AEP-NRC-2015-44, Response to NRC Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations

From kanterella
Jump to navigation Jump to search
Response to NRC Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations
ML15167A040
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 06/12/2015
From: Gebbie J
Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
AEP-NRC-2015-44, RIS-15-005
Download: ML15167A040 (4)


Text

INDIANA Indiana Michigan Power MICHIGAN Cook Nuclear Plant POWER" One Cook Place Bridgman, MI 49106 A unit of American Electric Power Indiana Michiga nPower.com June 12, 2015 AEP-NRC-2015-44 10 CFR 50.4 Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 RESPONSE TO NRC REGULATORY ISSUE

SUMMARY

2015-05 PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS U. S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, "Preparation and Scheduling of Operator Licensing Examinations," dated April 20, 2015, requests licensees to update examination schedules and applicant estimates for calendar years 2017 through 2020.

Indiana Michigan Power Company, the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, is providing, as an enclosure to this letter, NRC Form 536, "Operator Licensing Examination Data," which contains the details of CNP's examination schedule as requested.

There are no commitments included in this submittal. Should you have any questions, please contact Mr. Daniel M. Emery, Training Manager at (269) 466-3372.

Sincerely, Joel P. Gebbie Site Vice President KMH/ams

Enclosure:

NRC Form 536, Operator Licensing Examination Data 1ý11A 0 0 2--ý

U. S. Nuclear Regulatory Commission AEP-NRC-2015-44 Page 2 c: A. W. Dietrich, NRC Washington DC J. R. Kweiser - NRC Region III NRC Resident Inspector H. Peterson - NRC Region III

ENCLOSURE TO AEP NRC 2015-44 NRC FORM 536 OPERATOR LICENSING EXAMINATION DATA

NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/3112017 (01-2015) Estimated burden per response to comply mith this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden estimate to the FOIA, Privacy, and Information OPERATOR LICENSING Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC EXAMINATION DATA 20555-0001, or by intemet e-mail to lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Donald C. Cook Nuclear Plant 3 One Cook Place Bridgman, MI 49106 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2016 CY 2018 CY 2020 CY 2022 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2016 CY 2018 CY 2020 CY 2022 NUMBER OF REACTOR 8 10 8 8 OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT 6 6 4 3 NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 7 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 PROPOSED DATES PRIMARY DATE 07/11/2016 07/23/2018 07/20/2020 07/18/2022 ALTERNATE DATE 07/18/2016 07/30/2018 07/27/2020 07/25/2022 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2017 CY 2019 PROPOSED .

NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 16 12 CANDIDATES NRC FORM 536 (01-2015)