ML16015A050

From kanterella
Revision as of 16:35, 8 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Maine Yankee ISFSI - Three-Year Update to the Decommissioning Funding Plan
ML16015A050
Person / Time
Site: Maine Yankee
Issue date: 12/16/2015
From: Pizzella C M
Maine Yankee Atomic Power Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
OMY-15-053
Download: ML16015A050 (30)


Text

Maine Yankee 321 Old Ferry Road, Wiscasset, Maine 04578 December 16, 2015 OMY- 15-053 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 50-309)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Maine Yankee Atomic Power Company (Maine Yankee) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Maine Yankee ISFSI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original Maine Yankee ISFSI DFP on December 17, 2012 (Reference 1), as revised on January 8, 2013 (Reference 2). It includes adjustments to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the Maine Yankee ISFSI remains unchanged.

10 CFR 72.3 0(c) defines specific events that must be considered in the subsequent updates.Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012: 1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.2. Facility modifications that affected the ISF SI, including those that were implemented within the licensed area, were assessed for impact.3. There were no changes in authorized possession limits.4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.In addition, Maine Yankee complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 2 10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." Maine Yankee has established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the Maine Yankee ISFSI.10 CER 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning.

Enclosure 1 provides a revised DCE for the Maine Yankee ISFSI that: 1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30O(b)(2)(i);

2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii);

and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii).

In addition, the revised Maine Yankee ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination.

The revised Maine Yankee ISFSI DCE estimates the total cost to decommission the Maine Yankee ISFSI to be $27.4 million and $28.1 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.10 CFR 72.30(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the Maine Yankee ISFSI, including the key assumptions and the justification for their use.10 CFR 72.30(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility.

Maine Yankee will periodically reassess the decommissioning cost estimate in accordance with 10 CFR 72.30(c).On a periodic basis, Maine Yankee will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

Maine Yankee has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF)and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-20 12 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.Annually, Maine Yankee submits the reports required by 10 CFR 50.75(f)(2), 10 CFR 50.82(a)(8)(v) and 10 CFR 50.82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

Maine Yankee Atomic Power Company OMY- 15-053/December 16, 2015/Page 3 10 CFR 72.3 0(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination.

No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters;

4) nuclear activation of the Vertical Concrete Casks (VCCs), VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning.

Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the Maine Yankee ISFSI for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI through 2033.A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance 3. Total Costs Associated with the Maine Yankee ISFSI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 4

References:

1. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (OMY- 12-073)2. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Revised Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013 (OMY-13-003) cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager P. 1. Dostie, SNSI, State of Maine J. Hyland, State of Maine ENCLOSURE 1 TO OMY-15-053 DECOMMISSIONING STUDY OF THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation Prepared for Maine Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015 Knight Cost Engineering Services, LICKCS25-20-30Rv0 KCES 2015 -2015-300Rev.

O Table of Contents

1.0 INTRODUCTION

...............................................................................

3 2.0

SUMMARY

......................................................................................

4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH ............................

7 4.0 ASSUMPTIONS.................................................................................

8 5.0 SCHEDULE .......................................................................................

10 6.0 PROJECT MANAGEMENT

.......................................

...........................

12 61 OVERSIGHT STAFF.................................................................................

12 6.2 DECOMMISSIONING GENERAL CONTRACTOR

.............................................

13 6.3 SECURITY ............................................................................................

13

7.0 REFERENCES

...................................................................................

14 APPENDIX A............................................................................................

15 Page 2 of 15 Knight Cost Engineering Services, LLCKES25-20-30Rv0 KCES 2015- 2015-300 Rev. O 1.0 INTRODhUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Maine Yankee (MY) Independent Spent Fuel Storage Installation (ISFSI). This estimate includes only the structures, systems and land within the NRC licensed area. The MY ISFSI is located within the site boundary of the former Maine Yankee nuclear power plant in the Town of Wiscasset, Maine. The site is approximately 1200 feet north of the former plant site in an area used as a vehicle parking lot. The NAC-UMS fuel storage and transport canister system chosen by MY is licensed by the NRC for both storage and transportation.

The ISF SI consists of the storage system and concrete storage pads, a Protected Area (PA) for spent fuel storage and a Security/Operations Building for equipment and staff. The PA contains 16, 3 foot thick concrete pads, each 31 feet by 31 feet. There are 64 dry storage casks on the 16 pads, 60 for spent fuel and four for sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a two and a half-inch steel liner surrounded by 28.3 inches of reinforced concrete.Page 3 of 15 Knight Cost Engineering Services, LLCKCS21 20-30Rv0 KCES 2015 -2015-300 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination.

This estimate includes all costs incurred to release the property for unrestricted use.On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning.

The rule became effective on December 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate.

To assist in the implementation of the new rule, the NRC issued NUIREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness." NUREG-1757 does not apply to licensees under i0CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUJREG-1713.

It does provide additional information to support the development of the cost estimate.

This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG-1713.

In addition, it does take into account the guidelines identified in NUJREG-1757.

NUJREG- 1757 specifies that a contingency of 25% is to be included in the estimate.

This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated.

Second, the MY site has recently been successfully decommissioned, and the land released from the operating license, with the exception of land associated with the ISFSI and laydown area. The lessons learned from that project will be incorporated in the MY ISFSI decommissioning.

For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.30(b) was submitted on December 17, 2012, with a revision submitted on January 8, 2013. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the Maine Yankee ISFSI in December 2012: 1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.3. There were no changes in authorized possession limits.4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.Page 4 of 15 Knight Cost Engineering Services, LLC KCES 2015- 2015-300 Rev. 0 The total cost including contingency is $27.4 million, $21.6 million for radiological removal and$5.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Non-Radiological radiological Total Cost Removal $ Removal $Grand Total Building Tax on General Contractor

$27,423,524

$21,556,946

$5,866,578

$0$0$0 General Contractor with contingency Site Costs with contingency

$17,757,734

$13,958,910

$9,665,790

$7,598,036

$16,143,394

$12,689,919

$3,798,824

$2,067,754

$3,453,476 General Contractor Site Costs MY ISFSI$8,787,082

$6,907,305

$1,879,777

$24,930,477

$19,597,224

$5,333,253

$15,126,261

$1 1,890,375

$3,235,886 PERIOD DEPENDENT COSTS 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6.1.2 1.2.1 1.2.2 1.2.3 ACTIVITIES MY Site Costs Project Management Security Staff Fees Insurance Legal Property Taxes General Contractor Decommissioning General Contractor Waste Packaging Crew Equipment

& Materials$8,787,082

$4,111,355

$2,303,834

$719,678$582,818$200,000$869,397$6,339,179 S3,344,685

$1,062,680

$1,931,813

$6,907,305

$1,879,777

$565,721$458,139$157,215$683,411$4,983,070

$153,957$124,679$42,785$185,986$1,356,109

$9,804,216

$7,706,849

$2,097,367 1.3 1.3.1 1.3.2 1.4.1 1.4.2 1.4.3 Project Engineering Procedure Development and Review -Offsite Preparation of QA and Safety Documents

-Offsite (in parallel with 1.2.1)Site Mobilization and General Employee Training (GET)Site Mobilization General Employee Training Site Specific Training Site Preparation

-Performed by Staff$12,346$6,173$6,173$95,166$23,364$65,348$6,455$12,025$9,705$2,641 1.4$74,808$9,452$20,358$2,572 1.5 Page 5 of 15 Knight Cost Engineering Services, LLC KCES 2015-2015-300 Rev, O

SUMMARY

OF COSTS, continued 1.5.1 Initial site Survey 1.5.2 Setup work areas ,1.5.3 Decontamination Readiness Review 1.6 Disconnect all utilities to work areas. $6,012 $4,726 $1,286 1.6.1 Electrical

