BVY 22-007, Pre-Notice of Disbursement from Decommissioning Trust
ML22033A022 | |
Person / Time | |
---|---|
Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
Issue date: | 02/02/2022 |
From: | Metzger G, Reid B Bank of New York Mellon, NorthStar Vermont Yankee |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
References | |
BVY 22-007 | |
Download: ML22033A022 (1) | |
Similar Documents at Vermont Yankee | |
---|---|
Category:Decommissioning Plan DKTs 30
MONTHYEARBVY 22-005, ISFSI Decommissioning Funding Plan2022-02-24024 February 2022
[Table view]ISFSI Decommissioning Funding Plan BVY 22-007, Pre-Notice of Disbursement from Decommissioning Trust2022-02-0202 February 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 18-032, Pre-Notice of Disbursement from Decommissioning Trust2018-08-15015 August 2018 Pre-Notice of Disbursement from Decommissioning Trust BVY 17-018, Pre-Notice of Disbursement from Decommissioning Trust2017-05-11011 May 2017 Pre-Notice of Disbursement from Decommissioning Trust BVY 17-012, Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station2017-03-13013 March 2017 Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station 2022-02-24 Category:40 MONTHYEARBVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022
[Table view]Notification of Revised Decommissioning Cost Estimate BVY 22-009, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20212022-03-23023 March 2022 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2021 BVY 22-005, ISFSI Decommissioning Funding Plan2022-02-24024 February 2022 ISFSI Decommissioning Funding Plan BVY 22-007, Pre-Notice of Disbursement from Decommissioning Trust2022-02-0202 February 2022 Pre-Notice of Disbursement from Decommissioning Trust ML21054A1322021-04-14014 April 2021 U.S. NRC Analysis of Entergy Nuclear Operations, Inc'S Initial and Updated Decommissioning Funding Plans for the Big Rock Point, Indian Point, Pilgrim, Palisades, Fitzpatrick, and Vermont Yankee Independent Spent Fuel Storage Installations BVY 20-012, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20192020-03-31031 March 2020 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2019 CNRO-2019-00005, Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2019-03-28028 March 2019 Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc BVY 18-032, Pre-Notice of Disbursement from Decommissioning Trust2018-08-15015 August 2018 Pre-Notice of Disbursement from Decommissioning Trust CNRO-2018-00012, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2018-03-29029 March 2018 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 18-006, Pre-Notice of Disbursement from Decommissioning Trust2018-02-22022 February 2018 Pre-Notice of Disbursement from Decommissioning Trust ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning BVY 17-018, Pre-Notice of Disbursement from Decommissioning Trust2017-05-11011 May 2017 Pre-Notice of Disbursement from Decommissioning Trust BVY 17-012, Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station2017-03-13013 March 2017 Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station ENOC-16-00008, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii)2016-03-30030 March 2016 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii) CNRO-2016-00010, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2016-03-30030 March 2016 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 15-044, Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station2015-07-16016 July 2015 Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station ENOC-15-00005, Decommissioning Funding Status Report Entergy Nuclear Operations, Inc2015-03-30030 March 2015 Decommissioning Funding Status Report Entergy Nuclear Operations, Inc ENOC-15-00007, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 20142015-03-27027 March 2015 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2014 ENOC-15-00006, ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a2015-03-27027 March 2015 ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a BVY 14-082, Update to Decommissioning Funding Status Report2014-12-19019 December 2014 Update to Decommissioning Funding Status Report ENOC-14-00009, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2014-03-28028 March 2014 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-14-00008, Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a2014-03-28028 March 2014 Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a ENOC-13-00007, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2013-03-29029 March 2013 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-12-00039, ISFSI Decommissioning Funding Plans (10 CFR 72.30)2012-12-13013 December 2012 ISFSI Decommissioning Funding Plans (10 CFR 72.30) CNRO-2011-00006, Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications2011-12-13013 December 2011 Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications ENOC-10-00010, Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 20092010-03-31031 March 2010 Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 2009 BVY 10-020, 2009 Financial Test for Decommissioning Fund Parent Guarantee2010-03-30030 March 2010 2009 Financial Test for Decommissioning Fund Parent Guarantee ENOC-09-00034, Revised Decommissioning Funding Assurance Plan2009-10-29029 October 2009 Revised Decommissioning Funding Assurance Plan ENOC-09-00024, Decommissioning Funding Assurance Plans2009-08-13013 August 2009 Decommissioning Funding Assurance Plans ENOC-09-00007, Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1)2009-03-30030 March 2009 Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1) ENOC-08-00018, Stations - Decommissioning Fund Status Report for the Period Ending December 31, 20072008-03-26026 March 2008 Stations - Decommissioning Fund Status Report for the Period Ending December 31, 2007 ML0730304542007-10-18018 October 2007 (PA-LR) VY License Renewal Amendment 32 ML0711600532007-04-25025 April 2007 Decommissioning Funding Requirements for Vermont Yankee ENOC-07-00007, Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1)2007-03-29029 March 2007 Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1) ML0636202042006-12-0505 December 2006 2006/12/05-E-Mail: VY License Renewal Application Amendment 22 - (PA) ML0629603012006-10-17017 October 2006 2006/10/17-Vermont Yankee - License Renewal Application, Amendment 16 ML0208604402002-03-21021 March 2002 CFR 50.75(f)(1) Decommissioning Fund Status Report 2022-06-17 Category:50 MONTHYEARBVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022
[Table view]Notification of Revised Decommissioning Cost Estimate BVY 22-009, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20212022-03-23023 March 2022 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2021 BVY 22-005, ISFSI Decommissioning Funding Plan2022-02-24024 February 2022 ISFSI Decommissioning Funding Plan BVY 22-007, Pre-Notice of Disbursement from Decommissioning Trust2022-02-0202 February 2022 Pre-Notice of Disbursement from Decommissioning Trust ML21054A1322021-04-14014 April 2021 U.S. NRC Analysis of Entergy Nuclear Operations, Inc'S Initial and Updated Decommissioning Funding Plans for the Big Rock Point, Indian Point, Pilgrim, Palisades, Fitzpatrick, and Vermont Yankee Independent Spent Fuel Storage Installations BVY 20-012, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20192020-03-31031 March 2020 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2019 CNRO-2019-00005, Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2019-03-28028 March 2019 Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc BVY 18-032, Pre-Notice of Disbursement from Decommissioning Trust2018-08-15015 August 2018 Pre-Notice of Disbursement from Decommissioning Trust CNRO-2018-00012, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2018-03-29029 March 2018 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 18-006, Pre-Notice of Disbursement from Decommissioning Trust2018-02-22022 February 2018 Pre-Notice of Disbursement from Decommissioning Trust ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning BVY 17-018, Pre-Notice of Disbursement from Decommissioning Trust2017-05-11011 May 2017 Pre-Notice of Disbursement from Decommissioning Trust BVY 17-012, Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station2017-03-13013 March 2017 Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station ENOC-16-00008, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii)2016-03-30030 March 2016 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii) CNRO-2016-00010, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2016-03-30030 March 2016 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 15-044, Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station2015-07-16016 July 2015 Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station ENOC-15-00005, Decommissioning Funding Status Report Entergy Nuclear Operations, Inc2015-03-30030 March 2015 Decommissioning Funding Status Report Entergy Nuclear Operations, Inc ENOC-15-00007, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 20142015-03-27027 March 2015 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2014 ENOC-15-00006, ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a2015-03-27027 March 2015 ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a BVY 14-082, Update to Decommissioning Funding Status Report2014-12-19019 December 2014 Update to Decommissioning Funding Status Report ENOC-14-00008, Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a2014-03-28028 March 2014 Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a ENOC-14-00009, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2014-03-28028 March 2014 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-13-00007, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2013-03-29029 March 2013 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-12-00039, ISFSI Decommissioning Funding Plans (10 CFR 72.30)2012-12-13013 December 2012 ISFSI Decommissioning Funding Plans (10 CFR 