IR 05000146/1990001
| ML20058L447 | |
| Person / Time | |
|---|---|
| Site: | Saxton File:GPU Nuclear icon.png |
| Issue date: | 07/25/1990 |
| From: | Bores R, Roth J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20058L438 | List: |
| References | |
| 50-146-90-01, 50-146-90-1, NUDOCS 9008070217 | |
| Download: ML20058L447 (5) | |
Text
,=
^
.
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No. 50-146/90-01 Docket No. 50-146 License No. DPR-4 Priority Category D
Licensee: Saxton Nuclear Experimental Corporation /GPUN Corporation 1 Upper Pond Road
[arsippany,Newlersey 07054 Facility Name: Saxton Reactor Inspection At: Saxton, Pennsylvania Inspection Conduct
July 10-12, 1990
'
Inspectors:
gjs
Od
, J.
th. Pro ct Engineer Dater Ef ents Radiation Protection Section, Facilities Radiological Safety and Safeguards Branch, Div. of Radi on Safet and Safeguards Approved by:
7M8M
'
R. Bores, ief,1ffluents Date Radiation rotection Section, Facilities Radiological Safety and Safeguards Branch, Div of Radiation Safety and Safeguards Inspection Summary:
Inspection conducted on July 10-12, 1990 (Inspection Report No. 50-146/90-01).
Areas Inspected:
Special, announced inspection by one region-ba>ed inspector to review actions taken by the licensee to decontaminate several buildings on site and to review the results of a final release survey conducted by the licensee and reported to the NRC by letter dated April 26, 1990.
Results:
l No significant contamination was observed in the remediated buildings.
The inspector identified several areas in the final survey report which required additional information for review by the NRC prior to initiating a confirmatory survey.
The licensee committed to providing this information in a revised survey report by August 15, 1990.
9008070217 900726 PDR ADOCK 05000146 O
o
4
,
,
l
,
'
<
,.
..
r
-
L
.
'
DETAILS
>
- 1.0 Individuals Contacted
'
1.1 Saxton Nuclear Experimental Corporation (SNEC)
B. Good, General Manager, SNEC J.- Hildebrand, Vice President, SNEC
E. Pagan, Licensing Engineer, General Public Utilities e
R. Rolph, Radiation Safety Officer, SNEC I
1.2 Commonwealth of Pennsylvania. Department of Environmental Resources f
R. Hysong, Health Physicist
'
M. Murphy, Nuclear Engineer
-
,
M. Reilly, Chief, Division of Environmental Radiation
s U.S. NRC
,
J. Minns, Health Physicist, NRR l
L L. person, Project Manager, NMSS
-
'
J. Roth, Project Engineer, Region I
[i 2.0 Background By memorandum dated June 6,1990, from Mr. S. 'H. Weiss, Director, Non-Power Reactor, Decommissioning and Environmental Project. Directorate, Region I was requested to provide technical assistance in the review of the " Final Release Survey of SNEC (Saxton Nuclear Experimental Corporation) Support i
Buildings" submitted by the licensee by letter dated April 26, 1990.
This
'
review was to determine if the information in the final release report i
supported. release of the buildings for unrestricted use and if the information was sufficient to. justify scheduling an NRC confirmatory survey.
This-
~
,
inspection was conducted to examine the subject buildings and review the a
contents of the final survey report with licensee representatives.
3.0 Facility Tour g
L'
All areas and buildings on site were examined by the inspector to determine
.
status and condition with regard to decommissioning and decontamination
!
L activities.
The Control and Auxiliary Building (C&A Suilding), the Pipe f
,
Tunnel, the Radwaste Disposal Facility (RWDF), the Filled Drum Storage
'
l Area and the Containment Vessel were examined. All of the above areas l
'
except for the Containment Vessel were to be released for unrestricted use on the basis of the subject surytv report.
It was noted by the inspector that considerable effort had been expended by the licensee to decontaminate the buildings. However, it was noted that walls in the C&A Building and the RWDF were still painted and there was no indication in the survey
,
report that this paint had been sampled for contamination.
Licensee
_
/
v a.
.
m f
V
'
.
.
,s
.
.
,
.
- representativesEstated that paint chips will be analyzed for radioactive c
contamination.
Floor plates used to hold inside partition walls were
-
observed in the C&A Building. Since these plates could be a source of
!
retained contamination, they will be removed by the licensee prior to any
NRC confirmatory survey. The inspector also noted that most of the floor,
"
wall.and ceiling grid (one meter by one meter) markings had been removed :
c or worn off.
Licensee representatives stated that these markings would be E
replaced prior to any NRC confirmatory survey.
l Cursory radiation surveys conducted by the' inspector during examination of these buildings indicated a maximum radiation level on contact of about 22 microR per hour and an average radiation level about five i
to seven microR per hour at one meter from any surface.
11 dings.
