05000412/LER-1993-001, :on 930126,identified That Stress on AFW Piping to C SG Exceeded Design Stress Due to Water Hammer.Station Will Perform ISI Insps of AFW Piping & Replace Mechanical Snubbers W/New Hydraulic Snubbers

From kanterella
(Redirected from 05000412/LER-1993-001)
Jump to navigation Jump to search
:on 930126,identified That Stress on AFW Piping to C SG Exceeded Design Stress Due to Water Hammer.Station Will Perform ISI Insps of AFW Piping & Replace Mechanical Snubbers W/New Hydraulic Snubbers
ML20034F226
Person / Time
Site: Beaver Valley
Issue date: 02/25/1993
From: Freeland L
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LER-93-001, LER-93-1, ND3MNO:3417, NUDOCS 9303020427
Download: ML20034F226 (6)


LER-1993-001, on 930126,identified That Stress on AFW Piping to C SG Exceeded Design Stress Due to Water Hammer.Station Will Perform ISI Insps of AFW Piping & Replace Mechanical Snubbers W/New Hydraulic Snubbers
Event date:
Report date:
4121993001R00 - NRC Website

text

_

i

'%f Telephone (412) 393-6000 Nuclear Group P.O Box 4 Shippingport FA 15077MM i

February 251993

?

ND3MNO:3417 1

i Beaver Valley Power Station, Unit No. 2 l

Docket No. 50-412, Licensee No. NPD-73 LER 93-001-00 l

i t

United States Nuclear Regulatory Commission l

Document Control Desk Washington, DC 20555 i

Gentlemen:

In accordance with Appendix A, Beaver Valley Technical Specifications, the following Licensee Event Report is submitted:

{

i LER 93-001-00,10 CFR 50.73.a.2.ii.B, " Design Stress for the Auxiliary i

Feedwater System Exceeded Due to Water Hammer."

- i j

^

j Freeland l

General Manager i

Nuclear Operations

{

DJS/s1 j

i Attachment j

C2005G l

l 1

9303020427 930225

/

[I PDR ADOCK 05000412-

/

t S

pop 1 ;

U.

i

1 r

February 251993 ND3MNO:3417

~

Page 2 i

cc:

Mr. T. T. Martin, Regional Administrator United States Nuclear Regulatory Commission Region 1 475 Allendale Road i

King of Prussia, PA 19406 Mr. G. E. Edison, BVPS Licensing Project Manager United States nuclear Regulatory Commission Washington, DC 20555 Larry Rossbach, Nuclear Regulatory Commission, BVPS Senior Resident Inspector l

J. A. Holtz, Ohio Edison 76 S. Main Street Akron, OH 44308 l

Larry Beck Centerior Energy 6200 Oak Tree Blvd.

Independence, OH 44101-4661 INPO Records Center Suite 1500 1100 Circle 75 Parkway Atlanta, GA 30339 t

G. E. Muckle, Factory Mutual Engineering 680 Anderson Drive #BLD10 Pittsburgh, PA 15220-2773 Mr. Richard Janati Department of Environmental Resources P.O. Box 2063 16th Floor, Fulton Building Harrisburg, PA 17120 Director, Safety Evaluation & Control Virginia Electric & Power Co.

P.O. Box 26666 One James River Plaza t

Richmond, VA 23261 E

\\-

, - - - - ~

v

,v.-

,4-, -,,

%.-,%-,... 3

NRC 70QM 3h6 U.E. NUCL EAR REGULATORY COMMIS$10C3 APPROVED OMB NO 3% Dea E KPIRE S 4/30/97 ESTIMATED SURDEN PER RE$PON5t TO COMPLv WTH TMtB LlCENSEE EVENT REPORT (LER)

Espa"#sWGiR'DTG fU' " "' Es'#M#aD'sE 5'ECc'R%

DEN AND RE PORTS MANAGtMENT BRANCH (P630L b & buCLEAR EE GUL ATORY COMMISSION. W ASHINGTON. DC 205%, AND TO THE P APE RWORK RE DUCT 80N PROJi CT (31M41Dal. OF F ICE OF MANAGEMENT AND BUDGET,tNASHINGTON.DC 20b03.

