05000293/FIN-2016004-06
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Licensee-Identified Violation |
Description | TS 3.9.B.2 requires that when incoming power is not available from both startup and shutdown transformers, continued operation is permissible, provided both diesel generators and associated emergency buses remain operable, all core and containment cooling systems are operable, and reactor power level is reduced to 25% of design. Contrary to the above, on seven occasions between 2005 and August 27, 2014, for an average of 3.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, Entergy conducted test Procedures 3.M.3-1, A5/A6 Buses 4kV Protective Relay Calibration/Functional Test and Annunciator Verification Critical Maintenance, and 3.M.3-29, Shutdown Transformer and 23kV Relay Calibration and Functional Test, that placed the plant in a condition not allowed by TS 3.9.B.2. Specifically, the testing would have prevented emergency buses A5 and A6 from automatically transferring to their backup power supplies. Entergy entered this condition into their CAP as CR 2016- 2735. A Region I SRA conducted a detailed risk evaluation for this issue using IMC 0609, Appendix A, Significance Determination Process for Findings At-Power, issued June 19, 2012. Using the average time from above, along with operator recovery actions, the SRA calculated the change in core damage probability to be <1E-7, which was considered to be of very low safety significance (Green) |
Site: | Pilgrim |
---|---|
Report | IR 05000293/2016004 Section 4OA7 |
Date counted | Dec 31, 2016 (2016Q4) |
Type: | NCV: Green |
cornerstone | No Cornerstone |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | A Burritt B Deboer B Dionne B Pinson E Carfang J Deboer J Nicholson J Vasquez N Embert P Cataldo P Ott |
Violation of: | Technical Specification |
INPO aspect | |
' | |
Finding - Pilgrim - IR 05000293/2016004 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Pilgrim) @ 2016Q4