CP-200900474, Property Damage Insurance, Summary Report
ML090970734 | |
Person / Time | |
---|---|
Site: | Comanche Peak |
Issue date: | 03/26/2009 |
From: | Flores R Luminant Generation Co, Luminant Power |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
CP-200900474, TXX-09053 | |
Download: ML090970734 (2) | |
Similar Documents at Comanche Peak | |
---|---|
Category:Letter type:CP
MONTHYEARCP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024
[Table view]License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202400107, (CPNPP) - 2023 Annual Radiological Environmental Operating Report2024-04-18018 April 2024 (CPNPP) - 2023 Annual Radiological Environmental Operating Report CP-202400099, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2024-04-0909 April 2024 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202400092, (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-04-0101 April 2024 (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400089, Property Damage Insurance2024-03-25025 March 2024 Property Damage Insurance CP-202400087, (CPNPP) - Notification of Deviation from Electric Power Research Institute (EPRI) MRP 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in Non-Isolatable2024-03-21021 March 2024 (CPNPP) - Notification of Deviation from Electric Power Research Institute (EPRI) MRP 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in Non-Isolatable CP-202400085, (CPNPP) - Revised Requested Compliance Date - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-0707 March 2024 (CPNPP) - Revised Requested Compliance Date - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CP-202400073, (CPNPP) - Response to RAI for License Amendment Request to Extend Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-03-0404 March 2024 (CPNPP) - Response to RAI for License Amendment Request to Extend Allowed Outage Time for an Inoperable Emergency Diesel Generator CP-202400072, (Cpnpp), Unit 1, Special Report 1-SR-24-001-00, Inoperable Post Accident Monitoring Instrumentation2024-02-29029 February 2024 (Cpnpp), Unit 1, Special Report 1-SR-24-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300470, (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-02-28028 February 2024 (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown CP-202300474, (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-02-28028 February 2024 (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions CP-202400063, (CPNPP) - Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 23 (1RF23)2024-02-12012 February 2024 (CPNPP) - Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 23 (1RF23) CP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300533, (CPNPP) - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-14014 November 2023 (CPNPP) - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application – Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application – Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plants Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plants Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) 2024-09-12 Category:Report MONTHYEARML24136A1352024-07-30030 July 2024
[Table view]LRA - Record of Decision ML23355A2682023-12-21021 December 2023 NRC Comments - Comanche Peak LRA Supplement 3 (1) CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 ML22020A1792021-11-0404 November 2021 Fall 2021 Steam Generator Tube Inspections Discussion Input CP-202100127, Transmittal of Pressure and Temperature Limits Report, ERX-07-003, Revision 62021-03-16016 March 2021 Transmittal of Pressure and Temperature Limits Report, ERX-07-003, Revision 6 CP-202000462, Submittal of 10CFR50.59 Evaluation Summary Report 022, 007, and Commitment Material Change Evaluation Report 0162020-09-29029 September 2020 Submittal of 10CFR50.59 Evaluation Summary Report 022, 007, and Commitment Material Change Evaluation Report 016 ML20153A7442020-06-0404 June 2020 Review of the Fall 2018 Steam Generator Tube Inspection Report CP-201900467, (CPNPP) - Biennial Review of Procedures and Station Operations Review Committee Meetings2019-08-14014 August 2019 (CPNPP) - Biennial Review of Procedures and Station Operations Review Committee Meetings CP-201900378, Transmittal of Seventeenth Refueling Outage (2RF17) Steam Generator 180 Day Report2019-06-10010 June 2019 Transmittal of Seventeenth Refueling Outage (2RF17) Steam Generator 180 Day Report CP-201900126, Special Report 2-SR-19-001-00, Inoperable Post Accident Monitoring Instrumentation Report.2019-02-25025 February 2019 Special Report 2-SR-19-001-00, Inoperable Post Accident Monitoring Instrumentation Report. CP-201800652, Special Report 1-SR-18-001-00, Inoperable Post Accident Monitoring Instrumentation Report2018-09-12012 September 2018 Special Report 1-SR-18-001-00, Inoperable Post Accident Monitoring Instrumentation Report ML18044A0982018-02-0808 February 2018 Solid Waste Registration Number: 33306; Texas Waste Code: 37043902; Reference Number: 15749 CP-201700805, Sixteenth Refueling Outage (2RF16) Steam Generator 180 Day Report2017-10-30030 October 2017 Sixteenth Refueling Outage (2RF16) Steam Generator 180 Day Report CP-201700223, Decommissioning Funding Status Report for Financial Assurance as of 12/31/20162017-03-30030 March 2017 Decommissioning Funding Status Report for Financial Assurance as of 12/31/2016 CP-201700033, Mitigating Strategies Assessment Flood Report, NEI 12-06, Appendix G, Revision 2, G.4.1 Path2017-02-0909 February 2017 Mitigating Strategies Assessment Flood Report, NEI 12-06, Appendix G, Revision 2, G.4.1 Path CP-201600097, Westinghouse LTR-PAFM-16-2-NP, Technical Justification to Support Extended Volumetric Examination Interval for Comanche Peak Unit 1 Reactor Vessel Inlet Nozzle to Safe End Dissimilar Metal Welds.2016-02-29029 February 2016 Westinghouse LTR-PAFM-16-2-NP, Technical Justification to Support Extended Volumetric Examination Interval for Comanche Peak Unit 1 Reactor Vessel Inlet Nozzle to Safe End Dissimilar Metal Welds. CP-201600093, Transmittal of 10CFR50.59 Evaluation Summary Report 019, 10CFR72.48 Evaluation Summary Report 004, and Commitment Material Change Evaluation Report 0132016-02-24024 February 2016 Transmittal of 10CFR50.59 Evaluation Summary Report 019, 10CFR72.48 Evaluation Summary Report 004, and Commitment Material Change Evaluation Report 013 ML16014A1252016-01-22022 January 2016 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50 Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force ML16047A3302016-01-20020 January 2016 NEI 12-01 Phase 2 Staffing Assessment, Revision 1 ML15062A0302015-02-25025 February 2015 Work Plan for Completing a Once Through Cooling Water Study for Total Dissolved Solids, Chlorides, and Sulfates CP-201401268, Fourteenth Refueling Outage (2RF14) Steam Generator 180 Day Report2014-10-21021 October 2014 Fourteenth Refueling Outage (2RF14) Steam Generator 180 Day Report CP-201401027, 10CFR50.59 Evaluation Summary Report 018, 10CFR72.48 Evaluation Summary Report 003 and Commitment Material Change Evaluation Report 0122014-08-27027 August 2014 10CFR50.59 Evaluation Summary Report 018, 10CFR72.48 Evaluation Summary Report 003 and Commitment Material Change Evaluation Report 012 ML14189A5432014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 ML14189A4982014-06-19019 June 2014 Stars Response to Nuclear Regulatory Commission (NRC) Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program - Vendor Information Request ML14189A5002014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 5 ML14189A5312014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5 ML14189A5332014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5 ML14189A5372014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 CP-201400335, . Pressure and Temperature Limits Report2014-04-0808 April 2014 . Pressure and Temperature Limits Report CP-201400324, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-03-27027 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML14036A0362014-03-0707 March 2014 Staff Assessments of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to Fukushima Dai-Ichi Nuclear Power Plant Accident ML13225A5752013-12-19019 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies ML13338A6612013-12-18018 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Comanche Peak Nuclear Power Plant, TAC Nos.: MF0860 and MF0861 ML13309A0272013-10-31031 October 2013 WCAP-17728-NP, Rev. 1, Comanche Peak Nuclear Power Plant Units 1 and 2 Spent Fuel Pool Criticality Safety Analysis CP-201301238, Sixteenth Refueling Outage (1RF16) Steam Generator 180 Day Report2013-10-15015 October 2013 Sixteenth Refueling Outage (1RF16) Steam Generator 180 Day Report ML12159A2882012-06-11011 June 2012 Review of 60-day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near Term Task Force Related to Fukushima Dai-ichi Accident ML12080A1432012-03-0606 March 2012 CPNPP Systems Annual Operator Employment Notices ML12080A1502012-03-0606 March 2012 Submittal of Stc Annual Operator Employment Notices CP-201101257, Submittal of Operator Licensing Examination Data2011-09-21021 September 2011 Submittal of Operator Licensing Examination Data 2024-07-30 Category:Miscellaneous MONTHYEARML24136A1352024-07-30030 July 2024
