CY-15-042, ISFSI - Three-Year Update to the Decommissioning Funding Plan

From kanterella
Jump to navigation Jump to search
ISFSI - Three-Year Update to the Decommissioning Funding Plan
ML16020A209
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 12/14/2015
From: Pizzella C
Connecticut Yankee Atomic Power Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
CY-15-042
Download: ML16020A209 (28)


Text

CONNECTICUT YANKEE ATOMIC POWER COMPANY

~HADDAM NECK PLANT PLANT 362 INJUN HOLLOW ROAD u EAST HAMPTON, CT 06424-3099 December 14, 2015 CY-1 5-042 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk, U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation NRC License No. DPR-61 (NRC Docket No. 50-213)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Connecticut Yankee Atomic Power Company (CYAPCO) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Haddam Neck Plant (HINP) 1SF SI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original JiNP ISFS *I DFP on December 1-7, 2012*,,,.'"

(Reernc 1*.,,,

). It includesh~n adjus*,*,tmet to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the HNP ISFSI remains unchanged.

10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates.

Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

In addition, CYAPCO complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." CYAPCO has

Connecticut Yankee Atomic Power Company CY-15-035/December 14, 2015/Page 2 established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the HNP ISFSI.

10 CFR 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning. Enclosure 1 provides a revised DCE for the H{NP ISFSI that: 1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30(b)(2)(i); 2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii); and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii). In addition, the revised HNP ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination. The revised HINP ISFSI DCE estimates the total cost to decommission the HNP ISFSI to be $19.8 million and $20.3 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.

10 CFR 72.3 0(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the HNP ISFSI, including the key assumptions and the justification for their use.

10 CFR 72.3 0(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. CYAPCO will periodically reassess the decom~missioning cost estimate in accordance with 10 C2FR 72.30(c).

On a periodic basis, CYAPCO will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

CYAPCO has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-2012 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.

Annually, CYAPCO submits the reports required by 10 CFR 50.75(f)(2), 10 CFR 50.82(a)(8)(v) and 10 CFR 50. 82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

10 CFR 72.30(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination. No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the 1SF SI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste

Connecticut Yankee Atomic Power Company CY-15-035/December 14, 201 5/Page 3 are stored in sealed canisters; 4) nuclear activation of the Vertical Concrete Casks (VCCs),

VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning. Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the JINP ISFSI for the management of irradiated fuel and GTCC waste at the HNP ISFSI through 2033.

A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the HINP ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).

If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.

Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Connecticut Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance
3. Total Costs Associated with the HNP 1SF SI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste

Reference:

1. Letter from C. Pizzella (CYAPCO) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (CY-12-064) cc:

D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager J. Semancik, Director, CT DEEP, Radiation Division M. Firsick, CT DEEP, Radiation Division

ENCLOSURE 1 TO CY-15-042 DECOMMISSIONING STUDY OF THE COiNNECTICUT YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Decommissioning Study of the Connecticut Yankee Independent Spent Fuel Sto rage I nstallatio n Prepared for Connecticut Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015

Knight Cost Engineering Services, LLC KCES 2015, 2015-200 Rev. 0 Table of Contents 1.O INTRODUCTION.............................................................................. 3 2.9

SUMMARY

...................................................................................... 4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH............................ 7 4.0 ASSUMPTIONS................................................................................. 8 5.0 SCHEDULE.................................................................................... 10 6.0 PROJECT MANAGEMENT................................................................ 12 6.1 OVERSIGHT STAFF................................................................................. 12 6.2 DECOMMISSIONING GENERAL CONTRACTOR............................................ 13 6.3 SECURITY..........................................................................................1/3

7.0 REFERENCES

................................................................................. 14 APPENDIX A..........................................................................................

15 Page 2 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-I00 Rev. 0 1.0 XNTRODUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Connecticut Yankee (CY) Independent Spent Fuel Storage Installation (ISFSI).

This estimate includes only the structures, systems and land within the NRC licensed area. The CY ISFSI is located about three quarters of a mile from the former reactor site, tucked in a slight valley between natural ridgelines. The NAC-MPC fuel storage and transport canister system chosen by CY is licensed by the NRC for both storage and transportation.

There are 43 dry storage casks on the 100 by 200-foot, three-foot-thick concrete pad at the CY ISFSI. Forty of the casks contain the 1019 spent fuel assemblies and three casks store sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a three and a half-inch steel liner surrounded by 21 inches of reinforced concrete.

Page 3 of 15

Knight Cost Engineering Services. LIC KE 05 0510Rv KCES 2015,2015-100 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination. This estimate includes all costs incurred to release the property for unrestricted use.

On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning. The rule became effective on Decemrber 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate. To assist in the implementation of the new rule, the NRC issued NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."

NUREG-1757 does not apply to licensees under 10CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUREG-1713.

It does provide additional information to support the development of the cost estimate. This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG3-1713. In addition, it does take into account the guidelines identified in NUREG-1757.

NUREG-1757 specifies that a contingency of 25% is to be included in the estimate. This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated. Second, the CY site has recently been sueeessfid!!y d ecommissioned, and the land released from the operating license, with the exception of land associated with the ISF SI and a laydown area.

The lessons learned from that project will be incorporated in the CY ISFSI decommissioning. For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Haddam Neck Plant (HNP) Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.3 0(b) was submitted on December 17, 2012. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the HNP ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.

Page 4 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0

4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

The total cost including contingency is $19.8 million, $17.9 million for radiological removal and

$1.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Grand Total Building Tax on General Contractor General Contractor with contingency Site Costs with contingency General Contractor Site Costs CY ISI?,I PERIOD DEPENDENT COSTS 1.1 CY Site Costs 1.1.1I Project Management 1.1.2 Security Staff 1.1.3 Fees 1.1.4 insurance 1.1.5 Legal 1.1.6 Property Taxes 1.2 General Contractor 1.2.1 Decommissioning General Contractor 1.2.2 Waste Packaging and Loading Crew 1.2.3 Equipment & Materials Total Cost S$19,798,942

$715,084

$11,261,167

$7,822,691

$10,237,425

$7,111,538

$17,348,962

$11,553,111

$7,111,538

$2,683,040

$1,532,871

$724,931

$713,728

$200,000

$1,256,968

$4,441,573

$2, 176,599

$1,034,821

$1,230,154

$5,795,851

$19,517

$9,759

$9,759

$122,240

$32,388 Non-Radiological radiological Removal $

Removal $

$17,882,656

$1,916,287

$645,873

$69,211

$10,171,229

$1,089,938

$7,065,554

$757,137

$9,246,572

$990,853

$6,423,231

$688,307

$15,669,802

$1,679,160

$10,434,916

$1,118,195

$6,423,231

$688,307

$654,767

$70,164

$644,648

$69,080

$180,643

$19,357

$1,135,309

$121,659

$4,011,685

$429,888

$5,234,886

$560,965

$17,628

$1,889

$110,409

$11,831 ACTIVITIES 1.3 1.3.1 1.3.2 1.4 1.4.1 Project Engineering Procedure Development and Review - Offsite Preparation of QA and Safety Documents -

Offsite (in parallel with 1.2.1)

Site Mobilization and General Employee Training (GET)

Site Mobilization Page 5 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-I00 Rev. 0

SUMMARY

OF COSTS, conCinxed 1.4.2 1.4.3 1.5 1.5.1 1.5.2 1.5.3 1.6 1.6.1 1.6.2 1.6.3 1.7 1.7.1 1.7.2 1.7.2.1 1.7.2.2 1.7.3 1.7.4 1.7.5 1.8 1.8.1 1.8.2 1.8.3

!1.8.4 1.8.5 1.8.6

!1.8.7 1.8.8 1.8.9 1.9 1.9.1 1.9.2 1.9.3 1.9.4 1.9.5 1.10 1.11 1.11.1 1.12 1.13 General Employee Training Site Specific Training Site Preparation - Performed by Staff Initial Site Survey Setup work areas Decontamination Readiness Review Disconnect all utilities to work areas.

Electrical Ventilation Piping Removal inside security fence Remove EEE Remove VCCs Exterior Concrete Steel liner Remove Concrete Pad Remove Security Fence, Indust. Fence, Light Towers, Intrusion Sys. and Access Rd Remove walkway Removal outside fences Diesel Generator ISFSI Support Building SAS Building Septic System Dnnmnhn*, i Power to SAS Conduit and wire - SAS to pad Remove road inside licensed area Remove vehicle barriers Final Site Survey Str'ucture gone - By DGC Staff Prepare Final Status Survey Plan Soil Sampling Direct Survey Sampling Analysis Prepare Final Status Survey Report Orise Site Release Confirmation Outside areas Backfifll, grade and seed Demolition Crew Demobilization Final Project Report - Offsite

$80,389

$9,463

$17,629

$8,814

$4,407

$2,204

$2,204

$5,178,993

$5,392

$3,271,081

$1,585,685

$1,685,396

$1,759,783

$127,505

$15,233

$384,233

$5,779

$96,259

$50,228

$25,283

$16,866

$6,539

$95,859

$65,366

$22,053

$15,923

$7,961

$1,706

$853

$5,030,864

$148,129

$5,392

$3,271,081

$0

$0

$0

$1,759,783

$127,505

$15,233

$384,233

$5,779

$96,259

$50,228

$25,283

$16,866

$6,539

$95,859

$65,366

$22,053

$25,000

$6,740

$6,740

$22,926

$9,759

$22,580

$20,707

$8,814

$2,420

$6,740

$6,740

$2,219

$945 Page 6 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0 3.9 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate: activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach. Site material quantities for concrete, steel and equipment where developed from site specific drawings. Productivity factors were applied to these quantities to determine activity durations. Labor crews were developed and applied to the material quantities to determine labor costs and person-hours. The activity durations were used to develop a project schedule.

The level of effort costs such as equipment rental and the General Contractor (GC) staff were developed based on the project schedule duration. A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that is included in the cost estimate.

Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment. The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing. This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination. Clean structures will be demolished using mechanical means and disposed of at a local landfill.

In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.

This crew will consolidate, package and prepare containers for transportation.

The waste packaging is estimated to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.

Page 7 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-200 Rev. 0 4.4) ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study.

These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.
2. Concrete volumes were developed from plant drawings.
3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.
5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Connecticut based on the City Cost Indexes for Hartford, CT.
6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).
8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.
9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.
10. Transportation costs for LLW are included in the bulk disposal rate.
11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.
12. The following buildings are disposed of as Clean waste in local landfill at a cost of

$91.80 per ton.

Remove Security Fence, Indust. Fence, Light Towers, Intrusion Sys. and Access Rd Walkway Electrical Equipment Enclosure Diesel Generator ISFSI Support Building Security Alarm Station Page 8 of 15

Knight Cost Engineering Services, LIC KE 05 0510Rv KCES 2015, 2015-i00 Rev.O Septic System Pumphouse Power to SAS Conduit and wire - SAS to pad Road inside licensed area Vehicle barriers

13. All costs used in these calculations were current on September, 2015.
14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.
15. It is assumed that all spent fuel and MPCs will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $1,256,968 per year.
17. Fees are included in the estimate at the current cost of $724,931 per year.
18. Insurance costs are included in the estimate at the current cost of $713,728 per year.
19. Legal costs are eincuded in the estimate at the current cost of $200,000 per year.
20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.

Page 9 oflS5

Knight Cost Engineering Seri~ces, LIC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0 5.0 SCHiEDULE A scenario-specific schedule has been developed for estimate.

Activity durations were determined based on the unit cost factor approach.

Plant material inventory quantities were developed from site specific material. Unit rates for cost,, man hours and schedule hours were applied to the material quantities.

From this calculation the removal or decontamination cost, total man hours and total schedule hours were determined for an activity.

The schedule hours are then entered into the schedule to determine project duration. Two work crews are assumed for the concrete pad and concrete overpacks. All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 11.93 months.

Figure 5-1 provides the detailed decommissioning schedule.

