| Q | CCA | Title |
---|
05000327/FIN-2010002-01 | 2010Q1 | H.12 | Reactor Trip due to Inadequate Configuration Control |
05000327/FIN-2010007-01 | 2010Q2 | P.2 | Violation of 10 CFR 50, Appendix B, Criterion V for Failure to Follow Procedure for Vendor Contact Program |
05000327/FIN-2010007-02 | 2010Q2 | | Degraded Voltage Relay Issue |
05000327/FIN-2010004-01 | 2010Q3 | P.1 P.1(a) | Inadequate Inspection of Raw Water Side of Containment Spray Heat Exchangers |
05000327/FIN-2010004-02 | 2010Q3 | | Non-Conservative Design Calculation for RHR Suction Temperature Limit |
05000327/FIN-2010004-03 | 2010Q3 | H.14 | Failure to Maintain Thermal Power Less Than Licensed Limit |
05000327/FIN-2010005-02 | 2010Q4 | H.4 H.5 | Failure to implement Technical Specification requirements to vent ECCS piping |
05000327/FIN-2010005-03 | 2010Q4 | | Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations |
05000327/FIN-2010404-01 | 2010Q4 | | Security |
05000327/FIN-2010005-01 | 2010Q4 | | Failure to Collect Reactor Coolant Pump Oil Leakage |