MONTHYEARCY-23-014, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2023-12-0404 December 2023 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI CY-23-006, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-23-007, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-23-003, Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage CY-23-004, Independent Spent Fuel Storage Installation, Property Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Property Insurance Coverage CY-23-001, Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments CY-23-002, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments CY-22-012, Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2022-08-0303 August 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-22-010, Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager2022-05-25025 May 2022 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager CY-22-006, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 20212022-04-25025 April 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2021 CY-22-003, and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report2022-03-14014 March 2022 and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report CY-22-004, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-22-002, Independent Spent Fuel Storage Installation - Property Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-22-001, Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage CY-21-015, Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2021-12-10010 December 2021 Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-21-013, Biennial Update to the Haddam Neck Plant License Termination Plan2021-12-0101 December 2021 Biennial Update to the Haddam Neck Plant License Termination Plan CY-21-011, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2021-12-0101 December 2021 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI CY-21-014, Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration2021-11-18018 November 2021 Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration CY-21-005, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-21-006, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-21-004, Independent Spent Fuel Storage Installation - Property Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-21-003, Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage CY-20-011, Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement2020-05-14014 May 2020 Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement CY-20-007, Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager2020-03-31031 March 2020 Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager CY-20-004, Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste2020-03-17017 March 2020 Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste CY-20-003, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2020-03-12012 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-20-002, Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 20202020-01-22022 January 2020 Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 2020 CY-19-014, Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return2019-06-0505 June 2019 Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return CY-19-012, Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report2019-04-23023 April 2019 Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report CY-18-021, Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2018-12-10010 December 2018 Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-18-005, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-18-004, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-17-021, Independent Spent Fuel Storage Installation Formal Announcement of Change in HNP ISFSI Manager2017-09-0505 September 2017 Independent Spent Fuel Storage Installation Formal Announcement of Change in HNP ISFSI Manager CY-17-010, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2017-03-0909 March 2017 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-17-005, Independent Spent Fuel Storage Installation - Property Insurance Coverage2017-02-28028 February 2017 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-17-004, ISFSI - Nuclear Liability Insurance Coverage2017-02-28028 February 2017 ISFSI - Nuclear Liability Insurance Coverage CY-17-007, Independent Spent Fuel Storage Installation - Revision 6 to Haddam Neck Plant Post-Shutdown Decommissioning Activities Report2017-02-22022 February 2017 Independent Spent Fuel Storage Installation - Revision 6 to Haddam Neck Plant Post-Shutdown Decommissioning Activities Report CY-17-001, ISFSI - Notification of Changes to the Decommissioning Schedule, Per 10 CFR 50.82(a)(7)2017-01-0505 January 2017 ISFSI - Notification of Changes to the Decommissioning Schedule, Per 10 CFR 50.82(a)(7) CY-17-002, Independent Spent Fuel Storage Installation2017-01-0505 January 2017 Independent Spent Fuel Storage Installation CY-17-003, ISFSI - Report of 10 CFR 50.59 Changes, Tests, and Experiments for 01/01/1995 - 12/31/20162017-01-0505 January 2017 ISFSI - Report of 10 CFR 50.59 Changes, Tests, and Experiments for 01/01/1995 - 12/31/2016 CY-16-035, Independent Spent Fuel Storage Installation - Formal