Page 10 of 15

Knight Cost Engineering Services, LLC KCES 2015, 2015-100 Rev. 0 Figure 5-1 Project Scheule I

I V

I

~gg 2

P.*.t b~u~

S Pwu.ebr. ~uwle~.uqt ted ft~-

Oikb 4

PIqude. dQA.ad b~'0.wme.k -01kb Sb M.kbdwiind Smuud ~byeeTvmWeg (BUT) mammede.

  • .eudbywTdelrsg U

UbIpsdeTU*lg Sb Piuer*ie..Puftuud ~p~#

I

~I1k BWWi SeW-i--

I OSUfl*ige.Re~ ~ede.

14 WakeI S

Vei~i 1

MeW fl~Th.~dheMebwm Kate. 15 Bind ~w ft~

Cmli Fed

..ee. Fern. Md Tue...

WFU 1kied~

SAB.dd*W a

aa~inWem Pieqiutus Pu..

SAl Cwddwdu41..SMbped Kern 14Mdb ~d ws hub.

brvwBbueuu *eae.j BUC SinS a-

~

P.qm Phd SliMs Suuq Reput

~e bKdims.kiutbi.

  • e1kkbmm
  • ~.Bl~Mdmd miSb~linOindbdefi

~hdPV*d mepad -01kb Sdu*

ThulI,"ll'1 Wed l1*114 BOep Thu 1,211 Wedr 1*11 Idep Tim 112-it4 "rue t1*14 4dsp Wad 112214 Wa. 10'114 24pst Wed 10214 Th.1i22114 1 ep F4 ¶*fl 4 P.1112414 I dey Mun *7/14 M.* 10fl4 l~ap.

Tm 11314*

WeIlrIE jd Tep.* Tue 1s314 71JB14 Qi~et Wll ed IQ12(1 WedilNtlE1 BEEl dips "The 10*4 1he 1ense4 4l 4 dlp.

Th 185014 Tmu 194'04 3.74*

'lr hu 11*1 W ed 3(1*14 I13i dap Wed 311*14 Tu M*14 fI&M d TIes 30(r4 wig to/14 0.781dep Wed 41*14 11w 10014 3.5I1 *Ie The 1851*4 P.191*t4 BA dps P41I81114

,I~n

.2t0914

  • Zdep Mum 21*4 P.'1114 uSd54 FEZ*1114 I~n /SW14 St IdIps Mem21*14 11.4*1*4 321jSo Tle 2L1*.4 Tuoe4Ah14*

4.1'deps Me.l 4114(14 P I44/18/14 Sde1 Tlb 1122*14 Tle 11*1114 Sde'ps Thu 11*11r4 Tlu1111114

$4eps Tuell1tril4 Tue ll1S14 I0dep Tue 1211**14 Tue19*1

-T I/l

,i Ii w

Ii I'

I-

~0 Page 11 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015,2015-100 Rev. O 6.0 PROJECT MCANAGEMENT There arc three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security. The person levels for each are identified below.

6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning. In addition, the staff is augmented with one final status survey resource and one licensing person to assist in the decommissioning.

The staff will provide DGC oversight as well as maintain license compliance. Table 6-1l provides a summrary of this staff.

TABLE 6-1 OVERSIGHT STAFF Staff Number President1 Cask Relicensing Project Manager 1

Workers Concerns Manager 1

Director of Operations 1

ISFSI Manager 1

ISFSI RPM 1

ISFSI Operations Specialist 1

ISESI Administrator 1

Licensing Specialist1 ESS Manager 1

ISFSI Technical SpecialistI Assistant Director of Operations 1

Program Manager 1

Program Manager I

Program Manager I

Public/Government Regulatory Affairs General Counsel1 Licensing Engineer VP CFO & Treasurer Business Administrator1 Accounting Manager 1

Sr. Accountant1 Sr. Accountant1 Benefits I

IT Services 1

Security Manager 1

27 Page 12 of 15

Knight Cost Engineering Services, LLC KCES 2015, 2015-100 Rev. 0 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews, schedule work and supply 1-P support. The DGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a summary of the DGC staff.

TABLE 6-2 DGC STAFF 2015 Base Man Position Salary Level Project Superintendent

$200,000 1.00 QA Auditor/I nspector

$64,000 1.00 Health & Safety Supervisor

$89,205 1.00 Packaging/Shipping Specialist

$66,522 1.00 Cost Control Accountant

$65,071 1.00 Scheduler II

$65,000 1.00 Demolition Specialist

$56,000 1.00 Industrial Safety

$67,000 1.00 Engineering Supervisor

$113,000 1.00 Project Supervisor

$81,000 1.00 Decontamination Tech

$35,000 2.00 Instrumentation Tech

$42,248 1.00 Tool Crib Attendant

$33,976 1.00 14.00 6.3 SECURITY Once spent fuel and GTCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 20:1.5, 2015-100 Rev. 0

7.0 REFERENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.
2. Regulatory Guide 1.202, "Standard Format And Content Of Decommissioning Cost Estimates For Nuclear Power Reactors"
3. NUREG-17 13, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors"
4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."
5. 10CFR 72.30, Financial Assurance and Recordkeeping for Decommissioning
6.

Letter form Carla Pizella (CYAPCO) to Document Control Desk (NRC), Independent Spent Fuel Storage installation Decommissioning Funding Plan, dated December 17, 2012.

Page 14 of 15

/

Ignight Cost Engineering Services, LLC CE20521-00ev0 KCES 2015, 2015-*00 *,ev. 0 APPENIDIX A Page 15 of 15

c4~

1444 CU 14*14..

4414.

2s~

5114.

11.

W..

.. l..

41.

Wa 0$..

CU ti.(1 P~dV.b.

S CU 4*61

$61 4*161 4*.,61 V$a.4*l 44...441 244.1181 7404444 RIa 1*5741 14*

CO 744 CU 04

$51556

$14M

  • U IL'S 5--U*

ON9056ar I~b a-~k 9158$

SIN

'$4-S1~,?

6192*1 SIt.,,

NP'S 567V.

042425 U9$91 W25

$44961

$461751 V.

SI 556 949*17 5341495 3215611 StiSPI 14 t&tU 3*545?

WarN vans 526116?

1414595 5195 Pout IllU1W

$V.tfl49

$119761 049512 pit 543 MOMS MVJUIU 554U45 ItISUIlI 1149I5 Millsa

$461451 013~

SImm

'41759 561SU 95-S--mu LI MSU

  • SI4~~

LONUW.

1551 I Il 5-fl~4 ON a

CU~5-

-U--

a-

-5 maN5-5-

LsNn 7555-1 5157N~~

$56 5-6191 41$06140

~5-9191w I--

  • USIUS 5-75501 61-US-II, 5345-.

049 91V.U.U V.

6142

.49.61.

61 ?.U$44UAWSNU 32 SAM 44S4A..

w.51 Ms

.. a 1115

$135 2551?

1US$

SINS lOUSS?

IN 5961 US?

$901 NEW lASS?

LU SW 56.5?

$901

$11455 26115?

LU SUN NUt 16191 5615 tinS?

19 V.U.*

459 lUllS tAN 24*542 10 SN 0447 1955%

561421

$05?

LU t9N lUll 16101 5614)?

20519 It SR SUM lUSSI P061 taM 1U

$6175 NED ICONS SWAt) iSV It

$195 NW

$95 9149 159 IU SR 2542 jUN11

$1543 SU.$7

'U 5MM USC?

INSEt

$1091 261$?

U SN MIS?

IN.U$

USIS?

249w IN 9161 95*1 INSt 6155 tSP IN SUN Mill 161911 5061 265 P 161 SItS SI?

10491 69611 SUES?

161 U.N SI?

INSt 51545 465.1?

19 S2S.U US?

IU.

50.705 24347 IN SUS 9517 1945$

SUC 261547 19

'SR ml?

61.01 55*0 taP LU

$91?

UP 1Us$

SUMS SUP LU 56.9 551 INtli SUm SUP LU 1911 SUM 1US$

5094 ImP IN 0371 SUM INS

$4.04 2.557 LU

$1424 SM INNS SN~6 SUP IN NSU NW WASI MUltI tall IN NIt SUP

$991' 5121M$

250 161 N.54N 56110 99

  • Qet**

51 422 511 MON l4SUN44 4111 $0

  • N II wu '

4494 544

..4N 44.545 ON I

15 5674 1471 IN.a

$57111 5.5145 0691 N-SUNE ON 41651 ON 515)719 1145 991 11461 NIle 119 5401 Nfl P.295

¶19 591 PSI

$SSSS 119 SCSI 39611 SIISUN 119 5491 591

$4119190110 912.199 --

190400 9415 V.SSUU NON IS $0 LU -

161614 LU 415$

sPa'S P1479 MW'S 104955 11.554 12711.s 911525 5114161 V.14W 611055

=145 SIft'S

$15.97 41*561 1316103 V.21619

$3 10461

'1 5-5-5 124 in.*2SU UA~~

$0.

I-,

5--a

-a 5--ON-ON~

$345-S 614919 2425 6195619*

Nsr 155 N-tlK Ms 61461.5 I

591.81 SUM 1903 1534711 SUB

$4161 SUP INSt

$161410 13555?

59 SUP IN'S PU'S 1.561 I

SN

'SM

$9454 tIaUS Isp I

$141.

4441

$956

$16115 1369 I

$1444

'SI?

$956 14614*1 1*547 I

619 2ND 15.91

$19154 1169 1

$961 2619

$991 PON 11947 I

lltt.

ISV INS LISU 1919 4

UN 391?

$991 P31*8 1.NtM I

SM

'SM INS 56.61

$9714 4

55

'SN 1901

$11131 IONS SUN

'SAY 19615 ISIS 1.541 IA

$417461

?lfl.N 14940 14140 5-*

4*116 ONm

-S S wv 1.44 s..

SINS 04SU

  • 424244 NI 446115 4

51.8$

NW

$901 StUNS 4171 U

I

$519 NW 1956 541451 tall I

51561 SW 1901 5661 taIl 1

569 SUSI 1US$

$161355 24541 59 ON 4$

1455 995 14547 0.51

$I.m 9114

O~mm 0

0l 44 1

0~~aval.

454i0 54-Im 4

4

.,, s.eel 24.0 244 5445.

22-44 5457 4444 RS 025%

tb.4s.

  • 57 tSAWa 0

344.4 24.6.

WO W.v.

C fl.4157, 44.0

~

54.0 54~

fli4 5..

7*.n.

?.4

¶1v

  • 440 5..5457¶ V..544 5.4.2.412 144..47 ?.440

,44..,rn 454444 i7

7.

tS 7,.

7.6 2.547...

  • 2~s5 5

575 5711 52*4 57W 24-3*4 0

  • 22 25.540 570 5457 44 5457 44 577 57*4 54 57 5

7 5454 W

5 5224 52.455 5445 575757 RU 44245 5721724 5440 57.412 R70 57W?

51120 5745424 15*4 540' 4425 RU 4423 0444 57545 57*444211 152)11 44155.4.

0400

~4557~

tWit 2044545 at 4420 Os Rue lOs 55471 fle 4Os 10.71 -

20.7? Ru 15~

24171 Ru 15 4a en 2 445 5.25 -

lOs 5* 4.55 lOs 175 -

042?ian 21*1444

  • *,l *eaw4 50
4244,

¶ 114*

1244*

ot

"+"5 3+m ms m*

15~

¶2 2?54400557 2-4415-5415Os754~

244 042.2?5444 100 Os 442Os 015l4475~

t2 54..54..006' 4454171122 1

00 240 45*4 5522 S

iS 45 5

pip 1525 54 iSQ 5720 11

sin, a

i*

5415 54 41 2*

Wi 54 0

0

.*II16 II 0

45 O

D 177*25 57.427742 574550 11 50 51343 54 54 44425*2 55242*4 1111225 54 522544 11 57 54 54 57 SiSAl?

522545 57245 0757 54~57 a's 44 0244 257 I

52011 54 is I

54554 41 is 72 is 111 4444 47.245 54 245 a

5441 00 5444 10*4 540423 5i57

$22242

.5140 2 11154at 1S2)4at I PaOs~

4415 I 447-44.444 I ORuSOs I 44s44~

4 ~44 2 at44 2 4444Os 4 14402?