$3,006 1.6.2 Ventilation

$1,503 1.6.3 Piping $1,503 1.7 Removal inside fences $8,082,872

$7,570,361

$512,511 1.7.1 Remove compacted gravel $371,230 $371,230 1.7.2 Remove VCCs $5,464,765

$5,464,765

$0 1.7.2.1 Exterior Concrete $3,651,744

$0 $0 1.7.2.2 Steel liner $1,813,021 1.7.3 Remove Concrete Pad $2,105,596

$2,105,596 1.7.4 Remove Security Fence $63,016 $63,016'1.7.5 Remove Light Towers $7/8,265 $78,265 1.8 Removal outside fences $1,539,000

$1,539,000 1.8.1 Security/Operations Building $561,356 $561,356 1.8.2 Remove paved area inside nuisance fence $.86,508 $86,508 1.8.3 Remove nuisance fence $73,685 $73,685 1.8.4 Miscellaneous Pads $79,464 $79,464 1.8.5 Miscellaneous structures

$419,709 $419,709 1.8.6 Remove buried utilities

$153,213 $153,213 1.8.7 SOB electrical service $8,815 $8,815 1.8.8 Remove road inside licensed area $140,067 $140,067 1.8.9 Remove vehicle barriers $16,184 $16,184 Final Site Survey Structure gone -By DGC 1.9 Staff $25,000 $19,652 $5,348 1.9.1 Prepare Final Status Survey Plan 1.9.2 Soil Sampling 1.9.3 Direct Survey 1.9.4 Sampling Analysis 1.9.5 Prepare Final Status Survey Report 1.10 Orise Site Release Confirmation 1.11 Outside areas $8,712 $8,712 1.11.1 Backfill, grade and seed $8,712 $8,712 1.12 Demolition Crew Demobilization

$16,909 $13,292 $3,617 1.13 Final Project Report -Offsite $6,1]73 $4,853 $1,321 Page 6 of 15 Knight Cost Engineering Services, LLCKES21-20530R.0 KCES 2015- 2015-300 Rev. O 3.0 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate:

activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach.

Site material quantities for concrete, steel and equipment where developed from site specific drawings.

Productivity factors were applied to these quantities to determine activity durations.

Labor crews were developed and applied to the material quantities to determine labor costs and person-hours.

The activity durations were used to develop a project schedule.The level of effort costs such as equipmenit rental and the General Contractor (GC) staff were developed based on the project schedule duration.

A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that. is included in the cost estimate.Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment.

The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing.

This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination.

Clean structures will be demolished using mechanical means and disposed of at a local landfill.In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.This crew will consolidate, package and prepare containers for transportation.

The waste packaging crew is estimauted to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.Page 7 of 15 Knight Cost Engineering Services, LLCKES21-20530Rv0 KCES 2015 -2015-300 Rev. O 4.0 ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study. These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.2. Concrete volumnes were developed from plant drawings.3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Maine based on the City Cost Indexes for Bath, ME.6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.10. Transportation costs for LLW are included in the bulk disposal rate.11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.12. The following buildings are disposed of as Clean waste in local landfill.

A disposal rate of $91.80 per ton has been used in this estimate and is based on information provided in the 2015 R. S. Means Building Construction Cost Data.Compacted gravel around pads Security Fence Light Towers Security/Operations Building Paved area inside nuisance fence Page 8 of 15 Knight Cost Engineering Services, LIC ES01-21530Rv0 KCES 20!5 -2015-300 Rev. O Nuisance fence Miscellaneous Pads Miscellaneous structures Buried utilities SOB electrical service Road inside licensed area Vehicle barriers 13. All costs used in these calculations were current on September, 2015.14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.

15. It is assumed that all UMS canisters containing both spent fuel and GTCC will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $869,397 per year.17. Fees are included in the estimate at the current cost of $719,678 per year.18. Insurance costs are included in the estimate at the current cost of $582,818 per year.19. Legal costs are included in the estimate at the current cost of $200,000 per year.20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.22. The removal of the berm is not included in the estimate.23. No subsurface material is assumed to require remediation regarding radionuclides.

This assumption is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the 1SF SI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters;

4) nuclear activation of the VCCs, VCCs liners, and ISFSI pad are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface material occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent Page 9 of 15 IKnight Cost Engineering Services, LLC KE 05 0530Rv KCES 2015-2015-300 Rev. O 5.0 SCHEDULE A scenario-specific schedule has been developed for estimate.Activity durations were determined based on the unit cost factor approach.

Plant material inventory quantities were developed from site specific material.

Unit rates for cost, man hours and schedule hours were applied to the material quantities.

From this calculation the removal or decontamination cost, total man hours and total schedule hours were detei'mined for an activity.The schedule hours are then entered into the schedule to determine project duration.

Two work crews are assumed for the concrete pad and concrete overpacks.

All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 17.97 months.Figure 5-1 provides the detailed decommissioning schedule.Page 10 of 15 Knight Cost Eri[ineering Services, LLC KCES 2015- 2015-300 Rev. 0 Figure 5-1 Project Schedule 2-i- a5*8 Eus0'am ay 6 r a m day 1$. 1114 We.* 1Wa4.3 INgig, S Devesaaaladbvew-Otedays Thu' 1/11114 Wed

  • Sb elseds.TtW de1r ThjIl6114 WTu 11131/14--n-dlaiPpi~ay eedraud6 8S 4ays The 111411 Mn 111611 Sitell DydITdelgI dayl Woe 112114 The 1111114 t1C Wb oes Idap Ff1d22/14 flu 1/N4/I4"- at--" s b'mewt 1 da Mera 1/27114 655 1117)14 jj beilt81 8 t we/iitma.lS aye Tim 1/2N14 Wed 1/3144 14 11I da. 1iae 1114S Tee 1111 I Vee n:.8 dais P Wed1261 Wed 11111 beedledd be m 58/ ayeS Tlsi 1/'114 Pt 4r/411W* blU ell~n 60Tday" TIs'Wi 261 'Wed 6/1--Stedm, 14,1.U days flwh/23/4 Pit 116/4 21 aeee slaPd llu 48.1$ dais I 741/714 Man 216/14 IRemsee Sbslylala 16.3d ra 7I days Tis 3I/II/j4 Fit 3t148Gemeeedw lays Tee s w/11 Pt 111*U1561IUO N21t,7 aeys P14111 Tue M~ 6/13/1 0MflatUm C FadWne 64 bcye Tne6/3/4 s we 6/7/1 air i use .yi rev i r.u Si -, II __l_I I ml I , I *IIII I St ::::::-::::::::*.*-~**-*~**~-'**'~-.*.*.-.-.*.-.-..

IIw::::::::::::::::

1l:1 Page 11 of 15 Knight Cost Engineering Services, LLCKES21 20-30Rv0 KCES 2015 -2015-300 Rev. O 6.0 PROJECT MANAGEMENT There are three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security.

The person levels for each are identified below.6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning.

In addition, the staff is augmented with one final status survey resource and one licensing person to assist mn the decommissioning.

The staff will provide DGC oversight as well as maintain license compliance.

Table 6-1 provides a summary of this staff.TABLE 6-1 OVERSIGHT STAFF Staff Number President 1 Cask Relicensing Project Manager1 Workers Concerns Manager 1 Director of Operations I ISFSI Manager 1 ISFSI QA Manager 1 ISFSI RPM I ISFSI Operations Specialist 1 ISFSI Administrator 1 Licensing Specialist 1 FSS Manager 1 ISFSI Technical Specialist1 Assistant Director of Operations 1 Program Manager I Program Manager 1 Program Manager 1 Public/Government Affairs 1 Regulatory Affairs 1 General Counsel1 Licensing EngineerI VP CFO & Treasurer Business Administrator 1 Accounting Manager I Sr. Accountant 1 Sr. Accountant 1 Benefits 1*IT Services 1 Security Manager1 28'Page 12 of 15 Knight Cost Engineering Services,.

