Semantic search

Jump to navigation Jump to search
 Issue dateTitle
IR 05000382/202300124 April 2023Integrated Inspection Report 05000382/2023001, Independent Spent Fuel Storage Installation Report 07200075/2023001, and Exercise of Enforcement Discretion
ML22300A20830 November 2022Issuance of Amendment No. 269 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors
IR 05000382/20220021 November 2022Revised Integrated Inspection Report 05000382/2022002
ML22217A1119 August 2022Integrated Inspection Report 05000382/2022002
IR 05000382/202200117 May 2022Reissue IR 05000382/2022001
W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.16 May 2022Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.
ML22125A27310 May 2022Transmittal of Final Waterford Steam Electric Station, Unit 3 Accident Sequence Precursor Report (Licensee Event Report 382-2021-001) (Letter)
ML22124A3068 May 2022Integrated Inspection Report 05000382/2022001
ML22122A1904 May 2022Final Accident Sequence Precursor Analysis - Waterford Steam Electric Station Loss of Offsite Power Due to Hurricane Ida (LER 382-2021-001) - Precursor
ML21082A30219 May 2021Issuance of Amendment No. 259 to Revise Emergency Action Levels to a Scheme Based on NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors
W3F1-2021-0024, Emergency Preparedness Documents11 March 2021Emergency Preparedness Documents
W3F1-2021-0003, Application for Technical Specification Change to Adopt Risk-Informed Extended Completion Times - RITSTF Initiative 4B8 February 2021Application for Technical Specification Change to Adopt Risk-Informed Extended Completion Times - RITSTF Initiative 4B
W3F1-2020-0047, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, System, and Components (Sscs) for Nuclear Power Reactors18 December 2020Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, System, and Components (Sscs) for Nuclear Power Reactors
W3F1-2020-0062, Response to U.S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request for Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 615 December 2020Response to U.S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request for Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6
ML18323A10330 November 2018NUREG-1437, Suppl. 59, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford Steam Electric Station, Unit 3 - Final Report
ML18201A49220 July 2018Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing...Inspection Report 05000382/2017009 and Notice of Violation
IR 05000382/201701120 December 2017NRC Special Inspection Report 05000382/2017011
ML17186A4215 July 2017WAT3 - Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans (05000382/2017009) and Reques
ML17045A1483 March 2017Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051
CNRO-2016-00024, Entergy - Form 10-K for Fiscal Year Ended December 31, 201520 December 2016Entergy - Form 10-K for Fiscal Year Ended December 31, 2015
ML16256A45225 August 2016Revision 309 to Final Safety Analysis Report, Chapter 9, Auxiliary Systems, Section 9.5
ML16348A46425 August 2016Redacted - Waterford Steam Electric Station, Unit 3, Revision 309 to Final Safety Analysis Report, Chapter 11, Radioactive Waste Management, Section 11.4
ML16344A05125 August 2016Redacted - Waterford Steam Electric Station, Unit 3, Revision 309 to Final Safety Analysis Report, Chapter 2, Site Characteristics, Section 2.4
ML16256A15325 August 2016Revision 309 to Final Safety Analysis Report, Chapter 2, Site Characteristics, Section 2.5
W3F1-2016-0031, Notification of Full Compliance with EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond-Design-Basis External Events21 July 2016Notification of Full Compliance with EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond-Design-Basis External Events
ML16126A03327 June 2016Issuance of Amendment Regarding Transition to a Risk-Informed, Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c)
IR 05000382/201600125 April 2016NRC Integrated Inspection Report 05000382/2016001, January 1, 2016 Through March 31, 2016
W3F1-2016-0012, License Renewal Application Waterford Steam Electric Station, Unit 3 (Waterford 3) (Part 9 of 9)23 March 2016License Renewal Application Waterford Steam Electric Station, Unit 3 (Waterford 3) (Part 9 of 9)
ML16088A32923 March 2016License Renewal Application Waterford Steam Electric Station, Unit 3 (Waterford 3) (Part 7 of 9)
IR 05000382/201500830 September 2015IR 05000382/2015008; 08/10/2015 - 08/27/2015; Waterford Steam Electric Station, Unit 3; Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
IR 05000382/201500230 July 2015IR 05000382/2015002; on 04/01/2015 - 06/30/2015; Waterford Steam Electric Station, Unit 3; Adverse Weather Protection, Problem Identification and Resolution
ML15099A5639 April 2015Public Meeting Summary - Regulatory Conference with Entergy Operations, Inc., for Waterford Steam Electric Station, Unit 3
W3F1-2014-0050, Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Un28 August 2014Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Unit 3
W3F1-2014-0025, Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)11 June 2014Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)
IR 05000382/201300830 January 2014IR 05000382-13-008; on 05/20/13 - 12/19/13; Waterford Steam Electric Station, Unit 3; Surveillance Testing
ML13220A40222 November 2013Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies
ML13324B13320 November 2013IR 05000382-13-004; on 07/01/2013 - 09/30/2013; Waterford Steam Electric Station, Unit 3, Integrated Resident and Regional Report; Fire Protection, Post-Maintenance Testing, and Other Activities
IR 05000382/201300420 November 2013IR 05000382-13-004; on 07/01/2013 - 09/30/2013; Waterford Steam Electric Station, Unit 3, Integrated Resident and Regional Report; Fire Protection, Post-Maintenance Testing, and Other Activities
ML13317A96920 November 2013Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Waterford Steam Electric Generating Station, Unit 3, TAC No.: MF0977
W3F1-2013-0059, Revised Flooding Walkdown Report - Entergy'S Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Da11 November 2013Revised Flooding Walkdown Report - Entergy'S Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi
ML13127A23324 May 2013Safety Assessment for Review of Response to 3/12/12 Request for Information Pursuant to 10 CFR 50.54(f) for Recommendation 9.3 Emergency Planning Communications Assessment
IR 05000382/201300214 May 2013IR 05000382-13-002; 01/01/2013 - 03/31/2013; Waterford Steam Electric Station, Unit 3, Integrated Resident and Regional Report; Adverse Weather Protection, Operability Evaluations and Functionality Assessments, and Surveillance Testing
W3F1-2013-0017, (Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events28 February 2013(Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
W3F1-2013-0010, (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.321 February 2013(Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3
ML12278A33120 December 2012Issuance of Amendment No. 238, Relocate Technical Specification (TS) 3.4.6, TS 3.7.5, TS 3.7.9, and TS 3.9.5 to the Technical Requirements Manual
W3F1-2012-0101, Flooding Walkdown Report - Entergys Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights ...27 November 2012Flooding Walkdown Report - Entergys Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights ...
W3F1-2012-0095, Response to a Request for Additional Information Regarding License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual26 November 2012Response to a Request for Additional Information Regarding License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual
IR 05000382/201200414 November 2012IR 05000382-12-004; 07/01/2012 09/30/2012; Waterford Steam Electric Station, Unit 3, Integrated Resident and Regional Report; Licensed Operator Performance, Maintenance Effectiveness, and Maintenance Risk Assessments
ML12310A4585 November 2012Request for Additional Information Email, License Amendment Request to Relocate Technical Specification (TS) 3.4.6, TS 3.7.5, TS 3.7.9, and TS 3.9.5 to the Technical Requirements Manual
W3F1-2012-0064, Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request27 September 2012Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request