~ 444 2~

2001754 11440Os~Os 04.444 7.e~44100 4410.

542 44044*SiiaS¶5 4-2 7-411Os 2 0~

2 445550112-5.

I 755Os 10054 2507-Os I ba, 2 SOs0.e 2 5Os44

¶ 50544-450 2455444544215 2 704415504 4 54444 7 444 4 544i I 415.4

-a 44',-

.e~7-*-

44575444.6 44572 44.2 115 110 5.,P254425.4455 Rb Wipad as e7-1544 30

  • 4 RU 44 P007-054110 5511 4470.52544 RU 447-Oat.

Ru 4475457OsRu 45*

4411Os44.

3m 447~7-~=

1145 447-Os515 50 447-105.0i5 0*

445705Os44 044 110054 as 5545.75 5725*

4457 54.2345 54 0

57.2110 4400*

50 I

4454 14440 754~Os1500 54 245 40 1545 0*

0*

44 700Os44 0*

1154 44.44Os544 540 44444Os44 30 0*

44544004550244 114 5454 44~0W054.0 110

a.

ss,...een.o 513 00 44 7-Os544 1154 0*

44500Os44 0*

345 44 500Os450 1141 0*

4454.4Os0 0*

0*

4454Os 0*

0*

44011Os54 1154 054 447115Os44 520*

572525 1555 SharI 5124*

57110 717*2?

¶0 4114 10 00 44 47 554*145 4415 Sag 47 5440*

RU 4015 520 47 ness 54752.44 RU 54n57 42*

47 32750 575.0 24,5.

5454 54

co0.~IoFa 533.~4e*wO.lt m~4. 0.33.

2.1

(.1 A..

22&.

£33211 0

2.4 94 3496 14%

2.344 192.

33.

s 2.143..

3...

113.

4..

C..

06,433

£2.30 SO 3.2.41 374444¶ 52rn 11*42 93393 233171 0.1123 12.49.4 947 514 047 9...

02.7 0.49.4 MemOS

@7334 3.363 31.0

,a

.e 233 g.e 3.42 10J U5~93*w

03.

932.31 7123630-33 3M 31330433

  • 06**vaai 3.3.

3M flsO.a.n I i6~334 3.3 317133%5 7133535333646 3.3 34 033303.3933 i

3.3 33 W752154

.0335 3M 113.

W1,335236 1.033 33 91610.3033344.3.

3.3 312.33553333

  • 5s&.

33 33 3133b3.,.2..~.

  • 7123@73 33 Mm

%3713536*3633.

@027 33 33 P4

  • @3333234 34 3M

.3330333.53 2310*93311 302 3.3 033333333.

2 6.iMe 1133 151171 92.33 310' 6313 2 *'

833 55411 11113 59342 2?

3.2023 II 1.3773 6

3.3 iWe 302 1.3 1*

¶33 23 213 53340.33 II 3.

110001 112 iW ~

Ill

.3036.3 ill

-m

.5, 13.m~o 640 1

13 13 iS IS

  • 1.3 its s3

@4 iW 63 3

440

  • 3 is 2'

.23 402 23 202 14 3.34 LW, 2

SAC 3.200 5

9 5

uS 0

0 3

01323 i

13 94 5*

66 3.2 97~

a4 2331 9 63.3.1 93.734w 75 33 9331.9.

liStS

-30%

324 IS 024 sn is

a.

w.23211b3b.sfui ilslO#&i 460 23 iitS a

ii440 094

  • 5 23%

iS 43 334 3702 64 74 SAWS 3

3 5435315SO 41114 o.0 us.

3i~3 3

3 MiSS) 3*

307 34

  • 0 3

3*i.0 si.S)9.4 339m 3,+.-+lI 91.01.~

33..

i44 Cr331 2i0 5

4.01 033 04 073 41243 SWeil 330 23 IS 494 302 3M 3M Liii 2

tili still SliM S

50

'3

.03 4946 03654 973.53 033 II 0.93 04113.1 3.063.1, 3362.3 33 23313.1 N.m..

52371

.336 43.14 itS?

33 3 sI 3314 4391 2

9 0

0 I

3 1131909 3.42.544 3

3 PS, if

.w 33 0333.

93...

3.3 0..1 13.31.1 3365 WI 03 93 93 21.6 3.3 3.3 33 0.0133 107*114 3.4@i4 i19 34 33 520-433 hI0-WM A

i..n 3

ian us?

iRMA?

0 9642..

Sit 1433

  • 2539 9330.122 lw

-S ut 33 39 54*

3 3.23 42*10

  • 23.313 53%

12346 33 35 331

'S mb

  • 555333.

73107 322 intrO 23%

333.

33 3.4133.5 33 5

i.

S 55361 210.5 33 13 03 33 3.3 34 35 33iW237 2f2I3t 1.31W 3.24 3.3 3.3 194.03.3 344113

$3 13 iS Sr lilt 231*4 0

9737.0

  • 45513 54 31331 11431 911323 63173 5152400 1123.73 IliUm i2 243.34 9

Ft 911392.3

.3 462i1.3.t n

33.733 1141120 1241.31.3

.3.3%

46595 13.41 023 521633 23744 i3.3 0333.03233 11331.

333 0*254....

3i3r915 i3tS 29331 1 2465 1.0 640.

33

.3 05 43 346 30 3M 3.3 93 1110513 40402 1392 33 3.02 1950353 42525703 102 13*9 55391 353.33.@04141.21 5.2 57.37 19'4 3moe41t 33r6004,3.231+

el 33 ai3 3311mml 33 93033l 21 3...,6tin..i S

iC 13 243 1.31 2.3 146 33 lit i3,3 2.31£ 9035

.0073472 1331 2.3.

631 533139.

759 190

'moO urn 11723 991 04

13.

23 33 3U33.341 523113 43 1.36 491 53 64 6

i3 703 3333 53 1.36 113 3.3 0.4 33 iS 923 33 03120 13.1113 5449 3.4 1704 34 61 102 3.3 265310333.3413r 4913 iN 103 2

IS 0311 47931 15 30 21143..3%33i3

.93.

Ml 6~51J**l

¶3 itS 212391 302121 9.36 53%

1.23

4..53%

1.3 229 M103334i302l2 3.05 101193 931 3

64 iS 2366 13 43 3

3.

i3.463.0.W67.1S6S3.3.573413,23344...fl 9110 fiStS 9007 3 it 2033.5 73.51.1 5323.5 2.01 33 9.3051 023 305 3.313 130-92 13.233 63 63 33 33 3.0 3.3 ill w316w A

4 13 101

.3 0.3 1.37 Ye 136

$33 63 5133.9 393.'

1332.3.

fl 1 9116474472 23,3.024

.3 7%.7 0..

733eV 01936 2064 i45 503 131.59 55 Ms 1231 1.3 42, wsfbatS.

amMo

¶0014 63

  • 91 W.~49. 3 233 3 S 349.21 lM24 S i2wuSS 331 59107

ai

~601854 40400 3020 Oooao~*oC04 88460. C~

40.22 Ca 444

  • 2204 9*0.

300304.

848.3 Ca LogS Ad 30*2%

80%

1404.

sAd UASta 480430 30900 Wa 040*

$90.

000 11200.

4A*

001 1480 480

  1. 40 020440 44A304 co A..(00o1 202
0.

9.3.0...

804*444 30... 2*444 A*4~444 240.18 W4o0 A4d1 2.0.644

30.
  • 8*00 7.2 4824 4800 720 4042.0 1

nO 1*2480 00 48.30

$4049.0 0*0133 209)0*1 30 3030 3024 180 U.S A

C

  • m a

2.713 8

4 31430 30

$33190

$13090 04 30 30430*

$304~43 0

4 9*4 80 30

  • 30 30 04.042 0

0%

03.776 117*

100,8.

dOS 244 04.4.20 MOn 0

  • 0202424 408200 a

A80 000 a

24.2 41240 104946 8.0%

9133 114 4*4 0%

90 40 dOt 47*0 0.64 9030%

23.71 80

  • 0 600 430 430 dOS 120 11010

-0*4%

300 030 2630

~0100 1

030 I*030130.oO 0*112.0)0% 39.9 3060 Th.,084600a10013101004030010980408040309i 3021 44 330 InSt 10010 9040h 00 fayt AdOS 2000 1431130 3041 04 30*0 09071 3793.0 01148 80 80 8*4 0*4 30*4 3030 0*4 3

40 930

  • 481 SI 830 a a

.a 04

%i309 AS 303.

1020.00W Va tO t

800309.0 800.

0*40 431010

.44*0%

0300 3*4

  • 40 040404 1

4378*4 309*00

.00%

1070 410 30.0 3.0%

1 3.20 1830130 2*30%

$141.4 04 0*0 dO 90130 247 1

30 43*013 00300000304118flAS04.A 0060 80150010 40003000030. 030*48006084004800349900..00030 I

(tO 4*430120%3030,3081 13324338109.20260 09308302600030,0A1880.10880flb800448002304009 1*4 3130 30330000081.04113431 9.8.

3000340 Ca 43e4 010002*4 a

no..

0410001 088000 91.03.3; no 4543 030 3080 34219*0 38*0 030 3030*0 330.01430 00*030 0

80 9.30 346 90*4 030 08*4 080 2*

4*4 7434

  • 0 80 VOl 0000 0

08221 Wa 380%

310 2954*1 00 4231~fi 88000240 080340 000 80710003.

0.5

£01100 1

OflO Oslo

  • 4*4%

743*0 330 38.30 4.00%

¶ on a.oua.Oo.30 nun 08,4.4... 94,201 04500188.3011

.S.000434308042908090000A 1

41830 17*3130

.20*4%

11196 40 310 3046.

I 1*9 4.30*4420b00.3041 93*4 9.

304.l 0.60 418030o040~n.10300%066300450.4016430edt 2000.820 330 1130 00%

88*0 80 13000 0300 40 349 01330.3030 $1010.0 449 01 01*4 8*4%

000 80 800 SAS 40 90 30122.030.$14340301818 9

80 1000 8104*4

.300%

1220 1*0 0.0 0800 40 30*4 48S~11 40360830 44

.0 8*4%

030 4*4 4.3 000018 430 1130 0 1030*4 000*

110

'45 8*4%

30 030 01 200%

40 4130 4442$14300 60)10 3.240 4.804.

280.

2f8AS 0030030.0 4010.80 4.1040 1604 Ca 130010 9.41.10 434 0230 012084 37*00 31324*

IOWa 80 40 00 300 43*4 30*4 080 4

0 130 010 374 030 49 A. a 430400 64 2463022 438 40,0.4 Cant 20082024 84.448 Us a

02t a

87 80.4.0030.

8.7*0 30%

830 80 20 303080 4*4 AS 46433000212301S0%

0.40.4.80

  • 64 20 600 310 80 10 4.280 10 302 0132n803 4130110210 0000 9.743 4.0%

8.0 9.0 1.90 00410%

10 0*0 202200039 00,40%

30150300 01 30%

044 10 03 8.3.012 10

92) 01342133181360 044 184 34300 43030 812 4

10 430 6060%

01 00%

0*4 00 8.90 0410460 40 041 343004313011144 44030 2034130 6010 114 080.401 40330.0 no 1104)

Ca 80 04*0 330 90*4 0446 908.30 83030 0.4600%

4.0 40 8.30 90.0 30.0 30*4 3030 3

23 40 030 422 00 237 0 Ca 00.004 44 10*4.42 438 0.10.4 AS 304 480418024 £00.30 8001 04.1

  • 20 247 0.004*.

80 140%

21110 83

  • 30
30.

130 4*0 OlZa.oSI.A241 1013120

.AS04 80 0*4%

80 80 20 37104622 130 4*0 20230803003018130%

an.

a 03 7

830%

3.42 9.0 10 LAS 430 40 201,,so.44830301183184 80%

630 30%

8*4 23 4*0 00104634 430 92*

20246330031300143030 3004 A0 3130 88304 dOts 24.0 3042300*.

20%.S 14s90.8 no 1804 Ca 430 2008 8*0 903.

033.