LLC KE 05 0Rv KCES 2015-2015-300 Rev. O 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews., schedule work and supply HP support. The DOGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a Summary of the DGC staff.TABLE 6-2 DGC STAFF 2015 Base Man Position Salary. Level Project Superintendent

$200,000 1.00 QA Auditor/Inspector

$64,000 1.00 Health & Safety Supervisor

$89,205 1.00 Packaging/Shipping Specialist

$66,522 1.00 Cost Control Accountant

$65,071 1.00 Scheduler II $65,000 1.00 Demolition Specialist

$56,000 1.00 industrial Safety $67,000 1.00 Engineering Supervisor

$113,000 1.00 Project Supervisor

$81,000 1.00 Decontamination Tech $35,000 2.00 Instrumentation Tech $42,248 1.00 Tool Crib Attendant

$33,976 1.00 14.00 6.3 SECURITY Once spent fuel and G3TCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. .While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15 Knight Cost Engineering Services, LLCKCS01 21530Rv0 KCES 2015 -2015-300 Rev. 0 7.0 REFER]ENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.2. Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors" 3. NUREG-1713, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors" 4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness" 5. 10CFR 72.30, Financial Assurance and Recordikeeping for Decommissioning
6. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012.7. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013.Page 14 of 15 Knight Cost Engineering Services, LICKES21-20-30Rv0 KCES 2015 -2015-300 Rev. O APPENDIX A Page 15 of 15 iii i. 5 55 i' SI. (55 S S i55ta~i.5lli a-.-5-~l arm--a-ll i+i almios tarn.. tiiw iairnn oa ma. mm.m um~ 5am simmml -Ws lu0ls 11 la saUs UsaOW Usas4* unsta aSjamisa wliiis 7. 13 -ii.iiim.taul Minis Imum. ill LW&5 II NIiii m.Tila-irn-a-l~l~a-~i-i lml mns 41 -1 eta.is Dma.~W (5.5W CM 5W. Ma inn mm lasH. Haul 1114.3 i win mm urns ma? sum iU urn mm u.s mm 2,1mm 'a ma mm testis usia 5Mm in sum sam tans muss a.tnu us urn mm wins u.N. 271mm Ia urn mm u.s mm &itam in arm mm turns Hams 11143 iM isa mm tans stUns 2It4 in sun m iu.ns ass. ,,tti.u in urn mm inns mis. tiitm Ia mm mm wins sum 3.tlmm its awn mm wins SliMe 21,455 its urn mm u.s mu 211455 in urn mm ia.s ma. suisa in.it..a mm mas sutn s.iwm in inst mm wins .iu~aa 21169 in an mu aim us. s.nem in win mm tans pins &itsu in ms mm urns urSa suimm in mats mm tens stunt sum in at? mm u.s arm s.,tim in mm mm urns aria ..tieu in u.n mm wins asa aiim. an wi.ii mm wins slim ~ii4u in tim.?. mm tans mm. atisa in awn mm tans s. sitmm us u.s mm usui similE itiss in.mnim. am.. urn nun Its, -ama sa 5WW* 77.3 u4 is mw is isus'aI. Ua5W CM is mn ties tans simat? Unsti use tin wins maui tistis-a-i-a n.os an utah. ira ans ilitia ,~a.n ii,. u.s asii Sian its. hiSs iii.m mu. tnt ass a.iu.uan tim gas wine ursa tiut urns a.ni it u25SU4 UisU iii p..iiA Itat iii Pisittis litaisil tewi'mlisn --ama --auwits --in -in -in -am-- is a-ill H.-~i -~i.il ii,.41s.ts isa -~t mua ,'alrni aiim mUll maw mans ia..ta Sittlil am saYs. aa.m maw main am neens iins.m SW.I ii 5. a-Ma W.hta is isis smut am.u uumis Hielas us.Pan item tans am z.iam mita 1.3555 am am aim mu tees mum mm stint. stem tans Hata ama aiim stem tans itata hum ma aim tans mis. han aiim trim aims ma.. as...SiA win uns 1mm 1.3i55 UhI aim tani siam. 5s.w alit aim tans StiLe ,asm aim iim.u inns itiuuli hum mesa nan is-ala ~16. tilt mm--

5 5744 m m ~m 45*4 253 4 25.7i1inJ 33*15 1.3. 5-ima Ii.) 1454 Mi-be-tm-.

  • 4-4,,v twu, idp.4.ma Wma-]mlmee.--4hmem.---5.3 143 55 3 SN 34.1U U 3 f3331 amw a 33 31 Smo N 33 33su-mm at v sumN GWI-0a45m 45-4 acI-a ! e 44- Wm 4..0*4 -=J4 45 IA 4- 337*4..av S -~m Sm -I 012 3ee U4N 1.44 34004 0551 34 4534 I 531 5U83 34 5157 I aa3 345JI em tw .am 5*5.13 15 33 I 5333 3 Is .m tim 31254 334 N 1 525.5 3*64 314 mm 511*53 u ma.. slams, 31.45-15 5525* 55. 34 13.7 Pm ~ N -a t i 4 sla 115.33 33 30 33m1 Otaa. 1 33*64$1447*~ .4215 rn~5 36 3 s4 a m 34 a-tWa mm 5 4 11133 33 i4 am 33 ails i,.4 30 133 44 a-adS 1.33 $143 5 Sm am 33 14 ala 33 a¶vs m 5*6 12 25 34 331 o S 2911 0 4 3453 52543 16.5* N N 516* 521i4 37714 43 ISAIS aim?122 51414555.334513N151i11 44 4451 44beNSS I IA 455551eTS455t5*1 14.1 mm'ails aIls 514 mmSt~sam p.m.05 5,444-55 1 5~a r44344~* 515544554-I 04054.44-5 I ~I 04.444555 I -* ~3 4-55145 I 51517.4.I 1adIs4-3 4455 7 L*3 F~S 3 4-33*515-k..45ee44-440544454.5 I-'--142 a Itkls C-I 444-44 I Mka.4...a, I 51253.5534-15.45 C-Me 54 0544355555 as wu~~as pese444-as sea-m as 55adsg~as sa-as ssas~a-.55 wesia-~.g as sa44a-~uam as eta-45a-s as 1545,444-3445 as ~as sasoam 35.4 55453 45.5 564 45.34 51154 sau sias'-4 3 51 4 Se 33 Se u 3 15125.33 33 3454 M4 F-4-44.5O 44.14. 04545 as as 05~44C-am..s as as wsa-.s.asu as as 44a-5545 mm mja

~22~1 2342*3~7 282322*~3M2222We 7~2-1 I3M3M23~2.

'3M.-2 ~¶ ~¶ 128 2332We 2 223We 1 7.*M 2 3232 21 3M 3M 3M 3Mo~3M 3M 3Ma 3M 3M 3M 214.2824 d 4.3. 3.34 2~ 3332 2824 0-- -WA ------Ossa LEAVe -We -4824MM MUMU 282We ~V3M 82323282 1MMA~ 2~43 -~ ~ £~ L~ 4.3 4.3 33 4.3 33 3UF3Mm~23 223 143 We2.3M3MM 3M 33p3M4~3.aM ~3M 3.We2~3M 3M 3.2343333232 3M W314i28I~223 33 W343.~i3.23 3M Wm328We434 3M 3822.42833.343.

