Category:Letter type:BVY
MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-07-30
[Table view] |
Text
Entergy Nuclear Vermont Yankee, LLC tergy lEn Entergy Nuclear Operations, Inc.
185 Old Ferry Road Brattleboro, VT 05302-0500 December 2, 2003 BVY 03-1 10 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
References:
(a) Letter, VYNPC to USNRC, "Proposed Change No. 162, Toxic Gas Monitoring System," BVY 91-02, dated January 15, 1991.
(b) Letter, USNRC to VYNPC, "Issuance of Amendment No. 132 to Facility Operating License No. DPR Vermont Yankee Nuclear Power Station (TAC No. 79442)," NVY 91-205, dated October 24, 1991.
Subject:
Vcrmont Yankee Nuclear Power Station License No. DPR-28 (Docket No. 50-271)
Report of Bulk Chlorine Rail Shipments for 2003 In Reference (a), Vermont Yankee (VY) submitted a proposed change to the Technical Specifications requesting approval to remove the Toxic Gas Monitoring System. In Reference (b), tile NRC granted approval and issued Amendment No. 132. As a condition for granting the amendment, the NRC required that every three years, starting in 1994, VY submit a report providing the annual frequency of railroad shipments of bulk chlorine within five miles of the plant site. The NRC required the evaluation to verify that the probability of loss of control room habitability continues to meet the acceptance criteria of Section 2.2.3 of the NRC Standard Review Plan (NUREG-0800, July 1981). The NRC also required that the report consider any changes in quantity of chlorine in each shipment, and that the report reference the number and date of the license amendment. This letter constitutes the required report and summarizes our evaluation.
VY conducted an evaluation of rail shipments of bulk chlorine. The evaluation included the following:
- 1. A determination of the annual frequency of rail shipments of bulk chlorine within five miles of the plant site, and
- 2. Consideration of any changes in the quantity of chlorine in each shipment.
Annual Frequency of Rail Shipments The two railroads that operate along the tracks adjacent to the plant, Guilford Rail System and New England Central Railroad, both provided information on chlorine shipped during the three year period covering 2001, 2002 and 2003. It is concluded from this information that the total number of rail cars shipped by both companies was either zero or not greater than 20, as compared to a total of 60 rail cars assumed in the analysis supporting Reference (a).
- ODJ
t BVY 03-110/Page 2 of 2 Changes in Quantity of Chlorine Chlorine shipments, if any, were in individual tank cars carrying 180,000 pounds or less. This weight is equivalent to approximately 15,350 gallons. The analysis supporting Reference (a) used a tank car capacity of 20,000 gallons, or 234,560 pounds, which bounds current shipments.
In addition, each rail company stated that there are no industrial or economic changes anticipated in the near future that would lead to either an increase in the frequency of cars shipped or capacity of the cars.
If you have any questions concerning this transmittal or require additional information, please contact Mr. Jeff Meyer at (802) 258-4105.
Sincerely,
/ James M. DeVincentis Manager, Licensing cc: USNRC Region I Administrator USNRC Resident Inspector - VYNPS USNRC Project Manager - VYNPS Vermont Department of Public Service
NI A-
SUMMARY
OF VERMONT YANKEE COMMITMENTS BVY NO.: 03-110 The following table identifies commitments made in this document by Vermont Yankee. Any other actions discussed in the submittal represent intended or planned actions by Vermont Yankee. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Licensing Manager of any questions regarding this document or any associated commitments.
COMMITMENT DATE cOR/"OUTAGE" NoneIN/A