8084 360.42 004800 80 8*4 830 9046 0*4 3030 30*4 0

42 40 91*0 71 40

'118044

  • 0440 34 80%,

904135

  • 01.300 l7*ao& 34 Va04 AS 1890*0.0 a

242 4804.40430.

230 40%

80 40 20 3094*30 10 430 3433000003011100%

0800080 0

4 40%

30 9.0 404 LAS 40

'2 31*2108260.0*41182188 dO 9.10 4608 8*4 30 4*0 0,9404 10 830 010660..44030120%

309.60 0

814.3 0

846.04 3.40 4.30m~

I.3 30*0030 389 dO o-eaa n..

ioas no tao 4*4 346 8.0 90.0 0940 37*0 30*0 4*4 80 8.30 110 3030 18*0 30*4 0

In 40 9120 113 230 2444448 38.44 44 234 98030 AS 39.0 Va 0024

$804 US 40' 184.1%

09.8 AS 20.1 310 0.0%

330 80

  • 0 0*80 430 044 18103084U21030900%

30*

440 80%

1320 430 408 LAS 130 1012 312..0008030306.94390 0.130 0*494.

030 0*4 9*0 00280%

10 1*0 3612003130304*00 132*4 AU 194.00 00.304 30 180 43)0 Idi 280 4260430 4100.

30.3403040.

vrr.o i

no 808 Ca 430 17220 8.43 900 043 30092 5.9020 4.30 00 8.0 030 00 3030 300 43.4 06Va4401 0

0 446 012 10 9.0 00%.500 9.0t24133043010 890 a

.080 04 044

  • 10 dOlts 3041301 2.000.

804 26030000 AS Ca 2300) 01*44 13.313 8018

.130%

32030 380 a

81.80 401*4 300 dO 34383.30 2000 9* OdOUR nO 19003000 0

ASS Ca 0.010 fl SO 44.90*4 40200 012077 4800*44 40

  • 0 300 3030 3030 30*8 418 AS.85430 0

20 930 039 01 0

I 204.10120 0AS44570.130803 4a010083m 101 oOfo..%.

8030 a24 v.a 00 010302 101140 401008 0000 8

  • 30004 404 OCant Ca 230.00 I

00 143030

  • 4*4%

00 30 100 00800 Ca 04 4

030 9.23030

  • 400 310 030 23*0 3144.04 Ca 290208 034.34 30%

24.0 130 430 30 Ca 600600%

12030 8*0%

4*4 018 80 30 094.02 30 011030 0I 44 2243 *412301%.900419.12000 3742 I*kMO 09.00 82830 1

030 100342000004.2046 18*0608002.030 106000*600AS404.ofI40500402,040A042A01008 1

421 00042000~0303046 1230463130.290*

0.*2800AS40018 a6160041.0040309.

ccel

-m a: tat*o Cb

h.

m c

is 02 PSm t

-MA+..

-IP.

i.

iCiC ieiA C-i O

C C

C a

4U ifl OO10 00II lmU t

t t

O I

0.

it tmiw.P..moein..m.StWCSq tat pnma~

.nmii it; mm tam Oem tam tO mPwiC-CW.mC-t 01.

a to IC 0.-

S... a.

C1 aI m

u to..

to 100 4

C Oo.flw.e-n o

~.Snt~kt.to.flI ml dmt.C.i.t..eCtatt SC tnic tarn Ca Caew.w.

mom wIeCO.

W 310w.

IStam I to me w.o..et.

C C

WCt.St..taIt N

tilt SW ISC 110 IWO zig IS OS tO C

is tic em

  • t tICS tO Itte IN Ste mite.

aeeo

  • itmlitn tot Ce newt ftt tot

~

PS OUSt COW 00 CO 000 wUSPOt tO a

inbl...SiUittotIO SUn 0CC 00 CO Vim SiCtEm 10 C

CmwflhwitIIICm ow Ce tow w

w w

C w

m e

Ste 5.10 N*

N*

m*

a o

wot.0

i.

ol~st.

1o0*.5

  • ~+ olii i l.i lOO
  • i+;z..:

~r C~iO~..w lose ie w to

,.o I~nmol t,

cc tomi C-wi I

aSe ion to iI22laC.A.

00 Ctpmi~.eo I 0004 twit t~

Sw v-mcc~e...

we iwilItt.mC.teO I Cosretmo we P.OCCm.eCeo

~

mm ret p.1dt3..0ine p.~mtoe we oreTawom.oot.

I mine eC nem.~

I Ce~

Sm toPItwimew am

~

C C.~Ta toO t.inimite

~

me imie..wi 00 toP.tmwamm 2 55CC-sam men z

mt.

ma.

2 SC tIlCig 2

51*0 0002 or

slim, OOtSCOla C

4 Cm.emmettlet.0 4

Ia ISfhaike.C a

r, I,

C to i

31.1CC atoaxe iO.S mitit COltS I'

Pllwinumi.

ti 1nee 41wvm C-a~/m C.C SIne ri.11.C a

em ito am IC to 00mm Pm~

20 0

SO e

10 Wa C

I Cmi.C C

110 520 0

SOC C

IC CCI C

I WAti tC 51w CO.

ENCLOSURE 2 TO CY-15-042 CERTIFICATION OF FINANCIAL ASSURANCE

CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee:

Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation NRC No. DPR-61 (N-RC Docket No. 50-213) 362 Injun Hollow Road East Hampton, CT 06424-3099 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Connecticut Yankee Atomic Power Company is the licensee for the Haddam Neck Plant (HINP) Independent Spent Fuel Storage Installation (1SF SI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the HNP ISFSI.

During the operation of this 1SF SI, spent nuclear fuel and Greater than Class C waste will be stored at the HNP ISFSI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated cask~s will ultimately be removed from the ISF SI location, and HNP will dispose of other radiological waste in accordance with NRC regulations, at which time the HINP ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund HNP ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in the letter to which this Certification is attached. That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of:

HNP ISFSI

$17.9 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella

  • e Connecticut Yankee Atomic owe Company Vice President, Chief Financial Officer, and Treasurer Phone (860) 267-6426 x304 Corporate Seal1 Date

\\*l*,Jk

ENCLOSURE 3 TO CY-15-042 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRA)LA TED FIJL _AJ*. GTCC WASTE

2013 -2033 Summary (UN ESCALATED)

Coonnetiout Yankee Atomic Power Company Irradited Fool & GTCC Waste Monagement and [SPSt Decom Estimote Repmesented In 2016 Dollaom 0ERC Summary Oem of 2010 Scm of 2017 Som of 2010 Scm of 2019 Scm of 2020 Scm of 2021 Scm of 2022 Sam of 2023 Scm of 2024 Som of 2020 Som of 2026 Scm of 2027 Sam of 2020 Sam of 2029 Scm of 2020 Scm of 2031 Scm of 2032 Scm of 2033 Sam of Total 2013 -2932 Conthngency 0723.040

$730,992

$572,100

$0000073 0002.040 0573.100 0073.100

$072,100

$073,100 0012.034 0073,150

$573.100 0573,150

$710,020

$500,612 01.431.677 0401.253 011,070,375 GO Metds

$1,000,320

$1,895,329 01,895,328

$1,095,328 01,090.328 01,095,328 01,005,220 01,895,320 01.005,320 01,005.320 01,050.320 01,095,320 01,095,320 01,005.320

$1,090,320

$1,095,320

$0

$30,325,240 Insurance 0000,084 0000,004

$900,904 0600,004 0000,904 0000,904

$600,084

$5000,984

$000,004

$000,984 0000,904

$000,904

$000,004

$000,994 0000,004 0000,004 0050,073

$10.569,710 Labor - Non-Manuaol

$1,059,575 21,050,575

$1,059,575

$1,050,575 01,859.575

$1,059,575

$1,809,575

$1,050,570 01,009,079 01,009,0705$1,059.0705$1.059,570 01,859,570

$1,009,570

$1,000,075 01,059,575

$902,000 030,050,040 Laber -Secarity 03.009,200 03,378.235 53,370,238

$3,370,2330 03,370,230

$3,370,230 53,370,230 03.370,226

$3,376,235 03.370.236 03,376.236

$33.370,2330 03,270,230

$3,370,230 03.370,230 03,370,326

$0 053,713,841 Legal ServIces 0215,370

$215,370 0210,378

$210,370

$210,070 0210,378 9215,378 0215,378

$215,370 5315,370 0218,370

$210,370 9210,378

$215,370 0215,378 0310,378 0538,445 03,984,400 Materials & Supplies 0102.305

$102,305 0102,305 0102,305

$102,305 0102,300 0102,300 0102,309

$102,300 5102,205 0102,308 0102,305 0102,3005 2,055,060 0102,308 0103.305 95,384

$4,496,018 Miscetlaneo us 0100.238 0100,228 0108,228

$100,220

$100,330

$100,339 9108,328 0108,328 0108,330 0108,320 0100,228 0108,338 0108,228

$108.220 0100,3286 0108,338

$71,013 01,803,283 Outside Servicec -A&G 01.078,799 01,879,789 9002.908 0502,900 0021,030 0002,900 0002,000 0002,900 1002,008

$5053,000 0502.008 0002,908 0502,000 0002,000 0502,008 95003.900 0303,373

$10.702,408 Outside Serttces - Fool Leading 50 00

$0

$0

$0 00

$0

$0 30

$0

$0

$0 00

$0 90

$2,310,310

$0

$2,318.318 Outside Serviues - ISF01 OP's 03,850,014

$3,000,914 0015,581 0010,901 0010.801 0015,901 0015,01 6t,81 8415,981

$015,90 1

$615,901 0015, 981

$010,981 005,01 010,001 0015,001 0019.001 003.097

$14,419,500 Outside Services - Legal

$00,151 960,191

$00,101 0024,097 9309,374 080,151

$000,101

$00,151 000,101

$893,081 306,151 086,151 080,101 080,101

$355.374

$824,097 51,108,197 04,910,621 Outside Servires -N0O4-RAD D&Ddo

$0

$0

$0

$0 00

$0 90 90

$0 00

$0

$0 98

$0 00 00 91,904,104 90

$1,844,104 Outside Services - RA$ D&D of ISF51 50 90

$0

$0

$0

$0

$0 56

$0

$0

$0

$0 00

$0

$0 00

$10,328,733,

$0

$10.329.723 FropertyTaxes

$1,202,208 01.292,209 01.292,289 31,292,269

$1,202,209 01.292,209

$1,292,200

$1,292,209 01.292,2609$1.393,209 01,203.360

$1,202,269 21.292.209

$1,202,209 91,293,269 01,292,209 0430,700 921,107,084 Regulatory Peas 0743.000 9743,000

$743,085

$743,055 0743,000 3743,050

$743,080

$743,000

$743,080

$743,000 0743,099

$743,050

$743,055 9743,050 0743,080 0743,005 0371,527

$12,200,400 utgLte s 004,013 004,013

$04,813 004,013 304,013 004,813 904,013

$04,613 064,013 004,613

$04,613 004,012

$04,813

$64.013 364,013 004,013 564.613

$1,088,428 Grand Total 010,190,047

$18,918,824

$12,030,1060

$12,001,027

$12,443,007 912,80,6100 $12,90,8100 012,030,100 $12,030,100 $12,884,211 012.030.1100 $12.036,100 912,030,100 018.032.008 012,218.043 010,740,440 020,283,917 00.403.784

$223,731,497 Check 0um

$233, 73t1,490 Note 1: The cost ol management ot merdiated tuel and GTCC waste is calculatod as tollows:

3 3233,731.400 Grand Total tram Above 11,904.1041 Non-Rod D&D ISFSI 0

tlO,320,7221 Rod DOD ISF51 9

213,437,573 Management of Irradiated Fuel and GTCC Wasto Note 2: The nest ofRAG and NON-SAD DOD el the ISF51I n 2010 dollars as pronided in the column labeled 'Sum oft2O3r Is dottved by oscalating the naive ofthe cost eshmrrtes provided in Encloscre 1 0y32,5%.

