MONTHYEARML24213A2602024-07-31031 July 2024 Request for Additional Information LAR to Support Implementation of Framatome Gaia Fuel IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 ML24150A3362024-05-29029 May 2024 Request for Confirmation of Information Relief Request 1RR06 (Proposed Alternative) Susquehanna Nuclear, LLC Susquehanna Steam Electric Station (Susquehanna), Unit 1 Docket No. 50-387 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 ML24113A2502024-04-22022 April 2024 Request for Additional Information (e-mail 4/22/2024) License Renewal Commitment for Aging Management Program of Alloy 600 Components ML24102A1252024-04-10010 April 2024 Request for Additional Information for Susquehanna, Unit 1 Alternative Request 4RR-11 ML24065A3112024-03-0505 March 2024 Request for Additional Information (Redacted) (03/05/2025 E-mail from R. Guzman to S. Sinha) Framatome Gaia Fuel LOCA LAR ML23334A1502023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-02 ML23318A0952023-11-14014 November 2023 Request for Additional Information (E-mail Dated 11/14/2023) LAR to Revise TSs Related to Framatome Gaia Fuel ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information ML23199A2832023-07-18018 July 2023 Request for Additional Information (E-mail Dated 7/18/2023) LAR to Revise the Pressure-Temperature Limits ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23089A1882023-03-29029 March 2023 Request for Additional Information (E-mail Dated 3/29/2023) Spring 2022 Steam Generator Tube Inspection Report ML23073A1802023-03-14014 March 2023 Notification of Commercial Grade Dedication Inspection (05000336/2023010 and 05000423/2023010) and Request for Information ML23013A2082023-01-13013 January 2023 Request for Additional Information ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22146A1022022-05-26026 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000387/2022404 and 05000388/2022404 ML22146A0742022-05-25025 May 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22111A3132022-04-21021 April 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22041A1562022-02-10010 February 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000387/2022013 and 05000388/2022013 ML21316A1242021-11-18018 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Emergency Core Cooling Technical Specifications ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21182A2902021-07-0101 July 2021 7/1/2021 E-mail - Request for Additional Information Alternative Frequency to Supplemental Valve Position Verification Testing Requirements ML21112A3082021-04-22022 April 2021 Request for Additional Information (E-mail Dated 4/22/2021) License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML21105A1152021-04-15015 April 2021 Request for Additional Information (e-mail Dated 4/15/2021) Proposed LAR for Addition of Analytical Methodology to the Core Operating Limits Report for a LBLOCA ML21078A0332021-03-18018 March 2021 NRR E-mail Capture - Millstone Power Station, Unit 2 - Request for Additional Information - Proposed LAR to Revise TSs for Steam Generator Inspection Frequency ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21077A1652021-02-26026 February 2021 (02/26/2021 E-mail) Draft Request for Additional Information LAR to Revise Technical Specifications for Steam Generator Inspection Frequency ML21034A5762021-02-0303 February 2021 Request for Additional Information (e-mail Dated 1/3/2021) Alternative Request RR-05-06 Inservice Inspection Interval Extension for Steam Generator Weld Inspections ML20246G5612020-09-0202 September 2020 Request for Additional Information (E-mail Dated 9/2/2020) License Amendment Request for a One-Time Deferral of the Steam Generator Inspections ML20244A2902020-08-31031 August 2020 Request for Additional Information (E-mail Dated 8/31/2020) License Amendment Request to Revise Battery Surveillance Requirements ML20231A7172020-08-18018 August 2020 Request for Additional Information (e-mail Dated 8/18/2020) License Amendment Request to Revise TS Table 3.3-11 Accident Monitoring Instrumentation ML20184A0052020-07-0202 July 2020 Request for Additional Information (E-mail Dated 7/2/2020) Relief Request IR-3-33 for Limited Coverage Examiniations ML20075A0322020-03-15015 March 2020 Request for Additional Information (E-mail Dated 3/15/2020) Alternative Request IR-4-03 for Use of an Alternative Non-Code Methodology to Demonstrate Structural Integrity ML20056E4392020-02-21021 February 2020 Ti 2515/194 