Title | Failure to Evaluate Fire Wrap Testing Discrepancies |
Description | A noncited violation of License Condition 2.C(41), Fire Protection Program, was identified because the licensee failed to evaluate vendor fire test results to ensure that deviations from the acceptance criteria did not result in a reduction in the effectiveness of the approved Fire Protection Program. The licensee replaced existing fire barrier material installed on conduits with 3M Interam fire wrap without recognizing that applicable NRC test criteria were not met. As a result, the licensee failed to perform an evaluation to determine whether the test results would result in a reduction in the effectiveness of the fire protection provided to the cables inside the affected conduits. The new fire wrap was installed to protect redundant trains of cables necessary for safe shutdown between 2004 and 2007. This finding was entered into the licensees corrective action program under Condition Report 2008-01910. The licensee took prompt compensatory measures and implemented hourly fire watches while the issue was being evaluated. Failure to properly evaluate vendor fire test results that did not satisfy the acceptance criteria in Generic Letter 86-10, Supplement 1 prior to changing the existing fire wrap with 3M Interam fire wrap as required by the approved Fire Protection Program was a performance deficiency. This finding was more than minor because it affected the protection against external factors (fire) attribute of the Mitigating Systems Cornerstone Objective to ensure the availability, reliability, and capability of systems that respond to initiating events in order to prevent undesirable consequences. This performance deficiency was also similar to the more than minor portion of Inspection Manual Chapter 0612, Appendix B, Example 3.i, in that an engineering evaluation was necessary to determine the acceptability of the existing fire wrap to perform its intended function. This finding was evaluated using Inspection Manual Chapter 0609, Appendix F, Fire Protection Significance Determination Process, because it affected fire protection defense-in-depth strategies involving post-fire safe shutdown systems. This finding screened as having very low safety significance because it involved a fire barrier with a low degradation, since the nonconforming condition was subsequently determined to provide an acceptable margin to damage for the cables being protected |
Site: | Grand Gulf |
---|---|
Report | IR 05000416/2008006 Section 1R05 |
Date counted | Sep 30, 2008 (2008Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.05 |
Inspectors (proximate) | N O'Keefe K Sullivan S Alferink R Bywater R Mullikin P Qualls |
INPO aspect | |
' | |