ENS 47492
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
22:47 Nov 30, 2011 | |
| Title | |
| Event Description | On November 30, 2011, at 1747 hours0.0202 days <br />0.485 hours <br />0.00289 weeks <br />6.647335e-4 months <br /> [EST], with the reactor at 100% core thermal power and steady state conditions, Pilgrim Nuclear Power Station (PNPS) declared the High Pressure Coolant Injection (HPCI) system inoperable due to the HPCI turbine control valve (HPCI-24) failing to go open during planned post-maintenance testing. The HPCI-24 is a hydraulically operated control valve and its normal position is closed. The HPCI-24 valve has a safety function to open on a demand signal during certain event mitigation scenarios requiring the HPCI system operation.
Based on the turbine control valve failing to open during post-maintenance testing and a subsequent check out run per PNPS Procedure 8.5.4.1, the HPCI system was declared inoperable at 1747 hours0.0202 days <br />0.485 hours <br />0.00289 weeks <br />6.647335e-4 months <br /> and the appropriate LCO was entered. An investigation of the event is underway and continuing. This event had no impact on the health and/or safety of the public. The NRC Resident Inspector bas been notified. This is an 8-hour notification made in accordance with 50.72(b)(3)(v)(D). |
| Where | |
|---|---|
| Pilgrim Massachusetts (NRC Region 1) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
| Time - Person (Reporting Time:+-0.63 h-0.0263 days <br />-0.00375 weeks <br />-8.62974e-4 months <br />) | |
| Opened: | Ken Gracia 22:09 Nov 30, 2011 |
| NRC Officer: | Bill Huffman |
| Last Updated: | Nov 30, 2011 |
| 47492 - NRC Website
Loading map... | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_47492&oldid=87004"