Solo 3: This Sommory Combires CY's 2013 Approved PESO Rate Case writh the Knight Ccst Engineering Services 2015 SAD end NON-Rod [SPSt Decom Cost Estimate

CONNECTICUT YANKEE ATOMIC POWER COMPANY

~HADDAM NECK PLANT PLANT 362 INJUN HOLLOW ROAD u EAST HAMPTON, CT 06424-3099 December 14, 2015 CY-1 5-042 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk, U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation NRC License No. DPR-61 (NRC Docket No. 50-213)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Connecticut Yankee Atomic Power Company (CYAPCO) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Haddam Neck Plant (HINP) 1SF SI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original JiNP ISFS *I DFP on December 1-7, 2012*,,,.'"

(Reernc 1*.,,,

). It includesh~n adjus*,*,tmet to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the HNP ISFSI remains unchanged.

10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates.

Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

In addition, CYAPCO complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." CYAPCO has

Connecticut Yankee Atomic Power Company CY-15-035/December 14, 2015/Page 2 established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the HNP ISFSI.

10 CFR 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning. Enclosure 1 provides a revised DCE for the H{NP ISFSI that: 1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30(b)(2)(i); 2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii); and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii). In addition, the revised HNP ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination. The revised HINP ISFSI DCE estimates the total cost to decommission the HNP ISFSI to be $19.8 million and $20.3 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.

10 CFR 72.3 0(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the HNP ISFSI, including the key assumptions and the justification for their use.

10 CFR 72.3 0(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. CYAPCO will periodically reassess the decom~missioning cost estimate in accordance with 10 C2FR 72.30(c).

On a periodic basis, CYAPCO will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

CYAPCO has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-2012 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.

Annually, CYAPCO submits the reports required by 10 CFR 50.75(f)(2), 10 CFR 50.82(a)(8)(v) and 10 CFR 50. 82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

10 CFR 72.30(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination. No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the 1SF SI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste

Connecticut Yankee Atomic Power Company CY-15-035/December 14, 201 5/Page 3 are stored in sealed canisters; 4) nuclear activation of the Vertical Concrete Casks (VCCs),

VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning. Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the JINP ISFSI for the management of irradiated fuel and GTCC waste at the HNP ISFSI through 2033.

A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the HINP ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).

If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.

Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Connecticut Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance
3. Total Costs Associated with the HNP 1SF SI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste

Reference:

1. Letter from C. Pizzella (CYAPCO) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (CY-12-064) cc:

D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager J. Semancik, Director, CT DEEP, Radiation Division M. Firsick, CT DEEP, Radiation Division

ENCLOSURE 1 TO CY-15-042 DECOMMISSIONING STUDY OF THE COiNNECTICUT YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Decommissioning Study of the Connecticut Yankee Independent Spent Fuel Sto rage I nstallatio n Prepared for Connecticut Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015

Knight Cost Engineering Services, LLC KCES 2015, 2015-200 Rev. 0 Table of Contents 1.O INTRODUCTION.............................................................................. 3 2.9

SUMMARY

...................................................................................... 4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH............................ 7 4.0 ASSUMPTIONS................................................................................. 8 5.0 SCHEDULE.................................................................................... 10 6.0 PROJECT MANAGEMENT................................................................ 12 6.1 OVERSIGHT STAFF................................................................................. 12 6.2 DECOMMISSIONING GENERAL CONTRACTOR............................................ 13 6.3 SECURITY..........................................................................................1/3

7.0 REFERENCES

................................................................................. 14 APPENDIX A..........................................................................................

15 Page 2 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-I00 Rev. 0 1.0 XNTRODUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Connecticut Yankee (CY) Independent Spent Fuel Storage Installation (ISFSI).

This estimate includes only the structures, systems and land within the NRC licensed area. The CY ISFSI is located about three quarters of a mile from the former reactor site, tucked in a slight valley between natural ridgelines. The NAC-MPC fuel storage and transport canister system chosen by CY is licensed by the NRC for both storage and transportation.

There are 43 dry storage casks on the 100 by 200-foot, three-foot-thick concrete pad at the CY ISFSI. Forty of the casks contain the 1019 spent fuel assemblies and three casks store sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a three and a half-inch steel liner surrounded by 21 inches of reinforced concrete.

Page 3 of 15

Knight Cost Engineering Services. LIC KE 05 0510Rv KCES 2015,2015-100 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination. This estimate includes all costs incurred to release the property for unrestricted use.

On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning. The rule became effective on Decemrber 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate. To assist in the implementation of the new rule, the NRC issued NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."

NUREG-1757 does not apply to licensees under 10CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUREG-1713.

It does provide additional information to support the development of the cost estimate. This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG3-1713. In addition, it does take into account the guidelines identified in NUREG-1757.

NUREG-1757 specifies that a contingency of 25% is to be included in the estimate. This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated. Second, the CY site has recently been sueeessfid!!y d ecommissioned, and the land released from the operating license, with the exception of land associated with the ISF SI and a laydown area.

The lessons learned from that project will be incorporated in the CY ISFSI decommissioning. For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Haddam Neck Plant (HNP) Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.3 0(b) was submitted on December 17, 2012. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the HNP ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.

Page 4 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0

4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

The total cost including contingency is $19.8 million, $17.9 million for radiological removal and

$1.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Grand Total Building Tax on General Contractor General Contractor with contingency Site Costs with contingency General Contractor Site Costs CY ISI?,I PERIOD DEPENDENT COSTS 1.1 CY Site Costs 1.1.1I Project Management 1.1.2 Security Staff 1.1.3 Fees 1.1.4 insurance 1.1.5 Legal 1.1.6 Property Taxes 1.2 General Contractor 1.2.1 Decommissioning General Contractor 1.2.2 Waste Packaging and Loading Crew 1.2.3 Equipment & Materials Total Cost S$19,798,942

$715,084

$11,261,167

$7,822,691

$10,237,425

$7,111,538

$17,348,962

$11,553,111

$7,111,538

$2,683,040

$1,532,871

$724,931

$713,728

$200,000

$1,256,968

$4,441,573

$2, 176,599

$1,034,821

$1,230,154

$5,795,851

$19,517

$9,759

$9,759

$122,240

$32,388 Non-Radiological radiological Removal $

Removal $

$17,882,656

$1,916,287

$645,873

$69,211

$10,171,229

$1,089,938

$7,065,554

$757,137

$9,246,572

$990,853

$6,423,231

$688,307

$15,669,802

$1,679,160

$10,434,916

$1,118,195

$6,423,231

$688,307

$654,767

$70,164

$644,648

$69,080

$180,643

$19,357

$1,135,309

$121,659

$4,011,685

$429,888

$5,234,886

$560,965

$17,628

$1,889

$110,409

$11,831 ACTIVITIES 1.3 1.3.1 1.3.2 1.4 1.4.1 Project Engineering Procedure Development and Review - Offsite Preparation of QA and Safety Documents -

Offsite (in parallel with 1.2.1)

Site Mobilization and General Employee Training (GET)

Site Mobilization Page 5 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-I00 Rev. 0

SUMMARY

OF COSTS, conCinxed 1.4.2 1.4.3 1.5 1.5.1 1.5.2 1.5.3 1.6 1.6.1 1.6.2 1.6.3 1.7 1.7.1 1.7.2 1.7.2.1 1.7.2.2 1.7.3 1.7.4 1.7.5 1.8 1.8.1 1.8.2 1.8.3

!1.8.4 1.8.5 1.8.6

!1.8.7 1.8.8 1.8.9 1.9 1.9.1 1.9.2 1.9.3 1.9.4 1.9.5 1.10 1.11 1.11.1 1.12 1.13 General Employee Training Site Specific Training Site Preparation - Performed by Staff Initial Site Survey Setup work areas Decontamination Readiness Review Disconnect all utilities to work areas.

Electrical Ventilation Piping Removal inside security fence Remove EEE Remove VCCs Exterior Concrete Steel liner Remove Concrete Pad Remove Security Fence, Indust. Fence, Light Towers, Intrusion Sys. and Access Rd Remove walkway Removal outside fences Diesel Generator ISFSI Support Building SAS Building Septic System Dnnmnhn*, i Power to SAS Conduit and wire - SAS to pad Remove road inside licensed area Remove vehicle barriers Final Site Survey Str'ucture gone - By DGC Staff Prepare Final Status Survey Plan Soil Sampling Direct Survey Sampling Analysis Prepare Final Status Survey Report Orise Site Release Confirmation Outside areas Backfifll, grade and seed Demolition Crew Demobilization Final Project Report - Offsite

$80,389

$9,463

$17,629

$8,814

$4,407

$2,204

$2,204

$5,178,993

$5,392

$3,271,081

$1,585,685

$1,685,396

$1,759,783

$127,505

$15,233

$384,233

$5,779

$96,259

$50,228

$25,283

$16,866

$6,539

$95,859

$65,366

$22,053

$15,923

$7,961

$1,706

$853

$5,030,864

$148,129

$5,392

$3,271,081

$0

$0

$0

$1,759,783

$127,505

$15,233

$384,233

$5,779

$96,259

$50,228

$25,283

$16,866

$6,539

$95,859

$65,366

$22,053

$25,000

$6,740

$6,740

$22,926

$9,759

$22,580

$20,707

$8,814

$2,420

$6,740

$6,740

$2,219

$945 Page 6 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0 3.9 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate: activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach. Site material quantities for concrete, steel and equipment where developed from site specific drawings. Productivity factors were applied to these quantities to determine activity durations. Labor crews were developed and applied to the material quantities to determine labor costs and person-hours. The activity durations were used to develop a project schedule.

The level of effort costs such as equipment rental and the General Contractor (GC) staff were developed based on the project schedule duration. A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that is included in the cost estimate.

Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment. The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing. This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination. Clean structures will be demolished using mechanical means and disposed of at a local landfill.

In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.

This crew will consolidate, package and prepare containers for transportation.

The waste packaging is estimated to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.

Page 7 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015, 2015-200 Rev. 0 4.4) ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study.

These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.
2. Concrete volumes were developed from plant drawings.
3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.
5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Connecticut based on the City Cost Indexes for Hartford, CT.
6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).
8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.
9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.
10. Transportation costs for LLW are included in the bulk disposal rate.
11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.
12. The following buildings are disposed of as Clean waste in local landfill at a cost of

$91.80 per ton.

Remove Security Fence, Indust. Fence, Light Towers, Intrusion Sys. and Access Rd Walkway Electrical Equipment Enclosure Diesel Generator ISFSI Support Building Security Alarm Station Page 8 of 15

Knight Cost Engineering Services, LIC KE 05 0510Rv KCES 2015, 2015-i00 Rev.O Septic System Pumphouse Power to SAS Conduit and wire - SAS to pad Road inside licensed area Vehicle barriers

13. All costs used in these calculations were current on September, 2015.
14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.
15. It is assumed that all spent fuel and MPCs will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $1,256,968 per year.
17. Fees are included in the estimate at the current cost of $724,931 per year.
18. Insurance costs are included in the estimate at the current cost of $713,728 per year.
19. Legal costs are eincuded in the estimate at the current cost of $200,000 per year.
20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.

Page 9 oflS5

Knight Cost Engineering Seri~ces, LIC KE 05 0510Rv KCES 2015, 2015-100 Rev. 0 5.0 SCHiEDULE A scenario-specific schedule has been developed for estimate.

Activity durations were determined based on the unit cost factor approach.

Plant material inventory quantities were developed from site specific material. Unit rates for cost,, man hours and schedule hours were applied to the material quantities.

From this calculation the removal or decontamination cost, total man hours and total schedule hours were determined for an activity.

The schedule hours are then entered into the schedule to determine project duration. Two work crews are assumed for the concrete pad and concrete overpacks. All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 11.93 months.

Figure 5-1 provides the detailed decommissioning schedule.

Page 10 of 15

Knight Cost Engineering Services, LLC KCES 2015, 2015-100 Rev. 0 Figure 5-1 Project Scheule I

I V

I

~gg 2

P.*.t b~u~

S Pwu.ebr. ~uwle~.uqt ted ft~-

Oikb 4

PIqude. dQA.ad b~'0.wme.k -01kb Sb M.kbdwiind Smuud ~byeeTvmWeg (BUT) mammede.