FOCILITV NAME (15 DOCKET IWUMBE R (24

' AGE 4 Beaver Valley Power Station Unit 2 o ;5 ; o g o ; o ; 4; 1l 2 ilorlOg4 TITLE to:

Design Stress Fcr The Auxiliary Feedwater System Exceeded Due To Water Harnmer EVENT DATE (5)

LER NUMBE R 16)

REPORT DATE 47p OTHER S ACtLtTitS INVOLVED 181 MONTH Day YE. AR YEAR MON T M DAY YEAR F ADuiv Nawts DOCw(T NUMBE RiSI g

N/A 015101010 1 1 1 0l 1 - 2l 6 93 9l 3 0l 0l 1 0l0 0l2 2l 5 9j3 jo,5,o,o,o, l,

Twis REPORT is susMiTTED PuRauhNT TO Tui RL OuiRiMcNT: O, in C.R g.,cw.c....

e.,,....,,

<iii "oot =

1 ro.orm ro.osai

.o 73 man.,

73nw Em 2C so6tsH1101 60 3sich16 50 73talGH=l 73 71(c) 0;90 gaggge,A,agg 1

ro.oswmu

.owm E.o Tai.ian. o f101 20.406te H1 Han!

50.73w H2 nd So 73 alG)i.edHAl

.M6Al 20 ameH1H*vi X

so T3i.urrw so 73wunn. +ei 20 405taHi H.)

Do13esK2Hesil 60 73talGHal LICE NSE E CONTACT FOR TMrs LER 1121 NAME TE LEPHONE NUMBER AFL A CODE L R. Freeland. General Manager Nuclear Operations 4,1,2 6,4,3,

,l i 2,5;8 COM*LETE ONE LINE FOR f ACH COMPONENT FalLUPE DE SCRe86 D IN THIE REPORT f13)

E[

TO NPR C

O a

CAUSE

$4 5TE M COMPONENT

CAUSE

SYSTEM COMPONE N1 g

p B

BA SPT P

N O 2l 9 l

1 I I i

! I i 1

1 1 1 1

1 1 I I I I I 1

! I I I I I SUPPLEMENT AL REPORT E KPECTED {146 MONTM DAY vfAR

$UBvrS5 TON vis U, vns compes. t xPECTC SusutsSION CATE1 NO l

l l

A e rT R ACT u,~,, um,-

4...,,,...-,+, -..-.

,w..,-.

- n.

On 1/26/93 at 1720

hours, the results of extensive engineering analysis of previous plant events identified that the stress on the Auxiliary Feedwater (AFW) piping to the "C" Steam Generator, for combined water hammer and seismic events, exceeded the design stress allowables.

It has been hypothesized that the "C" AFW line has been subjected to water hammer due to steam pocket formation (voiding) and steam bubble collapse.

There have been two events at Beaver Valley Power Station Unit 2 since it went operational in 1987 that have been attributed to water hammer.

The location of the inside containment AFW check valves (inside CV's) and piping layout have the potential to

cause

voiding (see Figure 1).

The inside CV's are located near the main feedwater lines causincJ the piping upstream to be at elevated temperatures.

The inside CV's are also at a

higher elevation

.a n the AFW supply tank minimum water level.

If the inside CV's leak rate is less than the outside CV's, the AFW piping will depressurize causing voiding upstream of the inside CV's due to elevated temperatures.

AFW automatic actuation with unthrottled flow to a

voided AFW line is the main concern for water hammer.

There were minimal safety implications as a result of this event.

The mechanical snubbers were replaced with new hydraulic snubbers with a higher load rating.

NQC F.,m 366 (649)

_______________._____________________._______________j

x

~.

= ~.

hetCFORM306A U.S. NUCLEAR REGULATO3tv COMMISSION E kP6MES. Af30!92

{

UCENSEE EVENT REPORT (LER)

  • '4",;^.'Mo',73Es"oM3"MT'.37J,',7,*J"O TEXT CONTINUATION

!?""470,"#.'Mai&#'*dEc'O','El,"',TC C' i

5 UE"PAPEn"JcS?"fE'!'uET'io%^EI'c?'afi.oEE UE?ci f

'^'

OF MANAGE ME NT AND BUDGET, sWASHsNGTON.DC 20bo3.