[Table view]LRA - Record of Decision CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 ML22020A1792021-11-0404 November 2021 Fall 2021 Steam Generator Tube Inspections Discussion Input CP-202000462, Submittal of 10CFR50.59 Evaluation Summary Report 022, 007, and Commitment Material Change Evaluation Report 0162020-09-29029 September 2020 Submittal of 10CFR50.59 Evaluation Summary Report 022, 007, and Commitment Material Change Evaluation Report 016 ML20153A7442020-06-0404 June 2020 Review of the Fall 2018 Steam Generator Tube Inspection Report CP-201700033, Mitigating Strategies Assessment Flood Report, NEI 12-06, Appendix G, Revision 2, G.4.1 Path2017-02-0909 February 2017 Mitigating Strategies Assessment Flood Report, NEI 12-06, Appendix G, Revision 2, G.4.1 Path CP-201600093, Transmittal of 10CFR50.59 Evaluation Summary Report 019, 10CFR72.48 Evaluation Summary Report 004, and Commitment Material Change Evaluation Report 0132016-02-24024 February 2016 Transmittal of 10CFR50.59 Evaluation Summary Report 019, 10CFR72.48 Evaluation Summary Report 004, and Commitment Material Change Evaluation Report 013 ML16014A1252016-01-22022 January 2016 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50 Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force ML15062A0302015-02-25025 February 2015 Work Plan for Completing a Once Through Cooling Water Study for Total Dissolved Solids, Chlorides, and Sulfates CP-201401268, Fourteenth Refueling Outage (2RF14) Steam Generator 180 Day Report2014-10-21021 October 2014 Fourteenth Refueling Outage (2RF14) Steam Generator 180 Day Report CP-201401027, 10CFR50.59 Evaluation Summary Report 018, 10CFR72.48 Evaluation Summary Report 003 and Commitment Material Change Evaluation Report 0122014-08-27027 August 2014 10CFR50.59 Evaluation Summary Report 018, 10CFR72.48 Evaluation Summary Report 003 and Commitment Material Change Evaluation Report 012 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 ML14189A5432014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 ML14189A5372014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5 ML14189A5332014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5 ML14189A5312014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5 ML14189A5002014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 RIS 2014-07, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 52014-06-19019 June 2014 Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 1 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 2 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 3 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 4 of 5, Regulatory Issue Summary (RIS) 2014-07, Enhancements to the Vendor Inspection Program- Vendor Information Request. Part 5 of 5 CP-201400324, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-03-27027 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML14036A0362014-03-0707 March 2014 Staff Assessments of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to Fukushima Dai-Ichi Nuclear Power Plant Accident CP-201301238, Sixteenth Refueling Outage (1RF16) Steam Generator 180 Day Report2013-10-15015 October 2013 Sixteenth Refueling Outage (1RF16) Steam Generator 180 Day Report ML12159A2882012-06-11011 June 2012 Review of 60-day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near Term Task Force Related to Fukushima Dai-ichi Accident ML12080A1432012-03-0606 March 2012 CPNPP Systems Annual Operator Employment Notices ML12080A1502012-03-0606 March 2012 Submittal of Stc Annual Operator Employment Notices CP-201101257, Submittal of Operator Licensing Examination Data2011-09-21021 September 2011 Submittal of Operator Licensing Examination Data CP-201101169, CFR50.59 Evaluation Summary Report 016, 10CFR72.48 Evaluation Summary Report 001, and Commitment Material Change Evaluation Report 0102011-08-22022 August 2011 CFR50.59 Evaluation