MONTHYEARBSEP 19-0012, Submittal of 2018 Sea Turtle Annual Report2019-01-17017 January 2019 Submittal of 2018 Sea Turtle Annual Report BSEP 18-0052, Annual Radiological Environmental Operating Report - 20172018-05-10010 May 2018 Annual Radiological Environmental Operating Report - 2017 BSEP 18-0051, Annual Radioactive Effluent Release Report - 20172018-04-26026 April 2018 Annual Radioactive Effluent Release Report - 2017 BSEP 18-0045, Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time2018-04-25025 April 2018 Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time BSEP 18-0054, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential.2018-04-24024 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential. BSEP 18-0048, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-04-11011 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0044, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-04-11011 April 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0046, Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-04-10010 April 2018 Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0047, Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test2018-04-0505 April 2018 Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test BSEP 18-0041, Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report2018-04-0404 April 2018 Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report BSEP 18-0043, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-03-31031 March 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0035, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-29029 March 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0042, Cycle 22 Core Operating Limits Report (COLR)2018-03-27027 March 2018 Cycle 22 Core Operating Limits Report (COLR) BSEP 18-0040, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test2018-03-23023 March 2018 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test BSEP 18-0039, Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D2018-03-19019 March 2018 Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D BSEP 18-0034, Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-16016 March 2018 Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0032, Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-14014 March 2018 Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0026, Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2018-03-0707 March 2018 Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 18-0014, Fifth 10-Year Inservice Testing Program Plan2018-02-19019 February 2018 Fifth 10-Year Inservice Testing Program Plan BSEP 18-0021, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure2018-02-0505 February 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure BSEP 18-0017, Revision to Radiological Emergency Response Plan and Implementing Procedure2018-01-30030 January 2018 Revision to Radiological Emergency Response Plan and Implementing Procedure BSEP 18-0015, Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-01-23023 January 2018 Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-23023 January 2018 Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 18-0001, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements BSEP 18-0012, Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.32018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 BSEP 18-0009, 2017 Sea Turtle Annual Report2018-01-15015 January 2018 2017 Sea Turtle Annual Report BSEP 17-0098, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2018-01-10010 January 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors BSEP 17-0119, Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program2018-01-10010 January 2018 Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program BSEP 17-0115, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-0404 January 2018 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 17-0110, Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-12-20020 December 2017 Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination BSEP 17-0120, Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension..2017-12-12012 December 2017 Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension.. BSEP 17-0118, Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel..2017-12-0707 December 2017 Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel.. BSEP 17-0117, Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources..2017-12-0606 December 2017 Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources.. BSEP 17-0116, Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of ..2017-12-0404 December 2017 Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of .. BSEP 17-0104, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2017-11-29029 November 2017 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 17-0111, Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-28028 November 2017 Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0109, Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And.2017-11-24024 November 2017 Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And. BSEP 17-0108, Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-22022 November 2017 Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0017, Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material2017-11-15015 November 2017 Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material BSEP 17-0100, Fifth 10-Year Inservice Testing Interval2017-11-0202 November 2017 Fifth 10-Year Inservice Testing Interval BSEP 17-0089, Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0093, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0078, Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.52017-10-0303 October 2017 Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.5 BSEP 17-0076, Registration for Use of General License Spent Fuel Casks2017-09-0606 September 2017 Registration for Use of General License Spent Fuel Casks BSEP 17-0081, Revision to Radiological Emergency Response Plan Implementing Procedures2017-09-0505 September 2017 Revision to Radiological Emergency Response Plan Implementing Procedures BSEP 17-0039, Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements2017-08-15015 August 2017 Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements BSEP 17-0071, ISFSI - Registration for Use of General License Spent Fuel Casks2017-08-15015 August 2017 ISFSI - Registration for Use of General License Spent Fuel Casks BSEP 17-0064, Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N92017-07-10010 July 2017 Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N9 BSEP 17-0060, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-06-29029 June 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. 2019-01-17
[Table view] |
Text
Letter Enclosure I Contains Proprietary Information Duke Withhold in Accordance with 10 CFR 2.390(a)(4)
WEnergyo December 18, 2012 Serial: BSEP 12-0139 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Subject:
Brunswick Steam Electric Plant, Unit No 2 Docket No. 50-324 Response to Request for Additional Information Regarding Revision of Regulatory Commitment for Replacement of Core Plate Plugs (NRC TAC No. ME7702)
References:
- 1. Letter from Phyllis N. Mentel (CP&L) to the U.S. Nuclear Regulatory Commission, Revision of Regulatory Commitment Regarding Replacement of Unit 2 Core Plate Plugs, dated December 8, 2011, ADAMS Accession Number MLI 11348A1 15
- 2. Letter from Annette H. Pope (CP&L) to the U.S. Nuclear Regulatory Commission, Revision of Regulatory Commitment Regarding Replacement of Core Plate Plugs, dated November 5, 2012, ADAMS Accession Number ML12321A318
- 3. Letter from Heather M. Jones (NRC) to Michael J. Annacone (CP&L), Brunswick Steam Electric Plant: Request for Additional Information Regarding Core Plate Plug Replacement Commitment Change Request (TAC Nos. ME7702), dated December 17, 2012, ADAMS Accession Number ML12342A227 By letter dated December 8, 2011 (i.e., Reference 1), Carolina Power & Light Company (CP&L) submitted a request to revise a Brunswick Steam Electric Plant (BSEP), Unit No. 2 license renewal-related commitment. This commitment pertains to replacement of the existing Unit 2 core plate plugs prior to entering the period of extended operation authorized by the renewed facility operating license. Technical justification for the requested commitment change was provided in Structural Integrity Associates, Inc. Report No. 1000771.402, Revision 0, Life Extension for Core Plate Plugs at Brunswick Steam Electric Plant Unit 2. By letter dated November 5, 2012 (i.e., Reference 2), the technical justification was updated (i.e., to Structural Integrity Associates, Inc. Report No. 1000771.402P, Revision 2) due to the designation of proprietary information contained in the report.
