ENS 46243
ENS Event | |
---|---|
18:30 Sep 9, 2010 | |
Title | Accident Evaluation Improperly Analyzed in the Integrated Safety Analysis |
Event Description | During a GNF-A [Global Nuclear Fuel-Americas] review of the Fuel Manufacturing Operation (FMO) Integrated Safety Analysis (ISA), it was determined at [1430 EDT] on September 9, 2010 that the accident evaluation associated with hydrogen containment in the Dry Conversion Process was improperly analyzed in the ISA. A loss of hydrogen containment was analyzed in the ISA, however appropriate Items Relied on for Safety (IROFS) to prevent or mitigate a hydrogen explosion, resulting in a loss of UF6 or HF containment, were not identified in the ISA.
The affected equipment was promptly shut down on September 9, 2010. Existing hydrogen detection systems were augmented to assure controls are available and reliable to perform their intended safety functions as interim compensatory measures. These controls were functionally verified prior to restart of the affected operations at 2230 [EDT] on September 9, 2010. The interim controls will be designated as IROFS upon completion of the ISA documentation update currently underway. This event is being reported pursuant to the reporting requirements of 10CFR70 Appendix A(b)(1) within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of discovery. The licensee considers this discovery to be of low safety significance because the discovery did not result in an unsafe condition. The required IROFS have been identified and are in place. The licensee notified the NRC Region 2 Office, the North Carolina Radiation Protection Section and the New Hanover County Emergency Preparedness Organization. |
Where | |
---|---|
Global Nuclear Fuel - Americas Wilmington, North Carolina (NRC Region 2) | |
License number: | SNM-1097 |
Reporting | |
Part 70 App A (B)(1) | |
Time - Person (Reporting Time:+19.5 h0.813 days <br />0.116 weeks <br />0.0267 months <br />) | |
Opened: | Scott Murray 14:00 Sep 10, 2010 |
NRC Officer: | Vince Klco |
Last Updated: | Sep 10, 2010 |
46243 - NRC Website | |
Global Nuclear Fuel with Part 70 App A (B)(1) | |
WEEKMONTHYEARENS 528112017-06-16T21:00:00016 June 2017 21:00:00
[Table view]Part 70 App A (B)(1) Unanalyzed Condition Identified ENS 507502015-01-21T20:00:00021 January 2015 20:00:00 Part 70 App A (B)(1) Dry Conversion Process Improperly Analyzed in the Current Integrated Safety Analysis ENS 502762014-07-12T21:30:00012 July 2014 21:30:00 Part 70 App A (B)(1) Items Relied on for Safety Associated with the Dry Scrap Recycle Operations Not Meeting Requirements ENS 487092013-01-30T20:30:00030 January 2013 20:30:00 Part 70 App A (B)(1) Completion of Integrated Safety Analysis Action Plan Balance of Plant Milestone ENS 486952013-01-22T20:30:00022 January 2013 20:30:00 Part 70 App A (B)(1) Unanalyzed Condition - Based on Ongoing Integrated Analysis Review ENS 485542012-12-03T18:30:0003 December 2012 18:30:00 Part 70 App A (B)(1) Items Relied on for Safety Associated with the Dry Scrap Recycle Furnace Improperly Analyzed ENS 484972012-11-09T16:00:0009 November 2012 16:00:00 Part 70 App A (B)(1) Unanalyzed Condition - System As-Found Condition Not Fully Described in Isa ENS 477052012-02-27T19:30:00027 February 2012 19:30:00 Part 70 App A (B)(1) Unanalyzed Piping Configuration Discovered ENS 473252011-10-05T18:00:0005 October 2011 18:00:00 Part 70 App A (B)(1) Item Relied on for Safety Not as Described in the Integrated Safety Analysis ENS 467102011-03-29T14:00:00029 March 2011 14:00:00 Part 70 App A (B)(1) Completion of Isa Action Plan Conversion Milestone ENS 463052010-10-02T17:30:0002 October 2010 17:30:00 Part 70 App A (B)(1) Unanalyzed Condition When Fuel Pellet Boats Became Stacked ENS 462432010-09-09T18:30:0009 September 2010 18:30:00 Part 70 App A (B)(1) Accident Evaluation Improperly Analyzed in the Integrated Safety Analysis ENS 457172010-02-23T16:00:00023 February 2010 16:00:00 Part 70 App A (B)(1) Unanalyzed Condition - Incomplete List of Safety Controls in Integrated Safety Analysis Summary ENS 454912009-11-11T20:00:00011 November 2009 20:00:00 Part 70 App A (B)(1) Incomplete Documentation of Criticality Safety Controls in Integrated Safety Analysis Summary 2017-06-16T21:00:00 | |