Summary of Changes and Analysis for Revision 39 of PPM 13.8.1 Emergency Dose Projection System Operations
ML18206A423
Person / Time
Site: Columbia  Energy Northwest icon.png
Issue date: 07/24/2018
From: Gregoire D
Energy Northwest
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
GO2-18-094
Download: ML18206A423 (2)


Text

ENERGY Donald W. Gregoire Columbia Generating Station NORTHWEST P.O. Box 968, PE20 Richland, WA 99352-0968 Ph. 509.377.86161 F. 509.377.4674 dwgregoire@energy-northwest.com July 24, 2018 GO2-18-094 10 CFR 50.54(q) 10 CFR 72.44(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 205551

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCKET NO. 72-35

SUMMARY

OF CHANGES AND ANALYSIS FOR REVISION 39 OF PPM 13.8.1 EMERGENCY DOSE PROJECTION SYSTEM OPERATIONS

Dear Sir or Madam:

Enclosed is the summary of changes and analysis for Revision 39 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations issued on July 3, 2018.

The changes to the Plant Procedures Manual (PPM) have been evaluated in accordance with 10 CFR 50.54(q) and 10 CFR 72.44(f). The PPM, as revised, continues to meet the standards of 10 CFR 50.47(b) and the requirements of 10 CFR 50 Appendix E. The Enclosure contains a summary of changes and evaluations performed. Each change was evaluated in accordance with the station's 10 CFR 50.54(q) evaluation process. These changes do not create a reduction in effectiveness (RIE) of the approved emergency plan.

This submittal contains no new or revised regulatory commitments. Should you have any questions or desire additional information regarding these matters, please contact Sean E. Clizbe at (509) 377-4398.

Executed on the a_L(~ay of _-S,

_ J(_'f- - - ' 2018.

Respectfu I ,

~

D. W. Gregoire Manager, Regulatory Affairs

Enclosure:

Summary of Changes and Analysis cc: NRC Region IV Administrator NRC NRR Project Manager NRC Sr. Resident Inspector/ 988C Director- Spent Fuel Storage & Transportation, NMSS CD Sonoda, BPA / 1399 (email)

WA Horin -Winston & Strawn (email)

GO2-18-094 Enclosure Page 1 of 1 Summary of Changes and Analysis Revision 39 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations relocates guidance on the use of the Detailed URI program to an attachment. This change enhances the ability of the user to find this direction in an attachment versus in the body of the procedure. Additional changes include new Notes that provide guidance on system response during a loss of divisional power and a Note that describes operation of the PRM Stack Monitor sample rack. These changes do not reduce the effectiveness of the Emergency Plan and the Plan continues to meet the requirements in appendix §50 Appendix E and the planning standards of § 50.47(b).