[

s

' ACfLITV hAME IU DOCRET NUMELR Cl LER WUMBER (61 PAGE(3)

.f

'E*a

-" W P.','

3*,T 7

0 j0 0l 2 or 0 l4 f

Beaver Vauey Power Station Unit 2 ol5lololol4l1l2 9l3 0l0l1 Text rn i a.

,=,,me s.,,,, assm on

Description of Event

On 1/26/93 at 1720

hours, the results of extensive engineering analysis of previous plant events identified that the stress on the Auxiliary Feedwater (AFW) piping to the "C"

Steam Generator, for combined water hammer and seismic events, exceeded the design stress allowables.

It has been hypothesized that the "C" AFW line has been subjected to water hammer due to steam pocket formation (voiding) and

{

steam bubble collapse.

There have been two events at Beaver Valley Power Station Unit 2

since it went operational in 1987 that could be attributed to water hammer.

In event No 1, identified in April 1989, mechanical snubbers 2FWE-PSSP-009 and 2FWE-PSSP-010 on the "C" AFW line were found mechanically frozen durincJ an ISI inspection.

The cause of i

event no.

I was unknown at that time and the snubbers were replaced with identical new snubbers.

Event No.

2, identified in April 1992, t

j mechanical snubber 2FWE-PSSP-009 was found mechanically frozen and l

snubber 2FWE-PSSP-010 Pas found damaged during an ISI inspection on the l

l "C"

AFW line.

The cause for the snubber failure / damage was apparently i

due to excessive compressive or impact loading as a result of an unanticipated water hammer.

The mechanical snubbers were replaced with-new hydraulic snubbers with a higher load rating.

j i

l The location of the inside containment AFW check valves (inside CV's) l and piping layout have the potential to cause steam voiding (see Figure 1).

The inside CV's are located near the main feedwater lines causing l

the piping upstream to be at elevated temperatures (measured 268.3 degree F on top of pipe, 200 degrees F on bottom of pipe, approximately 2

feet upstream of the "C" AFW check valve).

The inside CV's are at a higher elevation than the AFW supply tank minimum water level.

If the I

inside CV's leak rate is less than the outside CV's, the AFW piping will depressurize causing voiding upstream of the inside CV's due to elevated temperatures.

The "C" AFW line has been depressurized.

Cause of Event

e The results of extensive engineering analysis of previous plant events identified that the stress on the Auxiliary Feedwater (AFW) piping to the "C"

Steam Generator, for combined water hammer and seismic events, exceeded the design stress allowables.

The AFW piping and pipe l

supports are classified as QA Category I, seismic, safety class II.

The piping is designed to the requirements of the ASME Boiler and j

Pressure Vessel

Code, Section
III, 1971 Edition including addenda through Wint^r 1972.

The supports are designed to the guidelines established 7

the 6th Edition of the AISC manual of Steel Construction.

The AFW piping and supports have been designed for

thermal, pressure,
deadload, and seismic conditions.

Anticipated or l

" designed" water hammer transients were not previously analytically i

considered.

It was previously assumed that the piping layout and j

components had been designed to preclude the development of postulated I

water hammer events.

In retrospect, there is the potential for l

unanticipated water hammer as a

result of unthrottled AFW flow from j

automatic AFW pump starts to a potentially voided "C" AFW line.

j wac Fo.m 3e6A (689)

V NRC FOR.:B 3eEA 4LE, NUCE EAR REGULATDAY COMMIS$3DN E XPiRES: 4/30/B2 LICENSEE EVENT REPORT (LER)

'Us"A^.'f o*J'"8[M',",c 'EE*uE'i,$'l"A","o'n"JA a

TEXT CONTINUATION

!?"*4"48."d".^7l"Gi,",?$'UUC". 'JhM".TENA 5

0?Tli JJ?"arao"N M"fe"e?&Pa:0?.C?

OF MANAGEMENT AND BUDGET. WASHINGTON.DC 206C3 F ActLfTY hAME (1)

DOCKET NUMBE R (2)

LER NUMBER ($)

PAGE (3)

VEAR

. EE t

SAL m a k p

n Beaver Valley Power Station Unit 2 o l5 l0 lo lo l 4l1l2 9l 3 0l 0l 1 0l0 0l3 or 0 l4 TEXT (# mere pace is regu.est ese edcheonet NRC Form M4 W (17)

Corrective Actions

i The following corrective actions have been or will be taken as a result of this event:

1.

Frequent monitoring of the AFW piping for evidence of elevated containment penetration temperatures, system pressures (temporary pressure gages t

installed), noise / water hammer.

2.

A Basis for Continued Operation (BCO) has been prepared to document operation in this condition.

This is based upon analysis to quantify loads resulting from a postulated water hammer event.

3.

The Station is pursuing a long term solution.

4.

The Station will perform ISI inspections of the

]

AFW piping and piping supports in containment following an unplanned AFW pump start that results in unthrottled AFW flow.

5.

The mechanical snubbers were replaced with new hydraulic snubbers with a higher load rating.

The new hydraulic snubbers are adequately sized to withstand a water hammer event.

Reportability

i This report is being submitted in accordance with 10CFR50.73.a.2.ii.B because this event resulted in operation outside the Unit 2 design basis.

Safety Implications d

The safety implications are minimal.

Engineering analysis has shown that in cases where the pipe stress levels under the-revised load combinations (to include water hammer) occurring simultaneously with a

seismic event exceeded original design code normal / upset allowables, an assessment of system operability was made to the design code faulted allowables.

The pipe stress

levels, for combined water hammer and seismic
events, are now within the design code faulted allowables.

In developing the BCO, it was determinen that the use of alternate code faulted allowables (i.e. Appendix F or later revisions of the ASME code) was not required due to the rigorous analysis performed to more adequately quantify the stress.

Previous Similar Events

There were no previously reported similar events.

NRC Fem 3e6A (6491

roRMas.A u.exuctEmEsute.ToRv Commission EXflRE.8 4/3022 5

LICENSEE EVENT REPORT (LER)

'S'"RfAio*N E85"dP "'$a"$dTT sof*L',',"OR.1"RS U

C D

g a rg COMMENTS S EGM.DtNG DoWDEN ESTIMATE TO THE RECOMDS w p0 TeNUM e s0N AND REPORTS MANAGEMENT BRANCH (*4301. U S NUCLE AR TEA 5 w

1*ef PAPER.Y COMMIESiON. t4ASHINGTON. DC 70%5 AND REGULATOR ORK REDUCTaON PROJECT 131600104). OF FICE OF MANAGEME,NT AND BUDGET. WASHINGTON DC 20$03.

FACILIYV hAME fil DOCEET NUMBER Lil ggg gygggg qg,

. pagg g,,

"em;;'

@i:::

i

~~

l Beaver Valley Power Station Unit 2 o l5 l0 l0 l0 l4 l1 l2 9l3 0l0l1 0 l0 0l 4 OF 0 l4 Yut w-M

. %. - we %.Muw nTi Figure No. 1

'2FWE-99 LOOP A'

2FWE-18$ LOOP 'B'

, 2FWE-ist LOOP 'C'

. 2FWE-42A1 t00P 'A' 2FWE-428I 2FWE-43A 777*-8*

2FWE-438} LOOP'B.

775'-8*

I 2FWE-44A 1 LOOP 'C' 2FWE-448 3 is;:l=1tDoeC-is.i.

=}to.e-

'C

- =~

,5,. 18

^$.

f HCV-180F 74 /'-11'

/* *

  • 745*-6*

74 3*-8' j TANK

.../

W, 2FWE*1K218 737'-2' 735'-8*

h RECIRCULATlON CONTAINHENT SAFEGUARDS 44 3

721'-3*

FCV m

PDETRATIONS: X-79 X-88 AUX. FEED PUMPS X-83 2FWE-P22 2FWE-P23A 2FWE-P238 NRC Form 3ASA (649)