYCLE 10 RESTART REPORT

EIGHT MODIFICATIONS COMPLETED

ONE MODIFICATION FORMALLY DEFERRED TO CYCLE 12

MISORIENTATION OF CV-518 BACKGROUND

FOR UNIT 1, HIGH SPRAY FLOW DURING INJECTION AND TRANSITION PHASE, LOW SPRAY FLOW DURING RECIRCULATION PHASE

CV-517 OR -518 ALONE PASSES FULL HIGH SPRAY FLOW

CLOSING CV-517 AND -518 REDUCES SPRAY FLOW AT ONSET OF RECIRCULATION PHASE CAUSE

OPERATORS CHANGED VALVE POSITION DURING MAINTENANCE WITHOUT ADEQUATE CONTROLS

NO EXTERNAL VALVE POSITION INDICATION

DISCOVERED DURING RECENT OUTAGE TESTS

MISORIENTATION OF CV-518 CORRECTIVE ACTION

CV-518 ALIGNED PROPERLY

PROPER POSITION INDICATOR ALIGNMENT VERIFIED FOR SIMILAR VALVES

INSTALLED EXTERNAL POSITION INDICATOR

MISORIENTATION OF CV-518 CONSEQUENCES CONTAINMENT SPRAY FLOW RATE DURING THE INJECTION AND TRANSITION PHASES WAS UNAFFECTED CONTAINMENT SPRAY FLOW DURING THE RECIRCULATION PHASE WOULD HAVE BEEN GREATER THAN EXPECTED AND WOULD HAVE PLACED AN OVER-POWER DEMAND ON THE SPRAY PUMP CONTROL ROOM OPERATORS WOULD HAVE BEEN ALERTED TO THIS CONDITION BY THE ABSENCE OF EXPECTED SPRAY FLOW DECREASE WHEN SHIFTING TO RECIRCULATION, OR BY THE TRIPPING OF THE SPRAY PUMP DUE TO OVERCURREN SAFETY SIGNIFICANCE WAS CONSIDERED TO BE MINIMAL AS THE OPERATORS WOULD HAVE OBSERVED THAT EXCESSIVE FLOW EXISTED AND TAKEN ACTION TO CORRECT IT

To CSS Spray H 3ader From Refueling CV-517 RWST Water Pumps FT-504 CV-518

-

~Recirculation--

Heat Exchanger RO-526 RO-525 To Charging Pump Suction Recirculation Pumps Containment Sump Spray Flow Limiter System During Recirculation

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RINGS BACKGROUND

SODIUM SILICATE COATING APPLIED TO SPRAY HEADER MID-70s AS CORROSION PROTECTION

SURVEILLANCE TESTING OF SPRAY RING PERFORMED EVERY OTHER REFUELING OUTAGE

THERMOGRAPHY TESTING PERFORMED IN PREVIOUS THREE SURVEILLANCES 6/80, 11/83, 12/88 (NO BLOCKAGE FOUND)

PROBLEM

SEVEN CONTAINMENT SPRAY NOZZLES DETERMINED TO BE PLUGGED DURING MOST RECENT SURVEILLANCE

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RING.)

CONSEQUENCES

39 OF THE TOTAL 71 NOZZLES REQUIRED TO BE AVAILABLE BY DESIGN BASIS CRITERIA (PRESSURE/TEMP/DOSE)

ti EVALUATION OF AS-FOUND CONDITION

SEVEN PLUGGED NOZZLES/64 NOZZLES AVAILABLE

PIPING RESTRICTION HAS NO EFFECT

DESIGN BASIS SATISFIED I-.

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RINGS WORST CREDIBLE ANALYSIS

39 NOZZLES REQUIRED OPERABLE TO SATISFY DESIGN BASIS (PRESSURE, TEMP, DOSE)

10 NOZZLES REQUIRED TO MEET REALISTIC CONDITIONS (PRESSURE, TEMP, DOSE)

TEST RESULTS SHOW PLUGGED NOZZLES REOPEN WITH DIFFERENTIAL PRESSURE OF 15-30 PSID

EXPECTED 130 PSID AP IN SPRAY RINGS WITH 10 NOZZLES OPERABLE

AT LEAST 10 NOZZLES WOULD UNBLOCK, SATISFYING BEST ESTIMATE CONDITIONS

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RINGS SIGNIFICANCE

AS FOUND CONDITION ACCEPTABLE

WORST CREDIBLE ANALYSIS REALISTICALLY ACCEPTABLE

IN OUR JUDGMENT AT LEAST 39 NOZZLES WOULD BE AVAILABLE

MINIMAL SAFETY SIGNIFICANCE

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RINGS CORRECTIVE ACTION

ALL NOZZLES CLEARED

LOOSE MATERIAL IN HEADER/RINGS REMOVED

HEADER/RING COATING REMOVED

-

MINIMAL RUST POTENTIAL (55% RH, 108 0F)