  • .eudbywTdelrsg U

UbIpsdeTU*lg Sb Piuer*ie..Puftuud ~p~#

I

~I1k BWWi SeW-i--

I OSUfl*ige.Re~ ~ede.

14 WakeI S

Vei~i 1

MeW fl~Th.~dheMebwm Kate. 15 Bind ~w ft~

Cmli Fed

..ee. Fern. Md Tue...

WFU 1kied~

SAB.dd*W a

aa~inWem Pieqiutus Pu..

SAl Cwddwdu41..SMbped Kern 14Mdb ~d ws hub.

brvwBbueuu *eae.j BUC SinS a-

~

P.qm Phd SliMs Suuq Reput

~e bKdims.kiutbi.

  • e1kkbmm
  • ~.Bl~Mdmd miSb~linOindbdefi

~hdPV*d mepad -01kb Sdu*

ThulI,"ll'1 Wed l1*114 BOep Thu 1,211 Wedr 1*11 Idep Tim 112-it4 "rue t1*14 4dsp Wad 112214 Wa. 10'114 24pst Wed 10214 Th.1i22114 1 ep F4 ¶*fl 4 P.1112414 I dey Mun *7/14 M.* 10fl4 l~ap.

Tm 11314*

WeIlrIE jd Tep.* Tue 1s314 71JB14 Qi~et Wll ed IQ12(1 WedilNtlE1 BEEl dips "The 10*4 1he 1ense4 4l 4 dlp.

Th 185014 Tmu 194'04 3.74*

'lr hu 11*1 W ed 3(1*14 I13i dap Wed 311*14 Tu M*14 fI&M d TIes 30(r4 wig to/14 0.781dep Wed 41*14 11w 10014 3.5I1 *Ie The 1851*4 P.191*t4 BA dps P41I81114

,I~n

.2t0914

  • Zdep Mum 21*4 P.'1114 uSd54 FEZ*1114 I~n /SW14 St IdIps Mem21*14 11.4*1*4 321jSo Tle 2L1*.4 Tuoe4Ah14*

4.1'deps Me.l 4114(14 P I44/18/14 Sde1 Tlb 1122*14 Tle 11*1114 Sde'ps Thu 11*11r4 Tlu1111114

$4eps Tuell1tril4 Tue ll1S14 I0dep Tue 1211**14 Tue19*1

-T I/l

,i Ii w

Ii I'

I-

~0 Page 11 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 2015,2015-100 Rev. O 6.0 PROJECT MCANAGEMENT There arc three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security. The person levels for each are identified below.

6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning. In addition, the staff is augmented with one final status survey resource and one licensing person to assist in the decommissioning.

The staff will provide DGC oversight as well as maintain license compliance. Table 6-1l provides a summrary of this staff.

TABLE 6-1 OVERSIGHT STAFF Staff Number President1 Cask Relicensing Project Manager 1

Workers Concerns Manager 1

Director of Operations 1

ISFSI Manager 1

ISFSI RPM 1

ISFSI Operations Specialist 1

ISESI Administrator 1

Licensing Specialist1 ESS Manager 1

ISFSI Technical SpecialistI Assistant Director of Operations 1

Program Manager 1

Program Manager I

Program Manager I

Public/Government Regulatory Affairs General Counsel1 Licensing Engineer VP CFO & Treasurer Business Administrator1 Accounting Manager 1

Sr. Accountant1 Sr. Accountant1 Benefits I

IT Services 1

Security Manager 1

27 Page 12 of 15

Knight Cost Engineering Services, LLC KCES 2015, 2015-100 Rev. 0 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews, schedule work and supply 1-P support. The DGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a summary of the DGC staff.

TABLE 6-2 DGC STAFF 2015 Base Man Position Salary Level Project Superintendent

$200,000 1.00 QA Auditor/I nspector

$64,000 1.00 Health & Safety Supervisor

$89,205 1.00 Packaging/Shipping Specialist

$66,522 1.00 Cost Control Accountant

$65,071 1.00 Scheduler II

$65,000 1.00 Demolition Specialist

$56,000 1.00 Industrial Safety

$67,000 1.00 Engineering Supervisor

$113,000 1.00 Project Supervisor

$81,000 1.00 Decontamination Tech

$35,000 2.00 Instrumentation Tech

$42,248 1.00 Tool Crib Attendant

$33,976 1.00 14.00 6.3 SECURITY Once spent fuel and GTCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15

Knight Cost Engineering Services, LLC KE 05 0510Rv KCES 20:1.5, 2015-100 Rev. 0

7.0 REFERENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.
2. Regulatory Guide 1.202, "Standard Format And Content Of Decommissioning Cost Estimates For Nuclear Power Reactors"
3. NUREG-17 13, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors"
4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."
5. 10CFR 72.30, Financial Assurance and Recordkeeping for Decommissioning
6.

Letter form Carla Pizella (CYAPCO) to Document Control Desk (NRC), Independent Spent Fuel Storage installation Decommissioning Funding Plan, dated December 17, 2012.

Page 14 of 15

/

Ignight Cost Engineering Services, LLC CE20521-00ev0 KCES 2015, 2015-*00 *,ev. 0 APPENIDIX A Page 15 of 15

c4~

1444 CU 14*14..

4414.

2s~

5114.

11.

W..

.. l..

41.

Wa 0$..

CU ti.(1 P~dV.b.

S CU 4*61

$61 4*161 4*.,61 V$a.4*l 44...441 244.1181 7404444 RIa 1*5741 14*

CO 744 CU 04

$51556

$14M

  • U IL'S 5--U*

ON9056ar I~b a-~k 9158$

SIN

'$4-S1~,?

6192*1 SIt.,,

NP'S 567V.

042425 U9$91 W25

$44961

$461751 V.

SI 556 949*17 5341495 3215611 StiSPI 14 t&tU 3*545?

WarN vans 526116?

1414595 5195 Pout IllU1W

$V.tfl49

$119761 049512 pit 543 MOMS MVJUIU 554U45 ItISUIlI 1149I5 Millsa

$461451 013~

SImm

'41759 561SU 95-S--mu LI MSU

  • SI4~~

LONUW.

1551 I Il 5-fl~4 ON a

CU~5-

-U--

a-

-5 maN5-5-

LsNn 7555-1 5157N~~

$56 5-6191 41$06140

~5-9191w I--

  • USIUS 5-75501 61-US-II, 5345-.

049 91V.U.U V.

6142

.49.61.

61 ?.U$44UAWSNU 32 SAM 44S4A..

w.51 Ms

.. a 1115

$135 2551?

1US$

SINS lOUSS?

IN 5961 US?

$901 NEW lASS?

LU SW 56.5?

$901

$11455 26115?

LU SUN NUt 16191 5615 tinS?

19 V.U.*

459 lUllS tAN 24*542 10 SN 0447 1955%

561421

$05?

LU t9N lUll 16101 5614)?

20519 It SR SUM lUSSI P061 taM 1U

$6175 NED ICONS SWAt) iSV It

$195 NW

$95 9149 159 IU SR 2542 jUN11

$1543 SU.$7

'U 5MM USC?

INSEt

$1091 261$?

U SN MIS?

IN.U$

USIS?

249w IN 9161 95*1 INSt 6155 tSP IN SUN Mill 161911 5061 265 P 161 SItS SI?

10491 69611 SUES?

161 U.N SI?

INSt 51545 465.1?

19 S2S.U US?

IU.

50.705 24347 IN SUS 9517 1945$

SUC 261547 19

'SR ml?

61.01 55*0 taP LU

$91?

UP 1Us$

SUMS SUP LU 56.9 551 INtli SUm SUP LU 1911 SUM 1US$

5094 ImP IN 0371 SUM INS

$4.04 2.557 LU

$1424 SM INNS SN~6 SUP IN NSU NW WASI MUltI tall IN NIt SUP

$991' 5121M$

250 161 N.54N 56110 99

  • Qet**

51 422 511 MON l4SUN44 4111 $0

  • N II wu '

4494 544

..4N 44.545 ON I

15 5674 1471 IN.a

$57111 5.5145 0691 N-SUNE ON 41651 ON 515)719 1145 991 11461 NIle 119 5401 Nfl P.295

¶19 591 PSI

$SSSS 119 SCSI 39611 SIISUN 119 5491 591

$4119190110 912.199 --

190400 9415 V.SSUU NON IS $0 LU -

161614 LU 415$

sPa'S P1479 MW'S 104955 11.554 12711.s 911525 5114161 V.14W 611055

=145 SIft'S

$15.97 41*561 1316103 V.21619

$3 10461

'1 5-5-5 124 in.*2SU UA~~

$0.

I-,

5--a

-a 5--ON-ON~

$345-S 614919 2425 6195619*

Nsr 155 N-tlK Ms 61461.5 I

591.81 SUM 1903 1534711 SUB

$4161 SUP INSt

$161410 13555?

59 SUP IN'S PU'S 1.561 I

SN

'SM

$9454 tIaUS Isp I

$141.

4441

$956

$16115 1369 I

$1444

'SI?

$956 14614*1 1*547 I

619 2ND 15.91

$19154 1169 1

$961 2619

$991 PON 11947 I

lltt.

ISV INS LISU 1919 4

UN 391?

$991 P31*8 1.NtM I

SM

'SM INS 56.61

$9714 4

55

'SN 1901

$11131 IONS SUN

'SAY 19615 ISIS 1.541 IA

$417461

?lfl.N 14940 14140 5-*

4*116 ONm

-S S wv 1.44 s..

SINS 04SU

  • 424244 NI 446115 4

51.8$

NW

$901 StUNS 4171 U

I

$519 NW 1956 541451 tall I

51561 SW 1901 5661 taIl 1

569 SUSI 1US$

$161355 24541 59 ON 4$

1455 995 14547 0.51

$I.m 9114

O~mm 0

0l 44 1

0~~aval.

454i0 54-Im 4

4

.,, s.eel 24.0 244 5445.

22-44 5457 4444 RS 025%

tb.4s.

  • 57 tSAWa 0

344.4 24.6.

WO W.v.

C fl.4157, 44.0

~

54.0 54~

fli4 5..

7*.n.

?.4

¶1v

  • 440 5..5457¶ V..544 5.4.2.412 144..47 ?.440

,44..,rn 454444 i7

7.

tS 7,.

7.6 2.547...

  • 2~s5 5

575 5711 52*4 57W 24-3*4 0

  • 22 25.540 570 5457 44 5457 44 577 57*4 54 57 5

7 5454 W

5 5224 52.455 5445 575757 RU 44245 5721724 5440 57.412 R70 57W?

51120 5745424 15*4 540' 4425 RU 4423 0444 57545 57*444211 152)11 44155.4.

0400

~4557~

tWit 2044545 at 4420 Os Rue lOs 55471 fle 4Os 10.71 -

20.7? Ru 15~

24171 Ru 15 4a en 2 445 5.25 -

lOs 5* 4.55 lOs 175 -

042?ian 21*1444

  • *,l *eaw4 50
4244,

¶ 114*

1244*

ot

"+"5 3+m ms m*

15~

¶2 2?54400557 2-4415-5415Os754~

244 042.2?5444 100 Os 442Os 015l4475~

t2 54..54..006' 4454171122 1

00 240 45*4 5522 S

iS 45 5

pip 1525 54 iSQ 5720 11

sin, a

i*

5415 54 41 2*

Wi 54 0

0

.*II16 II 0

45 O

D 177*25 57.427742 574550 11 50 51343 54 54 44425*2 55242*4 1111225 54 522544 11 57 54 54 57 SiSAl?

522545 57245 0757 54~57 a's 44 0244 257 I

52011 54 is I

54554 41 is 72 is 111 4444 47.245 54 245 a

5441 00 5444 10*4 540423 5i57

$22242

.5140 2 11154at 1S2)4at I PaOs~

4415 I 447-44.444 I ORuSOs I 44s44~

4 ~44 2 at44 2 4444Os 4 14402?

~ 444 2~

2001754 11440Os~Os 04.444 7.e~44100 4410.