Inspection Documentation Request ML20050F9212020-02-19019 February 2020 Request for Additional Information (E-mail Dated 2/19/2020) Proposed LAR to Revise TS 3.8.1.1, AC Sources Operating ML20023D0372020-01-23023 January 2020 Request for Additional Information (E-mail Dated 1/23/2020) Proposed LAR to Revise TS 3.8.1.1, AC Sources Operating ML20010D2012020-01-0909 January 2020 Request for Additional Information Related to Request to Allow Application of Framatome Analysis Methodologies Necessary to Support a Planned Transition to Atrium 11 Fuel Under Maximum ML19361A0382019-12-23023 December 2019 12/23/19 E-mail from R.Guzman to S. Sinha - Draft Request for Additional Information Planned Audit of LAR to Revise TS 3.8.1.1 ML19319A0092019-11-14014 November 2019 NRR E-mail Capture - Draft RAI for SSES Units 1 and 2 LAR to Replace ESW Piping ML19319B1922019-11-14014 November 2019 NRR E-mail Capture - RAI for Susquehanna, 1 and 2 License Amendment Request - Replace the Emergency Service Water System and Residual Heat Removal Service Water System ML19277B9082019-10-0707 October 2019 Supplemental Information Needed for Acceptance of Requested Licensing Action Extension of Technical Specification 3.8.1.1, A.C. Sources - Operating, Allowed Outage Time ML19248D7552019-09-0505 September 2019 Request for Additional Information Via E-mail from R.Guzman to S. Sinha Proposed License Amendment Request to Adopt 10 CFR 50.69 ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19128A0232019-05-0707 May 2019 Request for Additional Information: Susquehanna Steam Electric Station, Units 1 and 2 License Amendment Request for ESW Piping Replacement ML19042A1822019-02-11011 February 2019 Request for Additional Information LAR for TS Changes to Spent Fuel Storage and New Fuel Storage, 02/11/2019 E-mail from R. Guzman to S. Sinha ML18352B1832018-12-13013 December 2018 Enclosurequest for Additional Information (Letter to K. Cimorelli Request for Additional Information Regarding Susquehanna Nuclear, Llc'S Decommissioning Funding Plan Update for Susquehanna Steam Electric Station Independent Spent Fuel Stor 2024-07-31
[Table view] |
Text
DRAFT DRAFT OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE REQUEST FOR ADDITIONAL INFORMATION CHANGES TO CYBER SECUIRTY IMPLEMENTATION SCHEDULE MILESTONES 3 AND 6 PPL SUSQUEHANNA, LLC ALLEGHANY ELECTRIC COOPERATION, INC.
DOCKET NUMBERS 50
-387 AND 50
-388 SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 By letter dated April 30, 2012, 1 PPL Susquehanna, LLC (PPL) submitted a license amendment request for Susquehanna Steam Electric Station, Units 1 and 2 (SSES). The proposed amendment would make changes to the cyber security implementation schedule for milestone 3 and 6. Specifically, for milestone 3 PPL proposes to install a deterministic data diode appliance between Layers 3 and 2 instead of between Layers 3 and 4 with no change to the approved implementation date. For milestone 6, PPL proposes to implement the technical controls for critical digital assets (CDAs) by the approved implementation date, and to implement the operational and management controls for CDAs in conjunction with the full implementation of the Cyber Security Program.
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided by the licensee and has determined that the following additional information is needed in order to complete the review.
Milestone 3 of the Cyber Security Implementation Schedule implements installation of a deterministic one
-way device between lower level devices and higher level devices as described in Section 4.3, "Defense
-in-Depth Protective Strategies" of the Cyber Security Plan (CSP). In the April 30, 2012, request PPL states that (emphasis added)
"[f]or non-security critical digital assets (CDAs), the current implementation schedule and cyber security plan describe deterministic devices between Layers 3 and 4 with firewalls between Layers 1 and 2 and between Layers 2 and 3.
" PPL goes on to describe that the proposed change to the cyber defensive strategy would install a deterministic data diode appliance between Layers 2 and 3 with firewalls between the other layers.
Please explain how CDAs associated with safety, important to safety and security functions, as well as support systems and equipment which, if compromised, would adversely impact safety, important to safety and security functions will be affected by this change.
1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML12122A011