2742M 42342 333 3.3 3.272 21*8.~2 223.7*2 We.8.232 p17341*233*~. --IA) 231238272382 We We-*52~223 7 22834. We34 23338.422 7 32322 7 ~We 2W~I3.28.7 73332sh 2 ~3M..123 7 23123 123233233 I 33321 I 743.2 ~2 21 3MW 13. 73. 73.-- -----17 23323 2332 flU 2? 3533 2253 4 2223w 213 22 24M 3323 2737 7 737273 223 27 23*223 2323 24.13 32 3M 3 6 2ft323 542312 217.32 4 73 542 233 3.531 2353, 3M 3M 33223Ao*~3M 3.33333123.3.3.

3M 3.3 W3We~3M 3M 3M 33 33323428.3.

3M 3M 333333288.38.

3M 3M w*33~We 3M 33 3332833343.

3M 3M 3333213.233.

3M 3M 333332333.

3M 3M 33332123.323 3M 3M 332.34213234223 3M 213 33 2.34323.3.3.

3M 3M 333333343.

2243 2233-um 3234 21.a..5322 2733-u 6 MM 73 213 23 743 73 33 353 3,23 272.35 213 34 37 2MM8823., 1227.71.2J 823343.1.2Z 32327.#23* ,3 73O 430 28* 23 23 43 24 334.,. 4334 i 34I 4,e 3tlS WeIl 334 0 3211 2*732 33 7 3 3*1 213 273* 3 17137 2421 3 3 3.3 235 3 27 3m 22.3 215 22.73 27*3* 4 24444 2 3*3'U 2232.32 372*21 32 M~ 73 3.72 247228332733.122 3)2 2 2 2 2 22 27.43,222 24428.32 3 3 232.427 24.72232 3 33432 3 313)4423-3321 ~3L ft 33224 33 33.4. Sm 24 31223 71333 332 723.3 233--We 223.54 33 *233.8...

22 7332 MUAI 143.2 33 23 23 23 3M 3M 33 223 73.323 731223 3218. 213mM 3M 3532323 21122)223 77.22 38.232 A 2.32 73 3.21 72*27 322*7 7*2.32.2 43238 23 22.327 738. 43.22.1 V.3..3fl 2138.7.22 237 232243.8.

33 0.38234 3334 24 24*22 23222 2.3 4253 832*2 3.3 3.3 33 22282 33.3 7223. 332332 22 2 733.2 32~2 743.2 MU 23 23 33 3M 33 3M~ 8 2533242 2,2273 3M 23.323 22.3 223*33 2222.343 27J 73 2323 3237233.324347 G.3~32.4~3.

Th8.328.542343823473537454138.322.21333..

aM ~3U2 63 73.2 32737 232.32 3 27*1531 227 733.57 723233.3 3.3 77) 23222 33222 Pd A 73 73 733 2.23 3.2.3 2333 33 #3 33 3.2.32. .27.ft 222222.18.

We flat 3.23 332 23 23 3233 232323 .331 42 233 3M 3~3.7.3 733 333.333.2124 23227 2732.32II 3 2173122 24.73,23 73 733 7543113333327 71333.3.,.37 177227..8.3..23..24.273747242.21*8.*2A2322*2322282*2 133 Usa mm 464 -lmm1. -lUsa --- -LOAWS. d... 2*4 -V -VS. -LSA. ---12.4 ~i~A Wam l~

  • Us64 Y~ Y~M lmm*4 ~ ILmm64 1.~ 1*4Us Ca. Us Us lb W.~24 V*4l. 5*.d~ C*412 Tammi Usm5 1445 ~0Us am ma. 48 515 d1 U lam 365 mm as.aja..m a.,.,. nn I14amm Urn junam. ua.inis I.7A Us.a.3~I14U A In In IOU 164 56 1.0U 16.16 15 52 Us.m4a. ad l~ I.1. MV.1 ~54ft 3141.114 Usm.1. Us Oil 3551% 21n.1s.Us a~5 ~a 116 16014 USA1a Lam W a.. P~a.. mm 134 am 146n lb 13 INasn ,m 13 am ,,,.015 m. 1 0 4 5.m n.m UISA.aml.,.0llamlU US 6* 56mm us urn U Oem mmtm mm 3E ~.l ImmOiS ~6I 1445 ma. lUam .3 6* 26154 MMMI 15*157 am am am am am 115 UsL.UsT A Us im 3665 13. 56 46*4 46'1.6.. 6444. ~ ~'1R *56455 am ~1. 5165 mm 53~mm S 1215 311 am. 3I1 am OS LOUs mm bamedd*4 lao. sam ma .~U.am 15.134 565 13. ~1464 mm Usmm a 654 5.655 U A 215 53 mm T a 6 015126 061. 16 1 tin 53 mm 01am3'in U UsM 54.16* am 1* I 16 mm mm ~ 14 Usd1 224am am 114 I 501 3a.mm a.,, 5131 U 14, 115 am U~446L22U5*5l22 16 41.8 151.053U 22312616 Im 2,6 52146*65.01 a3314 IM 146 14 446 in am 56mm In 106 564*4 ma 5 ISOZI s a a.amsa.me mm~am mm.. mm.. ~ ~mm.s ~mma mm~s rams mm a.~ am 5166 mu mu am am am am am am A 1514 .m m 0.45 I. mm.aa52.53 U II6 U 65 U Il554 5i5 aIm U 161* IlIA, 5356~5-..mm mm..am mm mm.3~amm mm mma.mm~mm amamamins 16 13 W 5.124 am 114mm ad 3*4 2*6.1 ~.ft 14.In mm mm.a..& Sm a am am Cm sin 1mm spa.71056 1.aas15sU .sau. .u am am ~d64 566 ..inam.rn .US 11656 arm am ~wam¶ 4U2m6 22610 165546 11(14 UOSII .604 IWU 314 55, am U13SmUU.U4MM216 I 853 4241512Us.sa.2241 113Me1.a.*4.

fraamam.am.,Wa..a..mm5m.a..m.,mbl.2*4e~.14*4.1.

1 1~31 *4aa2U.....meU 11*UA.a..Us 1mUs515.ama..am.3..53515Usk3I..*Usmm44~

16 2612 3512Sm.m3U41 14.1)0122.

mm mm.. mao a. Va.*4.. 03645 I)m.14l a.Sma 10(5 a. 1Jan16 236516*5 211.35 am a641J1 amJaa.3a aW*l40 am am am am am am am.5.2 ma.56smm a 54 lm EN Us am 365*. 46 11am- ...ms Us.in~A 14am.u. mm mm.a.t mm mm mmm 616 044 amIss .a.m. ImAs 20* Us 03*..inn mm Smab. mail. a.Eain C.0 114Sma 61443 7445 ma ,wm.in ma am am mu miMn maw am am am am mm am am I*~ Oe53 5 16 16 15151 13. am agOem. amm, a mm... l56a. L~1. 446.4. 11441.14.