Announcement of Change in HNP ISFSI Manager2016-12-15015 December 2016 Independent Spent Fuel Storage Installation - Formal Announcement of Change in HNP ISFSI Manager CY-16-012, ISFSI - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2016-03-23023 March 2016 ISFSI - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-16-011, ISFSI - Decommissioning Funding Assurance Status Report2016-03-0909 March 2016 ISFSI - Decommissioning Funding Assurance Status Report CY-16-004, Independent Spent Fuel Storage Installation, Submittal of Property Insurance Coverage2016-02-29029 February 2016 Independent Spent Fuel Storage Installation, Submittal of Property Insurance Coverage CY-16-006, ISFSI - Annual Notification of Foreign Ownership, Control, or Influence (FOCI) Status2016-02-0202 February 2016 ISFSI - Annual Notification of Foreign Ownership, Control, or Influence (FOCI) Status CY-16-002, ISFSI - Revision 5 of the Post-Shutdown Decommissioning Activities Report2016-01-14014 January 2016 ISFSI - Revision 5 of the Post-Shutdown Decommissioning Activities Report CY-15-042, ISFSI - Three-Year Update to the Decommissioning Funding Plan2015-12-14014 December 2015 ISFSI - Three-Year Update to the Decommissioning Funding Plan CY-15-035, Redacted Haddam Neck ISFSI - Biennial Update to the Updated Final Safety Analysis Report2015-12-0101 December 2015 Redacted Haddam Neck ISFSI - Biennial Update to the Updated Final Safety Analysis Report CY-15-043, ISFSI - Revision 13 to the Emergency Plan2015-12-0101 December 2015 ISFSI - Revision 13 to the Emergency Plan CY-15-037, ISFSI - Biennial Update of the Quality Assurance Program2015-12-0101 December 2015 ISFSI - Biennial Update of the Quality Assurance Program 2023-03-06
[Table view] |
Text
CONNECTICUT YANKEE ATOMIC POWER COMPANY HADDAM NECK PLANT 362 INJUN HOLLOW ROAD
- EAST HAMPTON, CT 06424-3099 Docket No. 50-213 CY-05-195 Re: 10CFR50.90 U. S. Nuclear Regulatory Commission SEP 2 9 2005 Attention: Document Control Desk Washington, DC 20555 Haddam Neck Plant Clarification to License Amendment No. 202 and the Associated Safety Evaluation Report Reqardinq the License Termination Plan On August 19, 2005,(') the NRC issued Amendment No. 202 to Facility Operating License No. DPR-61 for the Haddam Neck Plant. A supporting Safety Evaluation Report (SER) was included. The License Amendment revised License Condition 2.C (7)to specify the proposed License Termination Plan (LTP) revision for the Haddam Neck Plant.
On August 22, 2005, CYAPCO verbally notified the NRC that to the License Amendment letter and the SER required a clarification. On September 13, 2005, CYAPCO and the NRC discussed our comments to Enclosure 1 and the SER statements.
CYAPCO hereby submits our clarifications regarding Enclosure 1 and the SER statements in Attachment 1.
If the NRC should have any questions regarding our comments, please contact Gerry van Noordennen at (860) 267-3938. No written response to this letter is requested.
1)' D. Gillen (NRC) letter to W. Norton (CYAPCO), "Issuance of Amendment No. 202," dated August 19, 2005.
Ars (nl
Document Control Center Document Control Center CY-05-195 / Page 2 Sincerely, CONNECTICUT YANKEE ATOMIC POWER COMPANY President Attachment cc: S. J. Collins, Region I Administrator M. T. Miller, Branch Chief, Decommissioning Branch, Region I T. B. Smith, Project Manager, Haddam Neck Plant Dr. E. L. Wilds, Jr., Director, CT DEP Radiation Division Subscribed and sworn before me this ck day of cap +/-.b . 2005
- ^ Notary Public My-Commission Expires ,a4 ....
MyC , mg
CY-05-1 95 Attachment 1 --
Haddam Neck Plant Clarification to License Amendment No. 202 and the Associated Safety Evaluation Report Regarding the License Termination Plan September 2005
Pocument Control Center v CY-05-195 / Attachment 1 NRC SE Statement Page No. Requiring Clarification CYAPCO Position Enclosure 1, Item 2 states "Accordingly the The proposed License Amendment request Item 2 license is amended by changes (application dated December 1, 2004) did not to the Technical Specifications as involve any changes to the Haddam Neck indicated in the attachment to Plant (HNP) Technical Specifications. Instead this license amendment". It the license amendment request consisted of further states that Paragraph changes to the methods included in the HNP 2.C.2 of Facility License License Termination Plan (use of Basement Operating License No. DPR-61 is Fill Model in lieu of a buried debris model to hereby amended to read as -calculate the future groundwater dose for- -
follows: "The Technical buried concrete and revised surface Specifications contained in contamination release limits for various piping Appendix A, as revised through sizes).
Amendment No. 202 are hereby incorporated in the license." CYAPCO has revised our controlled copies of the facility license to incorporate Amendment No. 202.
Enclosure 2, The second paragraph states in The assumed value for the porosity stated SER Section part, "The water activity was then should be 35% (Refer to Table F-1 of the HNP 2.2, Page 5 divided by water volume in the LTP and Page 20 of 38 of Attachment 2 of the backfill assuming a porosity of License Amendment request submittal dated 30%." December 1,2004).