Finding | |
---|---|
Title | Failure to Follow Procedure Results in Unplanned Reactor Core Isolation Cooling Unavailability |
Description | A self-revealed Green finding and associated Non-Cited Violation of Title 10 of the Code of Federal Regulations (CFR) Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings, was identified when the licensee failed to follow station procedure Clinton Power Station (CPS) 9030.01C034, RCIC [Reactor Core Isolation Cooling] Steam Line Flow E31N683A(B), E31N684A(B), Checklist. Specifically, the licensee failed to reset the isolation logic for the RCIC steam line outboard isolation valve prior to turning on the breaker for this valve. This resulted in the isolation of the steam supply to RCIC causing RCIC to become unavailable,and elevating the plant risk to Yellow. |
Site: | Clinton |
---|---|
Report | IR 05000461/2018001 Section 1R22 |
Date counted | Mar 31, 2018 (2018Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.22 |
Inspectors (proximate) | W Schaup E Sanchez L Rodriguez C Phillips S Mischke K Stoedter |
Violation of: | 10 CFR 50 Appendix B Criterion V |
INPO aspect | LA.5 |
' | |