~ mm mm...t mm mm mm am mm am talam Irn 44 mm ma. mm lao 0d1 5.45 U 5 am mm mm PIn ISo 31(0 54656 046 222 III Cm mm 1648 am me mm~ 2*o a.6 013.2 1mm; a..ga rams mm mu n.m am am 18 24163 mm~a au am am am am am am 15.4 *4~ftb 5 14 1.U 1454 Us am 4145-. Id ma mm 44a+/- mm~ mmiA. mm mmla.a. mm mm 53*464 &mm mm.. .6.16 2mm am am ~am mm mm. mu 6* .me 5126 IU am a...4in~mm mamma in. ,,am mm. mm am am ..4am 6146 am me ~ am 36. a.mma ramIla mama maLi Us' WOIWn 1.5146 mm am 11151.3 a.m ,s..lm.u mmoam am am am am am am am.u ~ 5 Us lm 22122 144 am~.,ammmlm.65U1a 35-. 56 mm ma siam.. t agm.~ft mama 424 mm amlS.L mm mm 535, am 3am lImos an n.am sam.mm 5-am. Us 265 456am .6*6 65 liP 36 ~1464.mm ~mm am am. mm as. 61465 ~3.mm a43 ~am 156' 6 L.a. SlUm en mm mmmm Us uW am mm am am ..mm 5-mmmm.. 165 IM5W am inn am 346 6160 mm 5-amm. UDU LinuS 4am m.56 V.6 Us ~6am mm mm~mm 6*1 3 am mrn en mm ~bnmamm 4am 2.64 16mm rnn'A UUd1 Sm n. 6.0am 4d5 1015 mm i mm'I, ino ,tJm sam**16 71 4.6 ma 1616 U 64121 114 55..I 7151 J..UOSma.65.U1 U8m.Uc4.a.,3.

13m5h..ama.Sm.l1.0*4a.24Us14562*Usmmamam I 3M 2*U4Imma.U6.U41 11356U.a.a.4'1 amUs0m..am~mmmmmm.m3b56amUsmm1464.

I 1* lbUUSmasftUsl 123 d2122.,..s*..

l4*Us0b444d.mm~5356mmUsfr*42*445-ammst mm a.722 1411.222 16 36 UUSma.21.641 14.12146.I am l3Ustmmmd1.U41 1236'U,,a..*..

UsUsk1..ams.mmI2*a.444...44.a.s..mbUs.sa64lmm424.mm..

in am UUSmUU.64 l1.13Ua1.16 am 621mm. 30411.120101.

am lame.I 122.3 25U16mm107111.IVIU, In 2233 UIlUsUamSa22l1.152m 16 lISa UU14a.3U41 1511010 I flU 3SUmU.U~I Wmad1c...in.raa..

1Us446am1...SbW.514415.&

mm am 215445. mm 36mm. ~1a ~a.s.5 mmV.a 1440 65 *.mamas amom 13112 am laliaM Um6'l) 1613.14 am am am am am am am ISa mm...... dO.. 5 26 151 26*1 1.140 am ama 356' Id mm... 064 14. 44.51 1644.414.

Sm4. 124 mm ~5~1. p..p mm 5-a64ssa*4, am am am Us s~1.Ms 16 2213 313mSm)1 22 322am mm aao-.m.ma am iso U155 2mm 3.3 .4 11456 16 244.4 22135.5. .am22U4.14316 5444.322 a.01.113 1122312 amm tea amamama a ama.~. a am meisaise.~

am~amam a--Se.5is *5 LiAise -_ a.~a- am LU. ama .m am sim us. am an am a ui am am 517 5 a am am s.ai a 5A54 tArn am 1ZS 4 am. -am in a ama sam t.t am em asia saw as. am 4.4 SM.5 ~ t.d *441 is~ Se. a- 2Sii~ n.m Se. ----c ,..we we we we it..amfl Vdt.5 Tame. ame. LamM ydu..M .~

  • Ta CaE tad.~it w55 e.s41 S issama in ii, aim in us ammamita*ittu.

Lam itO m.m ma,.eg..alsamamnin Lam in intL.a.urniwits is.im Sm 58 arnams. Uft14UM am in am amam am in us am in am at,'U in am am.. am amam. ., is ama.a va.a a- am UP 4.4 MM ist17~ Wb 3mm am a. am MM mm MM MM iA7 Imamama-e La l aIa am SM Ue etVkl e.,WlR&r am gw L Llama am1eo Ifl sew us U ftp am itO 38 m*rnamm Ui5i54 SM La- itO iU Uit.a.UU&istlSM 3m 18 GM MisiM~IiU3i4 U-MIII U an -ut amamam am.am is~a. e.~ Md-. a-a. Tg.) ~5 ~t a- 4M 5W LuG MM Ig.7i SIMM Ugt4 a-am am am am MM MM MM MM a a in MN a wiam. am..am sews.. MM4.g weaa wesseft am V~wet am ti7aa MMO 141345 .34g. IMMU-MN am U'am sin MN MM ftP iN US? SMTwaMesisuM i3.iTI Ut?mi. w aiUtua SiM aI a.,ma we.a-a--as am.ame.am.

a-Ca am a-a-a-a-U-a-a-weIIam a-sm.a-ait MUam am... a- ,a~am.e a-wi am..., am.. ra.)reaM g.e gas Siam.,. Ms.u.4 .saain am an MM tam mm MM a N IM USS Ut vga- am. sE tam. Am.g.I ve.a. ft mama am e..gwet e LI. SimM Mu. MN Lit ita simm -a.. an an u.n mm. use an OASiS 05g. Gig iii am 3am mm. me ssi a m em. letS lit is' Nm. mm am a it am. am am tiaSi il.USI. IGaSa IASM NI sun am am am sun in a-.. itim ~E amiss Ts.I US.t Ta.)41MM ami in tan sauw 1)91* Mmii em am GM MM Urn MM MM u.n in item ma ma uw.tit am ..3m MM isEim am se am sa am ii asistam in ta Ii -~Mn weams am bis 116455 pJ i ii) e.mUa-u.ggsi IIIS.I.asi.e.a.

lis.aa55esMmammewaiam....55amam..a..ie.am.ama.

I tit 4~mt2S.ese.g.U4i g.Um.a.is...a~

tgsis41.minamaiam...a.e.amams.am.amam in am g in am ama SM W.Mi2am..mU41 ttn~M.is..u~.

ThSaGM.Mewa.u.iam.u.hewa.igteemamw..am.mewam in SAC s~in~ins.in in am U iam in aatIam..Uusi la4aamm,, ewa. T*a5.nea-eU-.m.amammamewsamvgame.ams..saa.

in am am we we Tae.a-u.I...in...bGeCa u.S a-am a-a.a.05.iii ..eam S5l tat a-a41e..Sat a-RE a-a-a-a-.. amm mm'is amIMa-~igamue...hadaa ii iit.5 .44we4.u am we 5s'ai Siam g awam* am. a -* am- .is..is e. 24 5s us am- a "is it am. si a.a isa-a U ewam- 535mm$ am I am-I.amltm a ktl vlsl iS A 5it~ Sm is@8 a am an am a am am am mm A 54N iM isism a gin tEb~. tam *EU..iS am we amg.a am.s.a am a-suet am NP aim am em SM lat seMise. SM lit aainwe.siuas.,sw aim ama am am am isg.fra ItO U IMweainU S.5)S an am ltD m U w u a g.m g.m am ag.g.a 5W MiMg.W a-4.55V amw...it.

G~a. sil Ta.5 saweesam 5551mn tam en mmn N5iMa-Mmi4Stam a-a sam ass anma-nmu.stin.smaai uazeia is it a 11613 aiIm nmi I amawama..I eweamew S samaa-a-a amaamseam I GitO....5 si am.I ama-I ama-I bia5sa-am I a-a.a-S ~5mis3isThM am.aisU c~a MI. ama-am....

MM amam~a-.a son ama-am....

UI. a-a-a-am.a MN amama-ame.m MM ama-a-ama..

MM ama-tame....

MM simawia-.....

MM ama-a-ge..

