05000498/FIN-2013003-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate Design Calculations for Spent Fuel Pool Mitigation Strategies |
Description | The inspectors identified a Green finding for the licensees failure to follow Procedure 0PGP04-ZA-0307, Preparation of Calculations, Revision 4. Specifically, two parts were not followed, step 3.1.5.4 states all design calculations SHALL be identified AND their sources indicated by providing an adequate title/description; and step 3.2.2 which instructs performing a peer check review of the calculation for completeness, clarity, and accuracy. As part of a routine walkdown of the spent fuel pool area, the inspectors identified several issues of concern regarding the licensees spent fuel pool mitigation strategy equipment which implements the fill and/or spray strategy. Specifically, the as-designed equipment did not match the as-installed configuration and the as-designed calculations did not account for standard engineering practices to ensure that all calculation considerations were taken into account. The licensee captured these issues in Condition Reports 13-3767 and 13-5006. Corrective actions included updating the calculations to include standard engineering practices and ensuring that the design matched the as-installed configuration. The failure to follow Procedure 0PGP04-ZA-0307 to ensure an adequate design calculation and review for accuracy was a performance deficiency. This finding was more than minor because it adversely affected the design control attribute of the Barrier Integrity cornerstone and affected the cornerstone objective to provide reasonable assurance that physical design barriers such as fuel cladding protect the public from radionuclide releases caused by accidents or events. The inspectors performed the significance determination process using NRC Inspection Manual Chapter 0609, Attachment 4, Initial Characterization of Findings, which evaluates the finding using Appendix L, B.5.b Significance Determination Process, Table 2 - Significance Characterization, and determined the finding was of very low safety significance because the finding did not result in an unrecoverable mitigating strategy due to the unavailability of post-accident cooling systems for the spent fuel pool. No cross-cutting aspects are assigned to this finding because the calculations were performed in 2007 and 2008 and are not considered indicative of current performance (Section 1R15). |
Site: | South Texas |
---|---|
Report | IR 05000498/2013003 Section 1R15 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | Finding: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.15 |
Inspectors (proximate) | L Ricketson J Dixon B Tharakan A Sanchez W Walker P Jayroe D You |
INPO aspect | |
' | |