-

CARBON STEEL RISER PREVIOUSLY REPLACED WITH STAINLESS STEEL

-

UNCOATEDAREAS FOUND TO BE RUST FREE

EVALUATING NON-PLUGGING NOZZLES IN CYCLE 12

POTENTIAL BLOCKAGE OF CONTAINMENT SPRAY RINGS CONCLUSION

DETERMINISTIC ANALYSIS TO ESTABLISH PRECISE NUMBER OF NOZZLES WHICH COULD PLUG DUE TO LOOSE MATERIAL NOT TRACTABLE

CONTAINMENT SPRAY EVALUATED TO HAVE BEEN ADEQUATE

INFORMATIONAL LER TO BE SUBMITTED FOR INDUSTRY AWARENESS

16 NOZZLES 3"3 8 NOZZLES 6"

3" 3"

2" 4"EL98O 21 NOZZLES 6"

6" 24 NOZZLES EL. 90'0

ONLINE MAINTENANCE OPERATOR ATTENTIVENESS, UNITS 2/3 PROBLEMS:

HIGH ATTRITION LED TO REDUCED AVAILABLE MANPOWER

AGGRESSIVE IMPLEMENTATION OF A PREVENTATIVE MAINTENANCE PROGRAM RESULTED IN INCREASED ONLINE WORK LOAD

OPERATORS BELIEVED SUPPORTING SCHEDULED WORK HAD A HIGH PRIORITY AND CONCENTRATED EFFORTS HERE

EXTENSIVE ROUND SHEETS CREATED A LARGE DEMAND ON PLANT EQUIPMENT OPERATOR TIME

ONLINE MAINTENANCE OPERATOR ATTENTIVENESS, UNITS 2/3 SOLUTIONS:

SIGNIFICANT PAY INCREASES HAVE BEEN AWARDED AT ALL LEVELS REVERSING PREVIOUS ATTRITION TREND

LARGE NUMBERS OF OPERATORS IN TRAINING PIPELINE WILL BE AVAILABLE IN FALL 1991

OPERATORS HAVE BEEN RECEIVING REPEATED COACHING ON ACTUAL MANAGEMENT PRIORITIES

INCREASED MONITORING REQUIREMENTS HAVE BEEN PROCEDURALIZED

DETAILED TAILBOARDING OCCURS AT THE START OF EACH SHIFT

OVERALL MAINTENANCE WORKLOAD REDUCED

EXTRA OPERATOR SUPPORT SCHEDULED FOR HIGH WORK EVOLUTIONS

SCE WORK APPROVAL POLICY (UNDER DEVELOPMENT FOR SAFETY RELATED SYSTEMS)

PMs NORMALLY DONE DURING OUTAGES

EQUIPMENT OUTAGES NORMALLY LIMITED TO ACTIVITIES NEEDED TO MAINTAIN SYSTEM OPERABILITY AND RELIABILITY

OPTIONAL WORK IS APPROVED IF IT DOES NOT APPRECIABLY INCREASE SYSTEM OUTAGE TIME

RETEST COMMITTEE REVIEW OF RETEST REQUIREMENTS

HIGH PRIORITY GIVEN TO MINIMIZING SYSTEM OUTAGE TIME

RESTRICTIONS PLACED ON APPROVAL OF CROSS-TRAIN OR MULTIPLE SYSTEM OUTAGES

SAFETY SYSTEM PERFORMANCE SYSTEM UNIT 1 UNIT 2 UNIT 3 IND MED P

UP P

UP P

UP P

UP HPSI

.0001.0019

.0263.0021

.0123.0034

.0062.0010 AXFDWTR

.0289.0062

.0147.0315

.0258.0009

.0090.0015 SITE IND MED P

UP P

UP DGEN

.0087.0023

.0064

.0075 DATA IS A 24 MONTH AVERAGE FOR THE YEARS OF 1989-199 P

= PLANNED UP = UNPLANNED

OPTIMIZING SAFETY USING PRA

OVERVIEW OBJECTIVE Mission Statement of the Nuclear Safety Group:

To provide plant management with timely and credible advisories regarding:

whether existing and proposed equipment, operation and maintenance are within design basis assumptions and acceptably safe, and cost effective measures to reduce plant ris CHALLENGE Maintaining "objectivity" and "perspective".

