Text

ber 3, 2008

SUBJECT:

MILLSTONE POWER STATION - NRC TEAM INSPECTION REPORT 05000336/2008007 and 05000423/2008007

Dear Mr. Christian:

On August 28, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a team inspection of your Millstone Power Station Units 2 and 3. The enclosed report documents the teams results, which were discussed on August 28, 2008, with Mr. Skip Jordan and other members of your staff.

The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the condition of your operating license. Within these areas, the inspection involved examination of selected procedures and records, observation of activities, and interviews with station personnel.

This report documents one NRC-identified finding of very low safety significance (Green). This finding was determined to involve a violation of NRC requirements. Because of the very low safety significance and because this violation was entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV), in accordance with Section VI.A.1 of the NRC Enforcement Policy. If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Millstone Nuclear Power Station.

In accordance with 10 CFR 2.390 of the NRC Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of the NRC Agency-wide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, When separated from the Enclosure, this document is DECONTROLLED. D Christian 2 because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Sincerely,

/RA/

John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos.: 50-336, 50-423 License Nos.: DPR-65, NPF-49 Enclosure: Inspection Report 05000336/2008007 and 05000423/2008007 w/Attachment: Supplemental Information