On December 17, 2012 (i.e., Reference 3), the NRC provided a request for one of the reference documents supporting the Structural Integrity Associates, Inc. Report No. 1000771.402 (i.e.,
Reference 4: D. E. Delwiche, Revision of Core Support Plate Plug Service Life, General Electric Company Report NEDC-32120, July, 1992, SI File No. 1000771 202P). In response to the RAI, Enclosure 1 provides a copy of General Electric-Hitachi Nuclear Energy Americas LLC (GEH) Report NEDC-32120P, Revision of Core Support Plate Plug Service Life, dated July 1992, is provided in Enclosure 1.
U.S. Nuclear Regulatory Commission Page 2 of 3 This GE-Hitachi document in Enclosure 1 contains information considered proprietary to GE-Hitachi; therefore, an affidavit supporting withholding the report from public disclosure is provided in Enclosure 2. NEDC-32120P is considered entirely proprietary; therefore, a non-proprietary version of the document is not provided.
This document contains no regulatory commitments.
Please refer any questions regarding this submittal to Mr. Lee Grzeck, Manager - Regulatory Affairs, at (910) 457-2487.
Sincerely, FO0 Annette H. Pope Manager - Organizational Effectiveness Brunswick Steam Electric Plant WRM/wrm
Enclosures:
- 1. GE-Hitachi Nuclear Energy Americas LLC Report NEDC-32120P, Revision of Core Support Plate Plug Service Life, dated July 1992 (Proprietary Information - Withhold from Public Disclosure in Accordance With 10 CFR 2.390)
- 2. GE-Hitachi Nuclear Energy Americas LLC Affidavit Regarding Withholding Information from Public Disclosure
U.S. Nuclear Regulatory Commission Page 3 of 3 cc (with Enclosures 1 and 2):
U. S. Nuclear Regulatory Commission, Region II ATTN: Mr. Victor M. McCree, Regional Administrator 245 Peachtree Center Ave, NE, Suite 1200 Atlanta, GA 30303-1257 U. S. Nuclear Regulatory Commission ATTN: Ms. Michelle P. Catts, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission (Electronic Copy Only)
ATTN: Mrs. Farideh E. Saba (Mail Stop OWFN 8G9A) 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission (Electronic Copy Only)
ATTN: Mr. Christopher Gratton (Mail Stop OWFN 8G9A) 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission (Electronic Copy Only)
ATTN: Ms. Heather M. Jones 11555 Rockville Pike Rockville, MD 20852-2738 cc (with Enclosure 2 only):
Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510
BSEP 12-0139 Enclosure 2 GE-Hitachi Nuclear Energy Americas LLC Affidavit Regarding Withholding Information from Public Disclosure
GE-Hitachi Nuclear Energy Americas LLC AFFIDAVIT I, Edward D. Schrull, PE, state as follows:
(1) I am the Vice President, Regulatory Affairs, Services Licensing, GE-Hitachi Nuclear Energy Americas LLC ("GEH"), and have been delegated the function of reviewing the information described in paragraph (2) which is sought to be withheld, and have been authorized to apply for its withholding.
(2) The information sought to be withheld is contained in GEH proprietary report, NEDC-32120P, "Revision of Core Support Plate Plug Service Life," July 1992. NEDC-32120P is entirely proprietary, thus, NEDC-32120P carries the notation "GEH Proprietary Information
- Class III (Confidential) {3}" in the header of each page. In each case, the notation {3}
refers to Paragraph (3) of this affidavit, which provides the basis for the proprietary determination.