MECHANISM Probabilistic Risk Assessmen LO

OPERATIONAL USES OF PRA Outage Safety Assessments Quarterly Assessments of Plant Risk Design Change Safety Assessments Risk-Based Technical Specifications

OUTAGE SAFETY ASSESSMENTS WHAT Risk-based FMEA of shutdown conditio WHY Identify and address high consequence / high probability accident scenarios during refueling outage EXAMPLE RIR SYSTEM WITH SINGLE (A-TRAIN) COMPONENT AVAILABILITY FULL CAVITY AND SINGLE FAILURES 10 DAYS Comp Compen-Action Consequences of Current Single Failure satory Failure Failed Compen-Consequence Component Failure Mode Prob/Day Actions Prob/Demand satory Action Prob/Period RHR Mechanical 7.OE-4 Start 2.OE-1 Boiling 1.4E-4 Pump Failure Pump B 14A RHR Pump or alt RHR w/in 20 hrs

UNIT 1 CYCLE 11 OUTAGE Safety Assessment Results Residual Heat Removal System Worst Case Modified Probability Probability o CORE MELT 5E-6 3E-6 o BOILING 4E-3 1E-5 o PERSONNEL EXPOSURE 2E-3 7E-4 o REACTIVITY CONTROL 3E-8 3E-8 o SPILLAGE 2E-4 2E-4 Reactor Vessel Cover Plate Operations Worst Case Modified Probability Probability o PERSONNEL EXPOSURE 3E-2 3E-3 o SPILLAGE 2E-2 2E-2

San Onofre Unit 1 Reactor Cavity With Core Barrel and Upper Internals Removed Work Platform Water Level -4

..

Elevation 42'

122.00 Di Limiterpp Keytrna Thermal Shield

....

(....

...

1...

.

...

.....

ii.............................................................0 Th.rma Shield Uppi Internal Lowecr Support

!i'

Six Places-jToSpptPlt Rotating Baarng

.

Newi Core BarrelIUpeInralStd Support StandLU

.............. i:-

Ins' urnentation Ring R.(Retraced Position)

Upper Internals Core Plato Radial Supports

......

.....

...

QUARTERLY ASSESSMENT OF PLANT RISK WHAT Trend in core melt frequency as o function of safety equipment unavailabilitie WHY Identify and address equipment or activities which have significant risk consequence L)

ATTACHMENT ESTTMATED PROBABILISTIC RISK UNIT 2 Shown below is the trend in the risk of core damage as calculated using probabilistic risk assessment (PRA) techniques. These results are based upon 0:- PIUQL rejtIoSe to loss-of--:oolant and loss-of-offsite-power event Time period (3) shows a significant reduction in estimated risk and reflects the impact of Design Change Package 6204 which provided the capability to backflush the CCW heat exchanger Period (5) saw a further reduction in'risk due primarily to a continued increase in CCW heat exchanger availability. The minimum achievable risk of 1/24,000 years was not reached is this period due primarily to small unavailabilities of the CCW heat exchangers and HPSI trains resulting from maintenance activitie /1,000 Yus

-

_______________

_____

1/2,000 YRS 1/2000

L)

1/5,000 YRS S

3/10,000 YRS

__-----


1/14.000 1/20.000 YRS

& 1/50,000 YRS--

-

-

--

-

-

}yRSTSECON7D

REFITDING REFUELING CCW BACEMUSE 1/100,000 YRS rNT JAN 1984 -

NOV 1984 -

APR 1985 -

APR 1968 -

JUN 198 OCT 1984 MAR 1985 UAR 1986 MAY 1986 JU 1987 PEF.10D)

(3)

(4)

ATTACPUIENT TREND IN ESTIMATED PROBABILISTIC RISK UNIT 1 The trend in core damage risk appears in the chart below. These estimates derive from probabilistic models (fault trees and event trees) of plant accidents. The models portray the risks of loss-of-offsite power and loss-of-coolant accidents, and reflect actual equipment unavailabilities due to random failures, testing, or maintenanc Unit 1 was shutdown for the entire fourth quarter of 199 The reduction of risk following the Cycle-10 refueling was caused primarily by the addition of proceduralized actions following a loss-of-coolant accident to ensure isolation of the main feedwater pump miniflow to the condenser (SO1-1.0-10, "Reactor Trip or Safety Injection") and proceduralized actions following a loss of recirculation to establish alternative recirculatiori cooling (SO1-1.0-25, "Loss of Recirculation Flow").

