05000387/FIN-2008002-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate Application of Work Instructions Resulted in Unavailable and Inoperable Engineering Safeguards Electrical Bus (Section IR12) |
Description | A self-revealing, Green NCV was identified for failure to accomplish work in accordance with the appropriate instructions as required by 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings. Specifically, PPL did not complete the required actions that would properly protect the Unit 1 transformer 1X210 windings from moisture intrusion when heat was not applied to the transformer as specified by the work instructions and original equipment vendor manual. This resulted in high initial Doble test results, an investigation into cause, a drying out period, and additional Doble testing which caused an approximate 24-hour delay in the restoration of the safety-related 1A 4 KV ES bus. This electrical bus provides power to common safety-related loads which increased the online risk for Unit 2, the operating unit during the Unit 1 refueling outage. PPL applied concentrated heat and energized the primary windings to remove moisture from the windings prior to returning the transformer to service. This finding is greater than minor because it adversely impacted the equipment performance attribute of the Mitigating Systems cornerstone and affected the objective to ensure the availability, reliability and the capability of systems that respond to initiating events to prevent undesirable consequences. This finding was considered to have very low safety significance (Green), using phase one of the significance determination process for Unit 2. A contributing cause of this finding is related to the Human Performance cross-cutting area, work control planning attribute H.3.(a). Specifically, PPL did not appropriately plan and coordinate the work activities by incorporating job site conditions, including environmental conditions. (Section IR12 |
Site: | Susquehanna |
---|---|
Report | IR 05000387/2008002 Section 1R12 |
Date counted | Mar 31, 2008 (2008Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.12 |
Inspectors (proximate) | J Furia G Ottenberg D Orr F Jaxheimer H Gray P Krohn P Kaufman |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |