Finding | |
|---|---|
| Title | Failure to take adequate corrective actions for a condition affecting control room operability and temperature limits post-trip. (Section 4OA2.a.3.a) |
| Description | The inspectors identified a Green non-cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, for Dominions failure to take adequate corrective actions for a condition adverse to quality involving the potential for Unit 2 control room temperature heat-up challenging equipment operability and personnel habitability thresholds following a reactor trip. Specifically, in 2007, Dominions associated operability review, issue prioritization, and subsequent evaluation did not adequately consider post-trip time critical operator tasks, operator training, and control room heat-up rate calculations. As a result, Dominion incorrectly concluded that no further action was needed to ensure that control room temperature limits were not exceeded. Dominions short-term corrective actions included review of a control room heat-up calculation, providing interim direction to the operating crews concerning control room air conditioning (A/C) restoration, and updating applicable emergency operating procedures to ensure adequate control room cooling was maintained. The finding is more than minor because it was associated with the procedural quality attribute for the Mitigating System cornerstone and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems (and personnel) that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, Dominion did not ensure that control room temperature limits would not be exceeded for non-accident post-trip events involving a loss of control room A/C which could directly impact the reliability of safety-related equipment operated from the control room. This finding is of very low significance because it did not result in the loss of operability or functionality. This finding has a cross-cutting aspect in the area of Problem Identification and Resolution, Corrective Action Program Component, because Dominion did not properly evaluate a condition adverse to quality including properly classifying, prioritizing, and evaluating for operability (P.1.c). (Section 4OA2.a.3.a |
| Site: | Millstone |
|---|---|
| Report | IR 05000336/2008006 Section 4OA2 |
| Date counted | Mar 31, 2008 (2008Q1) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71152 |
| Inspectors (proximate) | M Gray S Mccarver J Benjamin J Tifft |
| CCA | P.2, Evaluation |
| INPO aspect | PI.2 |
| ' | |
Finding - Millstone - IR 05000336/2008006 | |||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Millstone) @ 2008Q1
| |||||||||||||||||||||||||||||||||