FREQUENCY OF SIGNIFICANT CORE DAMAGE TE-3 /YR 2E-

/YR-4 1.9E-4 go CYCIE 10 cLE1 OUTAGE REJEUING IE-5 /YR MAR 1985 -

AUG 1968-DEC 1988 -

MAY 1989 -

JA 1990 -

JJL 1990 JJL 1988 NOV 1988 APR 1989 DEC 1989 JJN 1990 DEC 1990

.ODE 1 HOURS

2745

3460 4148

37

ATTACHMENT TREND IN ESTIMATED PROBABILISTIC RISK UNIT 2 The trend in core damage risk appears in the chart below. These estimates derive from probabilistic models (fault trees and event trees) of plant accidents. The models portray the risks of loss-of-offsite power and loss-of-coolant accidents, and reflect actual equipment unavailabilities due to random failures, testing, or maintenanc One key factor influencing plant risk during Periods 5 and 6 was the status of the turbine driven AFW pump P-14 The steam trap on the turbine steam supply line was inadvertently isolated from August 31 until October 21, 1990. This isolation was assumed to result in a pump overspeed trip, but with a high likelihood of recovery with operator action. Still, the conditional probability of core damage given a station blackout increased because P-140 is the only pumping system available in this conditio FREQUENCY OF SIGNIFICANT CORE DAMAGE 1E-3 /YR 5E-4 /YR 2E-4 /YR 1E-4/Y SE-5 /YR 6.5E-5 4.8 E~5 2.7E-5 3. -5 2.6E-5 2E-5 /YR REFUEUNG OUTAGE TE-5 /YR NOV 198-APR

  • 98 SEP 1989-JAN 1990-MAY 1990-OCT 1990 MIAR 1989 AUG 19B9 DEC 1989 APR 1990 SEP 1990 DEC 1990 MODE 1 HOURS 2901 3092

2840 2544 2001

ATTACHMENT TREND IN ESTIMATED PROBABILISTIC RISK UNIT 3 The trend in core damage risk appears in the chart below. These estimates derive from probabilistic models (fault trees and event trees) of plant accidents. The models portray the risk of loss-of-offsite power and loss-of-coolant accidents, and reflect actual equipment unavailabilities due to random failures, testing, or maintenanc Principal contributors to the risk increase during Period 6 were two outages of CCW-Heat Exchanger E-001 of about 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> eac One outage was due to preventive maintenance ("Boundary of the Week") and the other was required for cleaning. The inadvertent misalignment of ECCS valve 3HV-9302 was shown to have had a very small (2%) impact on tore melt ris Factors influencing plant risk during Period 7 include preventive maintenance outages for LPSI pump P015, CCW Pump P025, and HPSI pump P018. An extended outage of HPSI pump P017 also ended in Novembe FREQUENCY OF SIGNIFICANT CORE DAMAGE 1E-3 /YR 5E-4 /YR 2E-4 /YR IE-4 /.

7.2E-5 5E-5 /YR 5.4E-5 3.4E-5 2.3E-~

)YA4.OE-5 DP*mer g

3.5E-5 2E-5 /YR 2.7E-5 REFUEUNG OUTAGE TE-5 /YR DEC 1988 -

APR 1989 -

P 1989-JAN 1990-MAY 1990-JJL 1990-OCT 1990 UAR 1989 AUG 1988 DEC 1989 APR 1990 JUN 1990 SEP 1990 DEC 1990 MODE 1 HOURS 2CE3 3039 2929 2254

1731 2208

DESIGN CHANGE EVALUATIONS WHAT PRAs performed for plant design changes to assess impact on system reliability and overa1 plant ris WHY IOCFR50.59 (NSAC/125)

RISK-BASED TECHNICAL SPECIFICATIONS WHAT Potential pilot plant using Electric Essential Systems Status Monitor (ESSM)

in cooperation with NRC's Risk-Based Technical Specifications Working Grou WHY Inability of current "deterministic" Technical Specifications to balance plant safety with plant operabilit NO.1)UI DOSl CCW HIT X &As 3ACKUP NITRIJGf N cGV PP 'SWING,'

STN AW ppTO HV-851 WL DIESEL 'DSD'

LD S\\1 C PP "AUX'

3.2E-4 /YR hw12--

YR12-Y 1.2E-

/YR El~~

T

_

IE-5

/YR

_

_

_

_

_

_

_

_

_

_

_

_

_

CONCLUSION APPLICATIONS OF PRA o

Licensing o

Engineering (offsite)

o Engineering (onsite)

o Operations

o Maintenance o

Training o

Emergency Preparedness o

Safety