542 44044*SiiaS¶5 4-2 7-411Os 2 0~

2 445550112-5.

I 755Os 10054 2507-Os I ba, 2 SOs0.e 2 5Os44

¶ 50544-450 2455444544215 2 704415504 4 54444 7 444 4 544i I 415.4

-a 44',-

.e~7-*-

44575444.6 44572 44.2 115 110 5.,P254425.4455 Rb Wipad as e7-1544 30

  • 4 RU 44 P007-054110 5511 4470.52544 RU 447-Oat.

Ru 4475457OsRu 45*

4411Os44.

3m 447~7-~=

1145 447-Os515 50 447-105.0i5 0*

445705Os44 044 110054 as 5545.75 5725*

4457 54.2345 54 0

57.2110 4400*

50 I

4454 14440 754~Os1500 54 245 40 1545 0*

0*

44 700Os44 0*

1154 44.44Os544 540 44444Os44 30 0*

44544004550244 114 5454 44~0W054.0 110

a.

ss,...een.o 513 00 44 7-Os544 1154 0*

44500Os44 0*

345 44 500Os450 1141 0*

4454.4Os0 0*

0*

4454Os 0*

0*

44011Os54 1154 054 447115Os44 520*

572525 1555 SharI 5124*

57110 717*2?

¶0 4114 10 00 44 47 554*145 4415 Sag 47 5440*

RU 4015 520 47 ness 54752.44 RU 54n57 42*

47 32750 575.0 24,5.

5454 54

co0.~IoFa 533.~4e*wO.lt m~4. 0.33.

2.1

(.1 A..

22&.

£33211 0

2.4 94 3496 14%

2.344 192.

33.

s 2.143..

3...

113.

4..

C..

06,433

£2.30 SO 3.2.41 374444¶ 52rn 11*42 93393 233171 0.1123 12.49.4 947 514 047 9...

02.7 0.49.4 MemOS

@7334 3.363 31.0

,a

.e 233 g.e 3.42 10J U5~93*w

03.

932.31 7123630-33 3M 31330433

  • 06**vaai 3.3.

3M flsO.a.n I i6~334 3.3 317133%5 7133535333646 3.3 34 033303.3933 i

3.3 33 W752154

.0335 3M 113.

W1,335236 1.033 33 91610.3033344.3.

3.3 312.33553333

  • 5s&.

33 33 3133b3.,.2..~.

  • 7123@73 33 Mm

%3713536*3633.

@027 33 33 P4

  • @3333234 34 3M

.3330333.53 2310*93311 302 3.3 033333333.

2 6.iMe 1133 151171 92.33 310' 6313 2 *'

833 55411 11113 59342 2?

3.2023 II 1.3773 6

3.3 iWe 302 1.3 1*

¶33 23 213 53340.33 II 3.

110001 112 iW ~

Ill

.3036.3 ill

-m

.5, 13.m~o 640 1

13 13 iS IS

  • 1.3 its s3

@4 iW 63 3

440

  • 3 is 2'

.23 402 23 202 14 3.34 LW, 2

SAC 3.200 5

9 5

uS 0

0 3

01323 i

13 94 5*

66 3.2 97~

a4 2331 9 63.3.1 93.734w 75 33 9331.9.

liStS

-30%

324 IS 024 sn is

a.

w.23211b3b.sfui ilslO#&i 460 23 iitS a

ii440 094

  • 5 23%

iS 43 334 3702 64 74 SAWS 3

3 5435315SO 41114 o.0 us.

3i~3 3

3 MiSS) 3*

307 34

  • 0 3

3*i.0 si.S)9.4 339m 3,+.-+lI 91.01.~

33..

i44 Cr331 2i0 5

4.01 033 04 073 41243 SWeil 330 23 IS 494 302 3M 3M Liii 2

tili still SliM S

50

'3

.03 4946 03654 973.53 033 II 0.93 04113.1 3.063.1, 3362.3 33 23313.1 N.m..

52371

.336 43.14 itS?

33 3 sI 3314 4391 2

9 0

0 I

3 1131909 3.42.544 3

3 PS, if

.w 33 0333.

93...

3.3 0..1 13.31.1 3365 WI 03 93 93 21.6 3.3 3.3 33 0.0133 107*114 3.4@i4 i19 34 33 520-433 hI0-WM A

i..n 3

ian us?

iRMA?

0 9642..

Sit 1433

  • 2539 9330.122 lw

-S ut 33 39 54*

3 3.23 42*10

  • 23.313 53%

12346 33 35 331

'S mb

  • 555333.

73107 322 intrO 23%

333.

33 3.4133.5 33 5

i.

S 55361 210.5 33 13 03 33 3.3 34 35 33iW237 2f2I3t 1.31W 3.24 3.3 3.3 194.03.3 344113

$3 13 iS Sr lilt 231*4 0

9737.0

  • 45513 54 31331 11431 911323 63173 5152400 1123.73 IliUm i2 243.34 9

Ft 911392.3

.3 462i1.3.t n

33.733 1141120 1241.31.3

.3.3%

46595 13.41 023 521633 23744 i3.3 0333.03233 11331.

333 0*254....

3i3r915 i3tS 29331 1 2465 1.0 640.

33

.3 05 43 346 30 3M 3.3 93 1110513 40402 1392 33 3.02 1950353 42525703 102 13*9 55391 353.33.@04141.21 5.2 57.37 19'4 3moe41t 33r6004,3.231+

el 33 ai3 3311mml 33 93033l 21 3...,6tin..i S

iC 13 243 1.31 2.3 146 33 lit i3,3 2.31£ 9035

.0073472 1331 2.3.

631 533139.

759 190

'moO urn 11723 991 04

13.

23 33 3U33.341 523113 43 1.36 491 53 64 6

i3 703 3333 53 1.36 113 3.3 0.4 33 iS 923 33 03120 13.1113 5449 3.4 1704 34 61 102 3.3 265310333.3413r 4913 iN 103 2

IS 0311 47931 15 30 21143..3%33i3

.93.

Ml 6~51J**l

¶3 itS 212391 302121 9.36 53%

1.23

4..53%

1.3 229 M103334i302l2 3.05 101193 931 3

64 iS 2366 13 43 3

3.

i3.463.0.W67.1S6S3.3.573413,23344...fl 9110 fiStS 9007 3 it 2033.5 73.51.1 5323.5 2.01 33 9.3051 023 305 3.313 130-92 13.233 63 63 33 33 3.0 3.3 ill w316w A

4 13 101

.3 0.3 1.37 Ye 136

$33 63 5133.9 393.'

1332.3.

fl 1 9116474472 23,3.024

.3 7%.7 0..

733eV 01936 2064 i45 503 131.59 55 Ms 1231 1.3 42, wsfbatS.

amMo

¶0014 63

  • 91 W.~49. 3 233 3 S 349.21 lM24 S i2wuSS 331 59107

ai

~601854 40400 3020 Oooao~*oC04 88460. C~

40.22 Ca 444

  • 2204 9*0.

300304.

848.3 Ca LogS Ad 30*2%

80%

1404.

sAd UASta 480430 30900 Wa 040*

$90.

000 11200.

4A*

001 1480 480

  1. 40 020440 44A304 co A..(00o1 202
0.

9.3.0...

804*444 30... 2*444 A*4~444 240.18 W4o0 A4d1 2.0.644

30.
  • 8*00 7.2 4824 4800 720 4042.0 1

nO 1*2480 00 48.30

$4049.0 0*0133 209)0*1 30 3030 3024 180 U.S A

C

  • m a

2.713 8

4 31430 30

$33190

$13090 04 30 30430*

$304~43 0

4 9*4 80 30

  • 30 30 04.042 0

0%

03.776 117*

100,8.

dOS 244 04.4.20 MOn 0

  • 0202424 408200 a

A80 000 a

24.2 41240 104946 8.0%

9133 114 4*4 0%

90 40 dOt 47*0 0.64 9030%

23.71 80

  • 0 600 430 430 dOS 120 11010

-0*4%

300 030 2630

~0100 1

030 I*030130.oO 0*112.0)0% 39.9 3060 Th.,084600a10013101004030010980408040309i 3021 44 330 InSt 10010 9040h 00 fayt AdOS 2000 1431130 3041 04 30*0 09071 3793.0 01148 80 80 8*4 0*4 30*4 3030 0*4 3

40 930

  • 481 SI 830 a a

.a 04

%i309 AS 303.

1020.00W Va tO t

800309.0 800.

0*40 431010

.44*0%

0300 3*4

  • 40 040404 1

4378*4 309*00

.00%

1070 410 30.0 3.0%

1 3.20 1830130 2*30%

$141.4 04 0*0 dO 90130 247 1

30 43*013 00300000304118flAS04.A 0060 80150010 40003000030. 030*48006084004800349900..00030 I

(tO 4*430120%3030,3081 13324338109.20260 09308302600030,0A1880.10880flb800448002304009 1*4 3130 30330000081.04113431 9.8.

3000340 Ca 43e4 010002*4 a

no..

0410001 088000 91.03.3; no 4543 030 3080 34219*0 38*0 030 3030*0 330.01430 00*030 0

80 9.30 346 90*4 030 08*4 080 2*

4*4 7434

  • 0 80 VOl 0000 0

08221 Wa 380%

310 2954*1 00 4231~fi 88000240 080340 000 80710003.

0.5

£01100 1

OflO Oslo

  • 4*4%

743*0 330 38.30 4.00%

¶ on a.oua.Oo.30 nun 08,4.4... 94,201 04500188.3011

.S.000434308042908090000A 1

41830 17*3130

.20*4%

11196 40 310 3046.

I 1*9 4.30*4420b00.3041 93*4 9.

304.l 0.60 418030o040~n.10300%066300450.4016430edt 2000.820 330 1130 00%

88*0 80 13000 0300 40 349 01330.3030 $1010.0 449 01 01*4 8*4%

000 80 800 SAS 40 90 30122.030.$14340301818 9

80 1000 8104*4

.300%

1220 1*0 0.0 0800 40 30*4 48S~11 40360830 44

.0 8*4%

030 4*4 4.3 000018 430 1130 0 1030*4 000*

110

'45 8*4%

30 030 01 200%

40 4130 4442$14300 60)10 3.240 4.804.

280.

2f8AS 0030030.0 4010.80 4.1040 1604 Ca 130010 9.41.10 434 0230 012084 37*00 31324*

IOWa 80 40 00 300 43*4 30*4 080 4

0 130 010 374 030 49 A. a 430400 64 2463022 438 40,0.4 Cant 20082024 84.448 Us a

02t a

87 80.4.0030.

8.7*0 30%

830 80 20 303080 4*4 AS 46433000212301S0%

0.40.4.80

  • 64 20 600 310 80 10 4.280 10 302 0132n803 4130110210 0000 9.743 4.0%

8.0 9.0 1.90 00410%

10 0*0 202200039 00,40%

30150300 01 30%

044 10 03 8.3.012 10

92) 01342133181360 044 184 34300 43030 812 4

10 430 6060%

01 00%

0*4 00 8.90 0410460 40 041 343004313011144 44030 2034130 6010 114 080.401 40330.0 no 1104)

Ca 80 04*0 330 90*4 0446 908.30 83030 0.4600%

4.0 40 8.30 90.0 30.0 30*4 3030 3

23 40 030 422 00 237 0 Ca 00.004 44 10*4.42 438 0.10.4 AS 304 480418024 £00.30 8001 04.1

  • 20 247 0.004*.

80 140%

21110 83

  • 30
30.

130 4*0 OlZa.oSI.A241 1013120

.AS04 80 0*4%

80 80 20 37104622 130 4*0 20230803003018130%

an.

a 03 7

830%

3.42 9.0 10 LAS 430 40 201,,so.44830301183184 80%

630 30%

8*4 23 4*0 00104634 430 92*

20246330031300143030 3004 A0 3130 88304 dOts 24.0 3042300*.

20%.S 14s90.8 no 1804 Ca 430 2008 8*0 903.

033.

8084 360.42 004800 80 8*4 830 9046 0*4 3030 30*4 0

42 40 91*0 71 40

'118044

  • 0440 34 80%,

904135

  • 01.300 l7*ao& 34 Va04 AS 1890*0.0 a

242 4804.40430.

230 40%

80 40 20 3094*30 10 430 3433000003011100%

0800080 0

4 40%

30 9.0 404 LAS 40

'2 31*2108260.0*41182188 dO 9.10 4608 8*4 30 4*0 0,9404 10 830 010660..44030120%

309.60 0

814.3 0

846.04 3.40 4.30m~

I.3 30*0030 389 dO o-eaa n..

ioas no tao 4*4 346 8.0 90.0 0940 37*0 30*0 4*4 80 8.30 110 3030 18*0 30*4 0

In 40 9120 113 230 2444448 38.44 44 234 98030 AS 39.0 Va 0024

$804 US 40' 184.1%

09.8 AS 20.1 310 0.0%

330 80

  • 0 0*80 430 044 18103084U21030900%

30*

440 80%

1320 430 408 LAS 130 1012 312..0008030306.94390 0.130 0*494.

030 0*4 9*0 00280%

10 1*0 3612003130304*00 132*4 AU 194.00 00.304 30 180 43)0 Idi 280 4260430 4100.

30.3403040.

vrr.o i

no 808 Ca 430 17220 8.43 900 043 30092 5.9020 4.30 00 8.0 030 00 3030 300 43.4 06Va4401 0

0 446 012 10 9.0 00%.500 9.0t24133043010 890 a

.080 04 044

  • 10 dOlts 3041301 2.000.

804 26030000 AS Ca 2300) 01*44 13.313 8018

.130%

32030 380 a

81.80 401*4 300 dO 34383.30 2000 9* OdOUR nO 19003000 0

ASS Ca 0.010 fl SO 44.90*4 40200 012077 4800*44 40

  • 0 300 3030 3030 30*8 418 AS.85430 0

20 930 039 01 0

I 204.10120 0AS44570.130803 4a010083m 101 oOfo..%.

8030 a24 v.a 00 010302 101140 401008 0000 8

  • 30004 404 OCant Ca 230.00 I

00 143030

  • 4*4%

00 30 100 00800 Ca 04 4

030 9.23030

  • 400 310 030 23*0 3144.04 Ca 290208 034.34 30%

24.0 130 430 30 Ca 600600%

12030 8*0%

4*4 018 80 30 094.02 30 011030 0I 44 2243 *412301%.900419.12000 3742 I*kMO 09.00 82830 1

030 100342000004.2046 18*0608002.030 106000*600AS404.ofI40500402,040A042A01008 1

421 00042000~0303046 1230463130.290*

0.*2800AS40018 a6160041.0040309.

ccel

-m a: tat*o Cb

h.

m c

is 02 PSm t

-MA+..

-IP.

i.

iCiC ieiA C-i O

C C

C a

4U ifl OO10 00II lmU t

t t

O I

0.

it tmiw.P..moein..m.StWCSq tat pnma~

.nmii it; mm tam Oem tam tO mPwiC-CW.mC-t 01.

a to IC 0.-

S... a.

C1 aI m

u to..

to 100 4

C Oo.flw.e-n o

~.Snt~kt.to.flI ml dmt.C.i.t..eCtatt SC tnic tarn Ca Caew.w.

mom wIeCO.

W 310w.

IStam I to me w.o..et.

C C

WCt.St..taIt N

tilt SW ISC 110 IWO zig IS OS tO C

is tic em

  • t tICS tO Itte IN Ste mite.

aeeo

  • itmlitn tot Ce newt ftt tot

~

PS OUSt COW 00 CO 000 wUSPOt tO a

inbl...SiUittotIO SUn 0CC 00 CO Vim SiCtEm 10 C

CmwflhwitIIICm ow Ce tow w

w w

C w

m e

Ste 5.10 N*

N*

m*

a o

wot.0

i.

ol~st.

1o0*.5

  • ~+ olii i l.i lOO
  • i+;z..:

~r C~iO~..w lose ie w to

,.o I~nmol t,

cc tomi C-wi I

aSe ion to iI22laC.A.

00 Ctpmi~.eo I 0004 twit t~

Sw v-mcc~e...

we iwilItt.mC.teO I Cosretmo we P.OCCm.eCeo

~

mm ret p.1dt3..0ine p.~mtoe we oreTawom.oot.

I mine eC nem.~

I Ce~

Sm toPItwimew am

~

C C.~Ta toO t.inimite

~

me imie..wi 00 toP.tmwamm 2 55CC-sam men z

mt.

ma.

2 SC tIlCig 2

51*0 0002 or

slim, OOtSCOla C

4 Cm.emmettlet.0 4

Ia ISfhaike.C a

r, I,

C to i

31.1CC atoaxe iO.S mitit COltS I'

Pllwinumi.

ti 1nee 41wvm C-a~/m C.C SIne ri.11.C a

em ito am IC to 00mm Pm~

20 0

SO e

10 Wa C

I Cmi.C C

110 520 0

SOC C

IC CCI C

I WAti tC 51w CO.

ENCLOSURE 2 TO CY-15-042 CERTIFICATION OF FINANCIAL ASSURANCE

CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee:

Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation NRC No. DPR-61 (N-RC Docket No. 50-213) 362 Injun Hollow Road East Hampton, CT 06424-3099 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Connecticut Yankee Atomic Power Company is the licensee for the Haddam Neck Plant (HINP) Independent Spent Fuel Storage Installation (1SF SI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the HNP ISFSI.

During the operation of this 1SF SI, spent nuclear fuel and Greater than Class C waste will be stored at the HNP ISFSI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated cask~s will ultimately be removed from the ISF SI location, and HNP will dispose of other radiological waste in accordance with NRC regulations, at which time the HINP ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund HNP ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in the letter to which this Certification is attached. That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of:

HNP ISFSI

$17.9 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella

  • e Connecticut Yankee Atomic owe Company Vice President, Chief Financial Officer, and Treasurer Phone (860) 267-6426 x304 Corporate Seal1 Date

\\*l*,Jk

ENCLOSURE 3 TO CY-15-042 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRA)LA TED FIJL _AJ*. GTCC WASTE

2013 -2033 Summary (UN ESCALATED)

Coonnetiout Yankee Atomic Power Company Irradited Fool & GTCC Waste Monagement and [SPSt Decom Estimote Repmesented In 2016 Dollaom 0ERC Summary Oem of 2010 Scm of 2017 Som of 2010 Scm of 2019 Scm of 2020 Scm of 2021 Scm of 2022 Sam of 2023 Scm of 2024 Som of 2020 Som of 2026 Scm of 2027 Sam of 2020 Sam of 2029 Scm of 2020 Scm of 2031 Scm of 2032 Scm of 2033 Sam of Total 2013 -2932 Conthngency 0723.040

$730,992

$572,100

$0000073 0002.040 0573.100 0073.100

$072,100

$073,100 0012.034 0073,150

$573.100 0573,150

$710,020

$500,612 01.431.677 0401.253 011,070,375 GO Metds

$1,000,320

$1,895,329 01,895,328

$1,095,328 01,090.328 01,095,328 01,005,220 01,895,320 01.005,320 01,005.320 01,050.320 01,095,320 01,095,320 01,005.320

$1,090,320

$1,095,320

$0

$30,325,240 Insurance 0000,084 0000,004

$900,904 0600,004 0000,904 0000,904

$600,084

$5000,984

$000,004

$000,984 0000,904

$000,904

$000,004

$000,994 0000,004 0000,004 0050,073

$10.569,710 Labor - Non-Manuaol

$1,059,575 21,050,575

$1,059,575

$1,050,575 01,859.575

$1,059,575

$1,809,575

$1,050,570 01,009,079 01,009,0705$1,059.0705$1.059,570 01,859,570

$1,009,570

$1,000,075 01,059,575

$902,000 030,050,040 Laber -Secarity 03.009,200 03,378.235 53,370,238

$3,370,2330 03,370,230

$3,370,230 53,370,230 03.370,226

$3,376,235 03.370.236 03,376.236

$33.370,2330 03,270,230

$3,370,230 03.370,230 03,370,326

$0 053,713,841 Legal ServIces 0215,370

$215,370 0210,378

$210,370

$210,070 0210,378 9215,378 0215,378

$215,370 5315,370 0218,370

$210,370 9210,378

$215,370 0215,378 0310,378 0538,445 03,984,400 Materials & Supplies 0102.305

$102,305 0102,305 0102,305

$102,305 0102,300 0102,300 0102,309

$102,300 5102,205 0102,308 0102,305 0102,3005 2,055,060 0102,308 0103.305 95,384

$4,496,018 Miscetlaneo us 0100.238 0100,228 0108,228

$100,220

$100,330

$100,339 9108,328 0108,328 0108,330 0108,320 0100,228 0108,338 0108,228

$108.220 0100,3286 0108,338

$71,013 01,803,283 Outside Servicec -A&G 01.078,799 01,879,789 9002.908 0502,900 0021,030 0002,900 0002,000 0002,900 1002,008

$5053,000 0502.008 0002,908 0502,000 0002,000 0502,008 95003.900 0303,373

$10.702,408 Outside Serttces - Fool Leading 50 00

$0

$0

$0 00

$0

$0 30

$0

$0

$0 00

$0 90

$2,310,310

$0

$2,318.318 Outside Serviues - ISF01 OP's 03,850,014

$3,000,914 0015,581 0010,901 0010.801 0015,901 0015,01 6t,81 8415,981

$015,90 1

$615,901 0015, 981

$010,981 005,01 010,001 0015,001 0019.001 003.097

$14,419,500 Outside Services - Legal

$00,151 960,191

$00,101 0024,097 9309,374 080,151

$000,101

$00,151 000,101

$893,081 306,151 086,151 080,101 080,101

$355.374

$824,097 51,108,197 04,910,621 Outside Servires -N0O4-RAD D&Ddo

$0

$0

$0

$0 00

$0 90 90

$0 00

$0

$0 98

$0 00 00 91,904,104 90

$1,844,104 Outside Services - RA$ D&D of ISF51 50 90

$0

$0

$0

$0

$0 56

$0

$0

$0

$0 00

$0

$0 00

$10,328,733,

$0

$10.329.723 FropertyTaxes

$1,202,208 01.292,209 01.292,289 31,292,269

$1,202,209 01.292,209

$1,292,200

$1,292,209 01.292,2609$1.393,209 01,203.360

$1,202,269 21.292.209

$1,202,209 91,293,269 01,292,209 0430,700 921,107,084 Regulatory Peas 0743.000 9743,000

$743,085

$743,055 0743,000 3743,050

$743,080

$743,000

$743,080

$743,000 0743,099

$743,050

$743,055 9743,050 0743,080 0743,005 0371,527

$12,200,400 utgLte s 004,013 004,013

$04,813 004,013 304,013 004,813 904,013

$04,613 064,013 004,613

$04,613 004,012

$04,813

$64.013 364,013 004,013 564.613

$1,088,428 Grand Total 010,190,047

$18,918,824

$12,030,1060

$12,001,027

$12,443,007 912,80,6100 $12,90,8100 012,030,100 $12,030,100 $12,884,211 012.030.1100 $12.036,100 912,030,100 018.032.008 012,218.043 010,740,440 020,283,917 00.403.784

$223,731,497 Check 0um

$233, 73t1,490 Note 1: The cost ol management ot merdiated tuel and GTCC waste is calculatod as tollows:

3 3233,731.400 Grand Total tram Above 11,904.1041 Non-Rod D&D ISFSI 0

tlO,320,7221 Rod DOD ISF51 9

213,437,573 Management of Irradiated Fuel and GTCC Wasto Note 2: The nest ofRAG and NON-SAD DOD el the ISF51I n 2010 dollars as pronided in the column labeled 'Sum oft2O3r Is dottved by oscalating the naive ofthe cost eshmrrtes provided in Encloscre 1 0y32,5%.

Solo 3: This Sommory Combires CY's 2013 Approved PESO Rate Case writh the Knight Ccst Engineering Services 2015 SAD end NON-Rod [SPSt Decom Cost Estimate