05000445/FIN-2009005-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Control Coolant System Pressure During Solid Plant Operations |
Description | The inspectors reviewed a self-revealing noncited violation of Technical Specification 5.4.1.a for the failure of operators to follow procedural requirements for maintaining reactor coolant system pressure. Specifically, a reactor operator adjusted charging flow during solid plant operations and failed to control the reactor coolant system pressure increase. As a result, a power operated relief valve lifted to provide low temperature overpressure protection of the reactor coolant system. The licensee entered the finding into the corrective action program as Condition Report CR-2009-005542. The finding was more than minor because it was associated with the human performance attribute of the initiating events cornerstone and affects the cornerstone objective to limit those events that upset plant stability and challenge critical safety functions during shutdown operations. Specifically, the inadvertent lifts of the power operated relief valves could lead to a loss of reactor coolant system inventory and pressure control. Using NRC Manual Chapter 0609, Appendix G, Attachment 1, Checklist 2, the finding was determined to be of very low safety significance because the licensee maintained adequate mitigation capability for the current plant state and the event was not characterized as a loss of control condition. The finding has a human performance crosscutting aspect associated with decision making because the licensee did not formally define the role of the reactor operator maintaining reactor coolant system pressure H.1a |
Site: | Comanche Peak |
---|---|
Report | IR 05000445/2009005 Section 1R20 |
Date counted | Dec 31, 2009 (2009Q4) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.2 |
Inspectors (proximate) | K Clayton B Tharakan L Carson W Walker B Tindell J Mateychick D Bollock D Graves T Buchanan J Kramer N Hernandez J Dixon |
CCA | H.13, Consistent Process |
INPO aspect | DM.1 |
' | |
Finding - Comanche Peak - IR 05000445/2009005 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Comanche Peak) @ 2009Q4
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||