05000293/FIN-2016007-02
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | |
Description | The team documented a self-revealing violation of 10 CFR 50, Appendix B, Criterion III, Design Control, as Entergy failed to verify the adequacy of the design to assure that applicable regulatory requirements and the design basis were correctly translated into safety-related SSW pump discharge piping support installation instructions. Specifically, Entergy did not assure that the SSW pump discharge piping supports were installed in accordance with design drawings which called into question the operability of both SSW loops. Entergys short-term corrective actions included implementing a permanent plant modification for the D SSW pump support and temporary modifications on the A, B, and E SSW pump discharge piping supports. The finding is considered more than minor because it is associated with the design control (initial design) attribute of the Mitigating Systems cornerstone and adversely affected the cornerstones objective of ensuring the reliability, availability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). The team evaluated the significance of this finding using IMC 0609, Appendix A, The Significance Determination Process for Findings at Power, Exhibit 2, Mitigating Systems Screening Questions. The team determined the finding screened as very low safety significance (Green) because the finding was a design deficiency which did not result in a loss of functionality of the SSW pump supports. This finding did not have a cross-cutting aspect because the most significant contributor of the performance deficiency occurred during initial construction and, thus, was not reflective of current Entergy performance. (Section 1R17.2.1.b.2) |
Site: | Pilgrim |
---|---|
Report | IR 05000293/2016007 Section 1R17 |
Date counted | Jun 30, 2016 (2016Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.17 |
Inspectors (proximate) | J Rady J Schoppy M Orr |
Violation of: | 10 CFR 50 Appendix B 10 CFR 50 Appendix B Criterion III, Design Control |
INPO aspect | |
' | |
Finding - Pilgrim - IR 05000293/2016007 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Pilgrim) @ 2016Q2
Self-Identified List (Pilgrim)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||