MM ama-a-am.lam ama-a-gm IWIdO1w¶ dI 2~*m I 7 LJ 1 ~m Sm m* m*6 116 1124514 IC

  • I~16 84453 ~A 316 *16 316 S S.* 36 2*13% ft~ C 3%~2 6144* 3 ¶16 *145 3 S 11316 14 116 3.13 3 I 6*1646 3 *16 14.13 3 4 3 34*3 3 3471 16*12 *443 1*461 ENCLOSURE 2 TO OMY-15-053 CERTIFICATION OF FINANCIAL ASSURANCE CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee: Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 72-30)321 Old Ferry Road Wiscasset, ME 04578-4922 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Maine Yankee Atomic Power Company is the licensee for the Maine Yankee Independent Spent Fuel Storage Installation (Maine Yankee ISFSI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the Maine Yankee ISFSI.During the operation of this ISFSI, spent nuclear fuel and Greater than Class C waste will be stored at the Maine Yankee 1SF SI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated casks will ultimately be removed from the ISFSI location, and Maine Yankee will dispose of other radiological waste in accordance with NRC regulations, at which time the Maine Yankee ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund Maine Yankee ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in Enclosure 1 to the letter to which this Certification is attached.That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of: Maine Yankee ISFSI $21.6 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella Maine Yankee Atomic Pd rer Company -Vice President, Chief Financial Officer, and Treasurer

-, Phone (860) 267-6426 x304 Corporate Seal Date \

ENCLOSURE 3 TO OMY-15-053 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRADIATED FUEL AND GTCC WASTE Maine Yankee 12222015 2013130? Budget Maine Yankee Atonio PeoenrComanry Spent Feel Managennnt and ISF21 Dnem Estimate-OEC~sanmeal Sumof62060 Sumaf2all Somal201 Sumneoele¶ Bumne2020 SanneOOOI2 5umof202~2 Suofoe2022 S~oaeel02 5wna62025 5umno62226 Suno62027 Sumnol202a 9ame12029 Sumoe62010 S~onnelO t smonteta3a aunnaof20 SrnetTalteale20132e.abat.-Sn-Manual latlrniab Supple.3o22d* Serreos- Fuel Leedina)22aso Saraos -ISF510CPa>226ad aauoans- 222-RAiD 252 atl1FSl Dupaaa Saeraica -29 P6D DaloISFSl logulalary Fe,.522,216$1,943,522

$2.750.762

$105,0473 Ila,274$-$-$225,275$612.452 $et5.5sa $ 455.3701 4220947 $ 474,522 55.O200 $ 522,2106 5022216 0 505.21$6.203,205

$ 1.243,20 $ 1.043.922 1,203.922 3.225.704

$ 3.225.724 3 .025.704 $32025,784 52,125 $ 22,025 $ 92,125 $ 162,247 113.207 $ 113.074 5 113.274 $ 113.074 552.223 $ 552,9223 522.223 $ 552,223-$ -.$3.932.235 5 7322282 725.203 $ n4.590 305.272 $ 219,2728 7534823 5 424,621-3 -$- $ --$ -$ 6 1,.0229$22 1,022,2229 0,222.2229 1.0802222 225.275 $ 225.275 2 25.275 5 825,975 018.452 2 112,4258 118.452 112,452$ 4L55.270 2 452,271 $ 455.270 3 455,371 0 425.754 2 455,371 $ 455,371 $ 452,271 $ 4552371 $ 422.232 0 1,52487e2 0 522,216 2 502,202 $ 5220,21 2 022.216 2 520,202 5052,216 5 54,219 $ 522.216 $ 532,216 $ 592,219 $ 222016$$ 1,843,906 0 1,823.922

$

2 1.043.922 5 1.543.922 1,243,326

$1,943.902

$ 1,843,922

$ 1.943,222

$10.43.222

$ 1.23.92,36$

3 22,1225 92.025 $ 92[2,12 92,122 $ 92,125 5 0,125 $ 2,0225 92.125 $ 22,025 5 2,122 $ 92.0225 9 052,223 2 5029,2 $ 5523238 0 5529,93 0 52522 $ 552,523 529,923 $ 2359293 $ 5529,223 052,222 2 205,076 2 205,272 2052372 215,372 0 0.0323.04

$ 215,372 205,272 210,272 215.279 424,221 0 723,8230........$ $ -" $ " $ " $ ...6,212,2..3 $ -$- 2 -$ -$ -$ .0 -$ -$727.522$14.el,.32o

$ 1.040229 $ 1.0802.32

$ 1.0222250,2,229$2 0,022,229

$ 0.9222229$

0.022229 $ 0.002.222

$ 0.020.229

$ 1.222291,80229 0 1.08022,229 O Ilo45 112,452 $ 118,4,58 116,452 012.402 019.452 108,4528 112,452 112,452 011.4528 161.5342 231,929 277.923$52,12352 241.525$90,727$9292068$226,22$9,126.822 1.,02.,376 722301,25 2,1092.470 17,5222221 6,14.2352, 1.921225e OrancdTotal

$ 12761494 $ 12606G720 8 91622223 61220992282

$ 91992492 $ 8i522263 $ etE62r78 $ 69r22780 $ $ laal10e8n 6 95622760 $ e912172e 0 29626278 $ 892.21700

$ 9242i6 $ 22202337a 32$2i316010

$ 0 946123 0 ieeoo26uae Noba 6: 75 et et managae~nt af Irtdiulod fust and GTOC Costes clonnatad as tosaa:$ 004.722,222 Grand TotalfSomajbooo

$ (9.013.2021 Naon-Rd 0&D ISF51 L.25571Rod 022 ISF51$671,217,616 Managesrnantallradluled Fuel 2722 Waste Noloa2: Th~olestofRAD and NsN.RAD 56BoftherSFSlpn201adlodaas auproidedpod haealunes labalad "Sumaot2203Pand"Sunlot2203T"Isaeorved by esaaua~ng tvalUe espn~osrodsd n E~ondor 027y2.5%.N90o 3: Ti~s Saronon C32rles MOYe 2013 Approaod 0365 Role Case rai tha Knight Cost Enginoeelng Seslos 2215 RAG end NO2N-Rud 0S700 Doam Cost Eusnoate Maine Yankee 321 Old Ferry Road, Wiscasset, Maine 04578 December 16, 2015 OMY- 15-053 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 50-309)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Maine Yankee Atomic Power Company (Maine Yankee) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Maine Yankee ISFSI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original Maine Yankee ISFSI DFP on December 17, 2012 (Reference 1), as revised on January 8, 2013 (Reference 2). It includes adjustments to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the Maine Yankee ISFSI remains unchanged.

10 CFR 72.3 0(c) defines specific events that must be considered in the subsequent updates.Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012: 1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.2. Facility modifications that affected the ISF SI, including those that were implemented within the licensed area, were assessed for impact.3. There were no changes in authorized possession limits.4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.In addition, Maine Yankee complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 2 10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." Maine Yankee has established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the Maine Yankee ISFSI.10 CER 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning.

Enclosure 1 provides a revised DCE for the Maine Yankee ISFSI that: 1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30O(b)(2)(i);

2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii);

and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii).

In addition, the revised Maine Yankee ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination.

The revised Maine Yankee ISFSI DCE estimates the total cost to decommission the Maine Yankee ISFSI to be $27.4 million and $28.1 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.10 CFR 72.30(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the Maine Yankee ISFSI, including the key assumptions and the justification for their use.10 CFR 72.30(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility.

Maine Yankee will periodically reassess the decommissioning cost estimate in accordance with 10 CFR 72.30(c).On a periodic basis, Maine Yankee will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

Maine Yankee has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF)and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-20 12 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.Annually, Maine Yankee submits the reports required by 10 CFR 50.75(f)(2), 10 CFR 50.82(a)(8)(v) and 10 CFR 50.82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

Maine Yankee Atomic Power Company OMY- 15-053/December 16, 2015/Page 3 10 CFR 72.3 0(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination.

No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters;

4) nuclear activation of the Vertical Concrete Casks (VCCs), VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning.

Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the Maine Yankee ISFSI for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI through 2033.A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance 3. Total Costs Associated with the Maine Yankee ISFSI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 4

References:

1. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (OMY- 12-073)2. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Revised Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013 (OMY-13-003) cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager P. 1. Dostie, SNSI, State of Maine J. Hyland, State of Maine ENCLOSURE 1 TO OMY-15-053 DECOMMISSIONING STUDY OF THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation Prepared for Maine Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015 Knight Cost Engineering Services, LICKCS25-20-30Rv0 KCES 2015 -2015-300Rev.

O Table of Contents

1.0 INTRODUCTION

...............................................................................

3 2.0

SUMMARY

......................................................................................

4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH ............................

7 4.0 ASSUMPTIONS.................................................................................

8 5.0 SCHEDULE .......................................................................................

10 6.0 PROJECT MANAGEMENT

.......................................

...........................

12 61 OVERSIGHT STAFF.................................................................................

12 6.2 DECOMMISSIONING GENERAL CONTRACTOR

.............................................

13 6.3 SECURITY ............................................................................................

13

7.0 REFERENCES

...................................................................................

14 APPENDIX A............................................................................................

15 Page 2 of 15 Knight Cost Engineering Services, LLCKES25-20-30Rv0 KCES 2015- 2015-300 Rev. O 1.0 INTRODhUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Maine Yankee (MY) Independent Spent Fuel Storage Installation (ISFSI). This estimate includes only the structures, systems and land within the NRC licensed area. The MY ISFSI is located within the site boundary of the former Maine Yankee nuclear power plant in the Town of Wiscasset, Maine. The site is approximately 1200 feet north of the former plant site in an area used as a vehicle parking lot. The NAC-UMS fuel storage and transport canister system chosen by MY is licensed by the NRC for both storage and transportation.

The ISF SI consists of the storage system and concrete storage pads, a Protected Area (PA) for spent fuel storage and a Security/Operations Building for equipment and staff. The PA contains 16, 3 foot thick concrete pads, each 31 feet by 31 feet. There are 64 dry storage casks on the 16 pads, 60 for spent fuel and four for sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a two and a half-inch steel liner surrounded by 28.3 inches of reinforced concrete.Page 3 of 15 Knight Cost Engineering Services, LLCKCS21 20-30Rv0 KCES 2015 -2015-300 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination.

This estimate includes all costs incurred to release the property for unrestricted use.On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning.

The rule became effective on December 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate.

To assist in the implementation of the new rule, the NRC issued NUIREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness." NUREG-1757 does not apply to licensees under i0CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUJREG-1713.

It does provide additional information to support the development of the cost estimate.

This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG-1713.

In addition, it does take into account the guidelines identified in NUJREG-1757.

NUJREG- 1757 specifies that a contingency of 25% is to be included in the estimate.

This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated.

Second, the MY site has recently been successfully decommissioned, and the land released from the operating license, with the exception of land associated with the ISFSI and laydown area. The lessons learned from that project will be incorporated in the MY ISFSI decommissioning.

For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.30(b) was submitted on December 17, 2012, with a revision submitted on January 8, 2013. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the Maine Yankee ISFSI in December 2012: 1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.3. There were no changes in authorized possession limits.4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.Page 4 of 15 Knight Cost Engineering Services, LLC KCES 2015- 2015-300 Rev. 0 The total cost including contingency is $27.4 million, $21.6 million for radiological removal and$5.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Non-Radiological radiological Total Cost Removal $ Removal $Grand Total Building Tax on General Contractor

$27,423,524

$21,556,946

$5,866,578

$0$0$0 General Contractor with contingency Site Costs with contingency

$17,757,734

$13,958,910

$9,665,790

$7,598,036

$16,143,394

$12,689,919

$3,798,824

$2,067,754

$3,453,476 General Contractor Site Costs MY ISFSI$8,787,082

$6,907,305

$1,879,777

$24,930,477

$19,597,224

$5,333,253

$15,126,261

$1 1,890,375

$3,235,886 PERIOD DEPENDENT COSTS 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6.1.2 1.2.1 1.2.2 1.2.3 ACTIVITIES MY Site Costs Project Management Security Staff Fees Insurance Legal Property Taxes General Contractor Decommissioning General Contractor Waste Packaging Crew Equipment

& Materials$8,787,082

$4,111,355

$2,303,834

$719,678$582,818$200,000$869,397$6,339,179 S3,344,685

$1,062,680

$1,931,813

$6,907,305

$1,879,777

$565,721$458,139$157,215$683,411$4,983,070

$153,957$124,679$42,785$185,986$1,356,109

$9,804,216

$7,706,849

$2,097,367 1.3 1.3.1 1.3.2 1.4.1 1.4.2 1.4.3 Project Engineering Procedure Development and Review -Offsite Preparation of QA and Safety Documents

-Offsite (in parallel with 1.2.1)Site Mobilization and General Employee Training (GET)Site Mobilization General Employee Training Site Specific Training Site Preparation

-Performed by Staff$12,346$6,173$6,173$95,166$23,364$65,348$6,455$12,025$9,705$2,641 1.4$74,808$9,452$20,358$2,572 1.5 Page 5 of 15 Knight Cost Engineering Services, LLC KCES 2015-2015-300 Rev, O

SUMMARY

OF COSTS, continued 1.5.1 Initial site Survey 1.5.2 Setup work areas ,1.5.3 Decontamination Readiness Review 1.6 Disconnect all utilities to work areas. $6,012 $4,726 $1,286 1.6.1 Electrical

$3,006 1.6.2 Ventilation

$1,503 1.6.3 Piping $1,503 1.7 Removal inside fences $8,082,872

$7,570,361

$512,511 1.7.1 Remove compacted gravel $371,230 $371,230 1.7.2 Remove VCCs $5,464,765

$5,464,765

$0 1.7.2.1 Exterior Concrete $3,651,744

$0 $0 1.7.2.2 Steel liner $1,813,021 1.7.3 Remove Concrete Pad $2,105,596

$2,105,596 1.7.4 Remove Security Fence $63,016 $63,016'1.7.5 Remove Light Towers $7/8,265 $78,265 1.8 Removal outside fences $1,539,000

$1,539,000 1.8.1 Security/Operations Building $561,356 $561,356 1.8.2 Remove paved area inside nuisance fence $.86,508 $86,508 1.8.3 Remove nuisance fence $73,685 $73,685 1.8.4 Miscellaneous Pads $79,464 $79,464 1.8.5 Miscellaneous structures

$419,709 $419,709 1.8.6 Remove buried utilities

$153,213 $153,213 1.8.7 SOB electrical service $8,815 $8,815 1.8.8 Remove road inside licensed area $140,067 $140,067 1.8.9 Remove vehicle barriers $16,184 $16,184 Final Site Survey Structure gone -By DGC 1.9 Staff $25,000 $19,652 $5,348 1.9.1 Prepare Final Status Survey Plan 1.9.2 Soil Sampling 1.9.3 Direct Survey 1.9.4 Sampling Analysis 1.9.5 Prepare Final Status Survey Report 1.10 Orise Site Release Confirmation 1.11 Outside areas $8,712 $8,712 1.11.1 Backfill, grade and seed $8,712 $8,712 1.12 Demolition Crew Demobilization

$16,909 $13,292 $3,617 1.13 Final Project Report -Offsite $6,1]73 $4,853 $1,321 Page 6 of 15 Knight Cost Engineering Services, LLCKES21-20530R.0 KCES 2015- 2015-300 Rev. O 3.0 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate:

activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach.

Site material quantities for concrete, steel and equipment where developed from site specific drawings.

Productivity factors were applied to these quantities to determine activity durations.

Labor crews were developed and applied to the material quantities to determine labor costs and person-hours.