(3) In making this application for withholding of proprietary information of which it is the owner or licensee, GEH relies upon the exemption from disclosure set forth in the Freedom of Information Act ("FOIA"), 5 USC Sec. 552(b)(4), and the Trade Secrets Act, 18 USC Sec. 1905, and NRC regulations 10 CFR 9.17(a)(4), and 2.390(a)(4) for trade secrets (Exemption 4). The material for which exemption from disclosure is here sought also qualifies under the narrower definition of trade secret, within the meanings assigned to those terms for purposes of FOIA Exemption 4 in, respectively, Critical Mass Energy Project v. Nuclear Regulatory Commission, 975 F2d 871 (DC Cir. 1992), and Public Citizen Health Research Group v. FDA, 704 F2d 1280 (DC Cir. 1983).
(4) The information sought to be withheld is considered to be proprietary for the reasons set forth in paragraphs (4)a. and (4)b. Some examples of categories of information that fit into the definition of proprietary information are:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GEH's competitors without license from GEH constitutes a competitive economic advantage over other companies;
- b. Information that, if used by a competitor, would reduce their expenditure of resources or improve their competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product;
- c. Information that reveals aspects of past, present, or future GEH customer-funded development plans and programs, resulting in potential products to GEH;
- d. Information that discloses trade secret and/or potentially patentable subject matter for which it may be desirable to obtain patent protection.
(5) To address 10 CFR 2.390(b)(4), the information sought to be withheld is being submitted to NRC in confidence. The information is of a sort customarily held in confidence by GEH, and is in fact so held. The information sought to be withheld has, to the best of my knowledge and belief, consistently been held in confidence by GEH, not been disclosed Affidavit for NEDC-32120P Revision 0 Affidavit Page I of 3
GE-Hitachi Nuclear Energy Americas LLC publicly, and not been made available in public sources. All disclosures to third parties, including any required transmittals to the NRC, have been made, or must be made, pursuant to regulatory provisions or proprietary and/or confidentiality agreements that provide for maintaining the information in confidence. The initial designation of this information as proprietary information, and the subsequent steps taken to prevent its unauthorized disclosure, are as set forth in the following paragraphs (6) and (7).
(6) Initial approval of proprietary treatment of a document is made by the manager of the originating component, who is the person most likely to be acquainted with the value and sensitivity of the information in relation to industry knowledge, or who is the person most likely to be subject to the terms under which it was licensed to GEH. Access to such documents within GEH is limited to a "need to know" basis.
(7) The procedure for approval of external release of such a document typically requires review by the staff manager, project manager, principal scientist, or other equivalent authority for technical content, competitive effect, and determination of the accuracy of the proprietary designation. Disclosures outside GEH are limited to regulatory bodies, customers, and potential customers, and their agents, suppliers, and licensees, and others with a legitimate need for the information, and then only in accordance with appropriate regulatory provisions or proprietary and/or confidentiality agreements.
(8) Public disclosure of the information sought to be withheld is likely to cause substantial harm to GEH's competitive position and foreclose or reduce the availability of profit-making opportunities. The information is part of GEH's comprehensive BWR safety and technology base, and its commercial value extends beyond the original development cost.
The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation process. In addition, the technology base includes the value derived from providing analyses done with NRC-approved methods.
The research, development, engineering, analytical and NRC review costs comprise a substantial investment of time and money by GEH. The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial. GEH's competitive advantage will be lost if its competitors are able to use the results of the GEH experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
(9) Public disclosure of the information sought to be withheld is likely to cause substantial harm to GEH's competitive position and foreclose or reduce the availability of profit-making opportunities. The information is part of GEH's comprehensive BWR safety and technology base, and its commercial value extends beyond the original development cost.
The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation process. In addition, the technology base includes the value derived from providing analyses done with NRC-approved methods.
Affidavit for NEDC-32120P Revision 0 Affidavit Page 2 of 3
GE-Hitachi Nuclear Energy Americas LLC The research, development, engineering, analytical and NRC review costs comprise a substantial investment of time and money by GEH. The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial. GEH's competitive advantage will be lost if its competitors are able to use the results of the GEH experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of this information to GEH would be lost if the information were disclosed to the public. Making such information available to competitors without their having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall, and deprive GEH of the opportunity to exercise its competitive advantage to seek an adequate return on its large investment in developing and obtaining these very valuable analytical tools.
I declare under penalty of perjury that the foregoing affidavit and the matters stated therein are true and correct to the best of my knowledge, information, and belief.
Executed on this 19th day of November 2012.
Edward D. Schrull, PE Vice President, Regulatory Affairs Services Licensing GE-Hitachi Nuclear Energy Americas LLC 3901 Castle Hayne Rd.
Wilmington, NC 28401 Affidavit for NEDC-32120P Revision 0 Affidavit Page 3 of 3