ENS Event | |
---|---|
22:47 Nov 30, 2011 | |
Title | |
Event Description | On November 30, 2011, at 1747 hours0.0202 days <br />0.485 hours <br />0.00289 weeks <br />6.647335e-4 months <br /> [EST], with the reactor at 100% core thermal power and steady state conditions, Pilgrim Nuclear Power Station (PNPS) declared the High Pressure Coolant Injection (HPCI) system inoperable due to the HPCI turbine control valve (HPCI-24) failing to go open during planned post-maintenance testing. The HPCI-24 is a hydraulically operated control valve and its normal position is closed. The HPCI-24 valve has a safety function to open on a demand signal during certain event mitigation scenarios requiring the HPCI system operation.
Based on the turbine control valve failing to open during post-maintenance testing and a subsequent check out run per PNPS Procedure 8.5.4.1, the HPCI system was declared inoperable at 1747 hours0.0202 days <br />0.485 hours <br />0.00289 weeks <br />6.647335e-4 months <br /> and the appropriate LCO was entered. An investigation of the event is underway and continuing. This event had no impact on the health and/or safety of the public. The NRC Resident Inspector bas been notified. This is an 8-hour notification made in accordance with 50.72(b)(3)(v)(D). |
Where | |
---|---|
Pilgrim Massachusetts (NRC Region 1) | |
Reporting | |
10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
Time - Person (Reporting Time:+-0.63 h-0.0263 days <br />-0.00375 weeks <br />-8.62974e-4 months <br />) | |
Opened: | Ken Gracia 22:09 Nov 30, 2011 |
NRC Officer: | Bill Huffman |
Last Updated: | Nov 30, 2011 |
47492 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 47492\u003C/a\u003E - \u003Ca href=\"/Pilgrim\" title=\"Pilgrim\"\u003EPilgrim\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EHigh Pressure Coolant Injection Declared Inoperable\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 47492 - Pilgrim\n","link":"","lat":41.942861111111114,"lon":-70.57673055555556,"icon":""}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |