GEH recently discovered that some calculations of the choked flow rate in the
Main Steam Lines (
MSLs) of
GEH BWRs were non-conservative, with potential effects on margins between choked flow conditions and existing
MSL high-flow Nominal Trip Setpoints (
NTSPs), Allowable Values (
AVs), and Analytical Limits (
ALs).
GEH has now completed the evaluation of this condition and has determined this condition is not reportable under 10 CFR 21 for all U.S. BWR/2-6 plants. The effect of the discovered non-conservatisms in choked flow rate values was offset by unintended conservatisms in the GEH recommended formulation for calculating pressure drop across the MSL flow restrictor. As a result, GEH has determined that the flow-instrument pressure remain at conservative values (which would ensure that the associated NTSPs and AVs expressed in psid also remain at conservative values), and the MSL high-flow trip will function as designed. This update to the 60-day Interim Notification issued on December 12, 2012 (MFN 12-111 R1) will be sent to all US BWR/2-6 plants licensed using the GEH design basis and safety analysis.
See previous
NRC Event 48350.