Summary Report 016, 10CFR72.48 Evaluation Summary Report 001, and Commitment Material Change Evaluation Report 010 ML1034206512010-09-17017 September 2010 FEMA, Comanche Peak Nuclear Power Plant - After Action Report/Improvement Plan, Drill Date August 18, 2010, Radiological Emergency Preparedness (REP) Program CPSES-201001000, Operator Licensing Examination Data, Form 5362010-07-28028 July 2010 Operator Licensing Examination Data, Form 536 ML1000700042009-12-0303 December 2009 After Action Report/Improvement Plan, Drill Date - December 03, 2009 CP-200901404, Core Operating Limits2009-11-0202 November 2009 Core Operating Limits CP-200900474, Property Damage Insurance, Summary Report2009-03-26026 March 2009 Property Damage Insurance, Summary Report CP-200900127, Guarantees of Payment of Deferred Premiums2009-01-19019 January 2009 Guarantees of Payment of Deferred Premiums CP-200900010, Core Flux Maps Data, Cycle 112009-01-0707 January 2009 Core Flux Maps Data, Cycle 11 CP-200800805, Report of Unusual or Important Environmental Event, Operating License, Appendix B, Environmental Protection Plan (Non Radiological) - Mortality of Avian Species2008-06-0404 June 2008 Report of Unusual or Important Environmental Event, Operating License, Appendix B, Environmental Protection Plan (Non Radiological) - Mortality of Avian Species CP-200800612, Commanche Peak, Units 1 & 2 - Transmittal of Revised Pressure and Temperature Limits Report2008-04-24024 April 2008 Commanche Peak, Units 1 & 2 - Transmittal of Revised Pressure and Temperature Limits Report CP-200800609, Pressurizer Weld Overlay 60 Day Report and Results of the Final Pdi/Ut Examination of Weld Overlays2008-04-24024 April 2008 Pressurizer Weld Overlay 60 Day Report and Results of the Final Pdi/Ut Examination of Weld Overlays CP-200800213, Response to Request for Additional Information2008-02-26026 February 2008 Response to Request for Additional Information CPSES-200700454, Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data2007-02-28028 February 2007 Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data CPSES-200601738, Transmittal of First-Half 2006 Fitness-For-Duty Program Performance Data2006-08-31031 August 2006 Transmittal of First-Half 2006 Fitness-For-Duty Program Performance Data CPSES-200600154, Transmittal of Unit 2 Inservice Inspection Program Plan, Revision 22006-08-0202 August 2006 Transmittal of Unit 2 Inservice Inspection Program Plan, Revision 2 ML0620500122006-07-17017 July 2006 Attachment 1 to TXX-0612 Response to Requests for Additional Information for the Replacement Steam Generator Supplement to Txu Power'S Large and Small Break Loss of Coolant Accident Analysis Methodologies, Pages 1 Through 74 ML0702303962006-04-10010 April 2006 Report 06-0413 Chart 250-200 ML0702303952006-04-0606 April 2006 Report 06-0413 Chart 120-307 2024-07-30 |
Text
Rafael Flores Luminant Power Senior Vice President P 0 Box 1002 Luminant & Chief Nuclear Officer rafael.flores @Luminant.com 6322 North FM 56 Glen Rose, TX 76043 T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-200900474 Ref. # 10CFR50.54(w)
Log # TXX-09053 March 26, 2009 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NOS. 50-445 AND 50-446 PROPERTY DAMAGE INSURANCE
Dear Sir or Madam:
In accordance with the requirements of 10CFR50.54(w), Luminant Generation Company LLC (Luminant Power) hereby submits the attached summary report of the level and source of on-site property damage insurance coverage for Comanche Peak as of April 1, 2009. The level of coverage maintained is in excess of the $1.06 billion as required by 10CFR50.54(w).
This communication contains no new licensing basis commitments regarding Comanche Peak Units 1 and 2.
Should you have any questions, please contact Mr. J. D. Seawright at (254) 897-0140.
Sincerely, Luminant Generation Company LLC Rafael Flores By: 2?ý/ ld-Fred W. Madden Director, Oversight & Regulatory Affairs Attachment c - E. E. Collins, Region IV B. K. Singal, NRR Resident Inspectors, Comanche Peak 1000 ý
Attachment to TXX-09053 Page 1 of 1 Comanche Peak Nuclear Property Insurance Coverage As of April 1. 2009 ProDertv - All Risk (Oeratina Facility)
Policy No. Insuring Company Amount of Insurance Expires P08-061 Nuclear Electric Insurance Ltd. $ 500,000,000 October 1, 2009 X08-062 Nuclear Electric Insurance Ltd. $ 1,750,000,000 October 1, 2009 Total $2,250,000,000