05000400/FIN-2013003-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | |
Description | A self-revealing Green finding (FIN) was identified for the licensees failure to adequately implement their procedure CAP-NGGC-0205, Condition Evaluation and Corrective Action Process, for two oil leaks from the B MFP which occurred on February 14, 2013 and February 17, 2013. Specifically, these failures resulted in a significant oil leak on the B MFP which required a rapid downpower to 55 percent RTP on March 29, 2013. The licensee entered this finding into their CAP as Action Request (AR) #598302. The licensee took corrective action to perform a design change to the breather to correct the plant issue. The licensees failure to adequately implement their procedure CAP-NGGC-0205 was a performance deficiency. The performance deficiency was more than minor because it was associated with the human performance attribute of the Initiating Events cornerstone and affected the cornerstone objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions. Specifically, this failure resulted in another oil leak on the B MFP which required a rapid downpower to 55 percent RTP on March 29, 2013. In accordance with IMC 0609.04, Initial Characterization of Findings, and Exhibit 1 of IMC 0609, Appendix A, The Significance Determination Process (SDP) for Findings at Power, the inspectors determined that this finding was of very low safety significance (Green) because the performance deficiency did not cause a reactor trip or the loss of mitigation equipment. The finding had a cross-cutting aspect of Evaluation of Identified Problems, as described in the Corrective Action component of the Problem Identification and Resolution cross-cutting area because the licensee failed to thoroughly evaluate the two oil leaks in February 2013 to ensure that the resolution addressed the cause, resulting in the transient on March 29, 2013. |
Site: | Harris |
---|---|
Report | IR 05000400/2013003 Section 1R04 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | Finding: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.04 |
Inspectors (proximate) | A Butcavage A Nielsen G Hopper J Austin P Lessard R Pursley |
CCA | P.2, Evaluation |
INPO aspect | PI.2 |
' | |
Finding - Harris - IR 05000400/2013003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Harris) @ 2013Q2
Self-Identified List (Harris)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||