These
measurements were made using a Ludlum Model 19 MicroR Me,,.
.,
i'
.
_
!
During examination of.the containment vessel, the inspector observed that
-
'
most of the equipment and piping associated with reactor operation was
'
still in place.
Licensee representatives indicated that decommissioning of this facility was not scheduled to start until about the 1996-1997 time period.
The inspector stated that the licensee should consider initiation
,'
of a characterization study within the next year in order to determine the
'
radiological status of each piece of equipment,. piping, ventilation system, and jumper cables remaining.
This would be needed to determine-the best. method to facilitate decommissioning and decontamination of the i
containment vessel.
Licensee representatives stated that they expected to
initiate this characterization study within the next-two years, i
4.0 Final Release Survey Report Review 4.1 Site Survey _ History
,
The reactor facility was constructed between 1960 and 1962, was operated between May,1962 and May 1972 by the Saxton Nuclear
,
Experimental Corporation (SNEC), a wholly owned subsidiary of the General Public Utilities (GPU) and was decommissioned (core i
removed) and partially decontaminated between 1972 and 1974.
In t
1981 GPU initiated actions to release the SNEC facility and site for unrestricted use.
This is expected to be a four phased plan.
Phase 1 - Removal of water from the basement of the Radwaste Building. This was completed in 1987.
Phase 2 - Decontamination and survey of the outbuildings.
This (
was completed in 1989 and is the subject of this report.
- l Phase 3 - Characterization, decommissioning, decontamination and l
survey of the containment vessel.
This is expected to start in about two years.
I i
h i
l5
....
. _
_
_
.
-
.
...
,
+
i Phase 4 - Characterization, decontamination, as necessary, and survey of the site (e.g., soil, other buildings not associated
with the reactor facility, etc.).
This has not been scheduled.-
l All of the above activities are expected to be completed prior.
to the year.2007 which is the expiration year for the current license, i
4.2 Report Review As a result of a page-by page review of the survey document,.the following major observations were made.
In addition, many minor a
comments were also made.
,
4.2.1 It was.noted that detailed descriptions and the status of each-
!
structure on' site (e.g., Pennelec warehouses, transmission'
i buildings, the pad for the-safety injection / refueling tank, and remedial work done on the filled-drum storage area) were not provided.
]
4.2,2 'It was noted through discussions with licensee representatives that survey probe geometry factors were not provided in sufficient detail for the reader to determine that the geometry factor for the scans was 20 cm' and for contact readings was
16 cm.
4.2,3 Figure 1 on page 5 did not show that the pipe tunnel extends.
,
under the fence toward the containment vessel.
This portion-of the tunnel has not decontaminated. As a result, the
<
licensee was requesta orovide positive assurance that ground
,
water coming through thu
. crete block wall installed at the
-
fence line would not be-contaminated.
The licensee expects to t
install a monitoring well on the yard side of the wall and will l
monitor this well for residual contamination until the remainder of the tunnel has been decontaminated.
v 4.2,4 There was no indication in the survey report with regard to licensee plans for the. concrete rubble to remain on' site following demolition of the buildings.
This information will be provided'
in the revised report.
4.2.5 If the licensee intends to leave the concrete rubble on site,-
then the pathway analysis must be modified to include the
'
residual contamination, if any, in the analysis.
The pathway l
analysis included in the report only accounts for residual
"
contamination in the soil which might be mixed with some of this rubble.
The licensee ststed that the pathway analysis would be modified.
r
- -,
T :.:
'
.
..
.
'
c. -
- -
i.
.
.
..
E
,
.
.
4;2.6 It was noted that a. detailed analysis of the concrete ~and soil.
I
~
x which would provide information on all radionuclides present was l
not provided in the report..This will be provided..
.
'4.2.7 The inspector noted that individual alpha survey results were
'
not' reported.
Beta gamma activity was reported.only as less than 5000 dpm/100 cm2 The licensee committed to revise the report
.
to provide actual alpha and beta gamma maximum and average;
'
<
survey.results for each block surveyed.
t 4.2.8 Is order to update the Region I files on this. facility, the
,
c li :ense9 was requested to and committed ~to providing the Region
~~.
- $ffice with at'least one' copy of each'of the references.
specified on page 33 of the survey report.
4.2.9 The' licensee was also requested to provide additional detail in
'
the report ;o that the sequence of decommissioning actions of-
.the site could be determined.
This additional detail will be an expansion of the information provided in Section 4.1 of this report.
..
5.0 -Licensee Discussions Discussions were. held throughout the inspection with the licensee representatives identified in Section 1.
The Commonwealth of Pennsylvania representatives were present during the detailed review of the survey report.
In order to expedite the scheduling of the NRC confirmatory survey, the licensee committed to provide NRR with a modified survey report which incorporated, as a minimum, the comments indicated in Section'4.0 of this report by August 15, 1990, i
o
!
i
!
i j