72.30) ENOC-10-00010, Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 20092010-03-31031 March 2010 Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 2009 BVY 10-020, 2009 Financial Test for Decommissioning Fund Parent Guarantee2010-03-30030 March 2010 2009 Financial Test for Decommissioning Fund Parent Guarantee ENOC-09-00034, Revised Decommissioning Funding Assurance Plan2009-10-29029 October 2009 Revised Decommissioning Funding Assurance Plan ENOC-09-00024, Decommissioning Funding Assurance Plans2009-08-13013 August 2009 Decommissioning Funding Assurance Plans ENOC-09-00007, Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1)2009-03-30030 March 2009 Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1) ENOC-08-00018, Stations - Decommissioning Fund Status Report for the Period Ending December 31, 20072008-03-26026 March 2008 Stations - Decommissioning Fund Status Report for the Period Ending December 31, 2007 ML0711600532007-04-25025 April 2007 Decommissioning Funding Requirements for Vermont Yankee ENOC-07-00007, Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1)2007-03-29029 March 2007 Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1) ML0208604402002-03-21021 March 2002 CFR 50.75(f)(1) Decommissioning Fund Status Report 2022-06-17 Category:70 MONTHYEARBVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022
[Table view]Notification of Revised Decommissioning Cost Estimate BVY 22-009, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20212022-03-23023 March 2022 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2021 BVY 22-005, ISFSI Decommissioning Funding Plan2022-02-24024 February 2022 ISFSI Decommissioning Funding Plan BVY 22-007, Pre-Notice of Disbursement from Decommissioning Trust2022-02-0202 February 2022 Pre-Notice of Disbursement from Decommissioning Trust ML21054A1322021-04-14014 April 2021 U.S. NRC Analysis of Entergy Nuclear Operations, Inc'S Initial and Updated Decommissioning Funding Plans for the Big Rock Point, Indian Point, Pilgrim, Palisades, Fitzpatrick, and Vermont Yankee Independent Spent Fuel Storage Installations BVY 20-012, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20192020-03-31031 March 2020 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2019 CNRO-2019-00005, Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2019-03-28028 March 2019 Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc BVY 18-032, Pre-Notice of Disbursement from Decommissioning Trust2018-08-15015 August 2018 Pre-Notice of Disbursement from Decommissioning Trust CNRO-2018-00012, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2018-03-29029 March 2018 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 18-006, Pre-Notice of Disbursement from Decommissioning Trust2018-02-22022 February 2018 Pre-Notice of Disbursement from Decommissioning Trust ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning BVY 17-018, Pre-Notice of Disbursement from Decommissioning Trust2017-05-11011 May 2017 Pre-Notice of Disbursement from Decommissioning Trust BVY 17-012, Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station2017-03-13013 March 2017 Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station ENOC-16-00008, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii)2016-03-30030 March 2016 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2015, Per 10 CFR 50.82(a)(8)(vii) CNRO-2016-00010, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2016-03-30030 March 2016 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) BVY 15-044, Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station2015-07-16016 July 2015 Pre-Notice of Disbursement from Decommissioning Trust - Vermont Yankee Nuclear Power Station ENOC-15-00005, Decommissioning Funding Status Report Entergy Nuclear Operations, Inc2015-03-30030 March 2015 Decommissioning Funding Status Report Entergy Nuclear Operations, Inc ENOC-15-00007, Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 20142015-03-27027 March 2015 Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2014 ENOC-15-00006, ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a2015-03-27027 March 2015 ISFSI and Vermont Yankee - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2014 Per 10 CFR Part 30 App. a BVY 14-082, Update to Decommissioning Funding Status Report2014-12-19019 December 2014 Update to Decommissioning Funding Status Report ENOC-14-00009, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2014-03-28028 March 2014 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-14-00008, Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a2014-03-28028 March 2014 Entergy Nuclear Operations, Inc. - Financial Test for Decommissioning Funding Parent Guarantees for the Year Ending December 31, 2013 Per 10 CFR Part 30 App. a ENOC-13-00007, Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2013-03-29029 March 2013 Decommissioning Funding Status Report Per 10 CFR Section 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc ENOC-12-00039, ISFSI Decommissioning Funding Plans (10 CFR 72.30)2012-12-13013 December 2012 ISFSI Decommissioning Funding Plans (10 CFR 72.30) CNRO-2011-00006, Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications2011-12-13013 December 2011 Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications ENOC-10-00010, Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 20092010-03-31031 March 2010 Entergy Nuclear Operations, Inc. - Status of Decommissioning Funding for Year Ending December 31, 2009 BVY 10-020, 2009 Financial Test for Decommissioning Fund Parent Guarantee2010-03-30030 March 2010 2009 Financial Test for Decommissioning Fund Parent Guarantee ENOC-09-00034, Revised Decommissioning Funding Assurance Plan2009-10-29029 October 2009 Revised Decommissioning Funding Assurance Plan ENOC-09-00024, Decommissioning Funding Assurance Plans2009-08-13013 August 2009 Decommissioning Funding Assurance Plans ENOC-09-00007, Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1)2009-03-30030 March 2009 Status Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2008 - 10 CFR 50.75(f)(1) ENOC-08-00018, Stations - Decommissioning Fund Status Report for the Period Ending December 31, 20072008-03-26026 March 2008 Stations - Decommissioning Fund Status Report for the Period Ending December 31, 2007 ML0730304542007-10-18018 October 2007 (PA-LR) VY License Renewal Amendment 32 ML0711600532007-04-25025 April 2007 Decommissioning Funding Requirements for Vermont Yankee ENOC-07-00007, Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1)2007-03-29029 March 2007 Status of Decommissioning Funding for Year Ending December 31. 2006 - 10 CFR 50.75(f)(1) ML0636202042006-12-0505 December 2006 2006/12/05-E-Mail: VY License Renewal Application Amendment 22 - (PA) ML0629603012006-10-17017 October 2006 2006/10/17-Vermont Yankee - License Renewal Application, Amendment 16 ML0208604402002-03-21021 March 2002 CFR 50.75(f)(1) Decommissioning Fund Status Report 2022-06-17 Category:Letter type:BVY MONTHYEARBVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024
[Table view]Pre-Notice of Disbursement from Decommissioning Trust BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection 2024-07-30 |
Text
NorthStar Vermont Yankee, LLC Vermont Yankee Nuclear Power Station 320 Governor Hunt Rd.
Vernon, VT 05354 802-451-5354 BVY 22-007 February 2, 2022 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Pre-Notice of Disbursement from Decommissioning Trust Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28
Dear Sir or Madam:
In accordance with Vermont Yankee Nuclear Power Station (VYNPS) Renewed Facility Operating License Condition 3.J.a.(iii), the decommissioning trust agreement must provide that no disbursements or payments from the trust, other than for ordinary administrative expenses, shall be made by the trustee until the trustee has first given thirty (30) days prior written notice to the NRC.
Article IV, Section 4.05 of the Master Decommissioning Trust Agreement by and between NorthStar Vermont Yankee, LLC (NorthStar) and The Bank of New York Mellon, successor by operation of law to Mellon Bank, N.A. as Trustee, provides that no disbursements or payments shall be made by the Trustee, other than Administrative Expenses in accordance with Section 4.02 of the Master Trust Agreement, until the Trustee has first given the NRC thirty (30) days prior written notice of payment; provided, however, that no disbursement or payment from the Master Trust shall be made if the Trustee receives prior written notice of objection from the NRC Director of the Office of Nuclear Reactor Regulation.
This letter provides NRC written notification of The Bank of New York Mellons intent, upon receipt of a completed Disbursement Certificate from NorthStar, to make a disbursement from the VYNPS nuclear decommissioning trust in an amount not to exceed (without a supplemental 30-day notice to the Director) $5,300,000.00, for the period of January 2022. The disbursement request is expected to include, among other things, site-specific decommissioning costs related to licensing contractor costs, insurance and property tax.
The disbursement from the VYNPS nuclear decommissioning trust in the amount described above is planned to be made thirty (30) days following the date of this letter, unless the trustee receives prior written notice of objection from the NRC Director of the Office of Nuclear Reactor Regulation.
This letter contains no new regulatory commitments.
Should you have any questions concerning this letter or require additional information, please contact Mr. Glen Metzger at 412-234-0573 or Mr. Thomas B. Silko at 802-451-5354, Ext 2506.
BVY 22-007 / Page 2 of 2 Sincerely, Glen Metzger Billy E. Reid, Jr.
Vice President & Service Director Site Vice President The Bank of New York Mellon NorthStar Vermont Yankee, LLC cc: Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 Mr. David C. Lew Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Commissioner Vermont Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05602-2601