The activity durations were used to develop a project schedule.The level of effort costs such as equipmenit rental and the General Contractor (GC) staff were developed based on the project schedule duration.

A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that. is included in the cost estimate.Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment.

The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing.

This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination.

Clean structures will be demolished using mechanical means and disposed of at a local landfill.In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.This crew will consolidate, package and prepare containers for transportation.

The waste packaging crew is estimauted to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.Page 7 of 15 Knight Cost Engineering Services, LLCKES21-20530Rv0 KCES 2015 -2015-300 Rev. O 4.0 ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study. These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.2. Concrete volumnes were developed from plant drawings.3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Maine based on the City Cost Indexes for Bath, ME.6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.10. Transportation costs for LLW are included in the bulk disposal rate.11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.12. The following buildings are disposed of as Clean waste in local landfill.

A disposal rate of $91.80 per ton has been used in this estimate and is based on information provided in the 2015 R. S. Means Building Construction Cost Data.Compacted gravel around pads Security Fence Light Towers Security/Operations Building Paved area inside nuisance fence Page 8 of 15 Knight Cost Engineering Services, LIC ES01-21530Rv0 KCES 20!5 -2015-300 Rev. O Nuisance fence Miscellaneous Pads Miscellaneous structures Buried utilities SOB electrical service Road inside licensed area Vehicle barriers 13. All costs used in these calculations were current on September, 2015.14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.

15. It is assumed that all UMS canisters containing both spent fuel and GTCC will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $869,397 per year.17. Fees are included in the estimate at the current cost of $719,678 per year.18. Insurance costs are included in the estimate at the current cost of $582,818 per year.19. Legal costs are included in the estimate at the current cost of $200,000 per year.20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.22. The removal of the berm is not included in the estimate.23. No subsurface material is assumed to require remediation regarding radionuclides.

This assumption is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the 1SF SI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters;

4) nuclear activation of the VCCs, VCCs liners, and ISFSI pad are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface material occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent Page 9 of 15 IKnight Cost Engineering Services, LLC KE 05 0530Rv KCES 2015-2015-300 Rev. O 5.0 SCHEDULE A scenario-specific schedule has been developed for estimate.Activity durations were determined based on the unit cost factor approach.

Plant material inventory quantities were developed from site specific material.

Unit rates for cost, man hours and schedule hours were applied to the material quantities.

From this calculation the removal or decontamination cost, total man hours and total schedule hours were detei'mined for an activity.The schedule hours are then entered into the schedule to determine project duration.

Two work crews are assumed for the concrete pad and concrete overpacks.

All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 17.97 months.Figure 5-1 provides the detailed decommissioning schedule.Page 10 of 15 Knight Cost Eri[ineering Services, LLC KCES 2015- 2015-300 Rev. 0 Figure 5-1 Project Schedule 2-i- a5*8 Eus0'am ay 6 r a m day 1$. 1114 We.* 1Wa4.3 INgig, S Devesaaaladbvew-Otedays Thu' 1/11114 Wed

  • Sb elseds.TtW de1r ThjIl6114 WTu 11131/14--n-dlaiPpi~ay eedraud6 8S 4ays The 111411 Mn 111611 Sitell DydITdelgI dayl Woe 112114 The 1111114 t1C Wb oes Idap Ff1d22/14 flu 1/N4/I4"- at--" s b'mewt 1 da Mera 1/27114 655 1117)14 jj beilt81 8 t we/iitma.lS aye Tim 1/2N14 Wed 1/3144 14 11I da. 1iae 1114S Tee 1111 I Vee n:.8 dais P Wed1261 Wed 11111 beedledd be m 58/ ayeS Tlsi 1/'114 Pt 4r/411W* blU ell~n 60Tday" TIs'Wi 261 'Wed 6/1--Stedm, 14,1.U days flwh/23/4 Pit 116/4 21 aeee slaPd llu 48.1$ dais I 741/714 Man 216/14 IRemsee Sbslylala 16.3d ra 7I days Tis 3I/II/j4 Fit 3t148Gemeeedw lays Tee s w/11 Pt 111*U1561IUO N21t,7 aeys P14111 Tue M~ 6/13/1 0MflatUm C FadWne 64 bcye Tne6/3/4 s we 6/7/1 air i use .yi rev i r.u Si -, II __l_I I ml I , I *IIII I St ::::::-::::::::*.*-~**-*~**~-'**'~-.*.*.-.-.*.-.-..

IIw::::::::::::::::

1l:1 Page 11 of 15 Knight Cost Engineering Services, LLCKES21 20-30Rv0 KCES 2015 -2015-300 Rev. O 6.0 PROJECT MANAGEMENT There are three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security.

The person levels for each are identified below.6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning.

In addition, the staff is augmented with one final status survey resource and one licensing person to assist mn the decommissioning.

The staff will provide DGC oversight as well as maintain license compliance.

Table 6-1 provides a summary of this staff.TABLE 6-1 OVERSIGHT STAFF Staff Number President 1 Cask Relicensing Project Manager1 Workers Concerns Manager 1 Director of Operations I ISFSI Manager 1 ISFSI QA Manager 1 ISFSI RPM I ISFSI Operations Specialist 1 ISFSI Administrator 1 Licensing Specialist 1 FSS Manager 1 ISFSI Technical Specialist1 Assistant Director of Operations 1 Program Manager I Program Manager 1 Program Manager 1 Public/Government Affairs 1 Regulatory Affairs 1 General Counsel1 Licensing EngineerI VP CFO & Treasurer Business Administrator 1 Accounting Manager I Sr. Accountant 1 Sr. Accountant 1 Benefits 1*IT Services 1 Security Manager1 28'Page 12 of 15 Knight Cost Engineering Services,.

LLC KE 05 0Rv KCES 2015-2015-300 Rev. O 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews., schedule work and supply HP support. The DOGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a Summary of the DGC staff.TABLE 6-2 DGC STAFF 2015 Base Man Position Salary. Level Project Superintendent

$200,000 1.00 QA Auditor/Inspector

$64,000 1.00 Health & Safety Supervisor

$89,205 1.00 Packaging/Shipping Specialist

$66,522 1.00 Cost Control Accountant

$65,071 1.00 Scheduler II $65,000 1.00 Demolition Specialist

$56,000 1.00 industrial Safety $67,000 1.00 Engineering Supervisor

$113,000 1.00 Project Supervisor

$81,000 1.00 Decontamination Tech $35,000 2.00 Instrumentation Tech $42,248 1.00 Tool Crib Attendant

$33,976 1.00 14.00 6.3 SECURITY Once spent fuel and G3TCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. .While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15 Knight Cost Engineering Services, LLCKCS01 21530Rv0 KCES 2015 -2015-300 Rev. 0 7.0 REFER]ENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.2. Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors" 3. NUREG-1713, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors" 4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness" 5. 10CFR 72.30, Financial Assurance and Recordikeeping for Decommissioning
6. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012.7. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013.Page 14 of 15 Knight Cost Engineering Services, LICKES21-20-30Rv0 KCES 2015 -2015-300 Rev. O APPENDIX A Page 15 of 15 iii i. 5 55 i' SI. (55 S S i55ta~i.5lli a-.-5-~l arm--a-ll i+i almios tarn.. tiiw iairnn oa ma. mm.m um~ 5am simmml -Ws lu0ls 11 la saUs UsaOW Usas4* unsta aSjamisa wliiis 7. 13 -ii.iiim.taul Minis Imum. ill LW&5 II NIiii m.Tila-irn-a-l~l~a-~i-i lml mns 41 -1 eta.is Dma.~W (5.5W CM 5W. Ma inn mm lasH. Haul 1114.3 i win mm urns ma? sum iU urn mm u.s mm 2,1mm 'a ma mm testis usia 5Mm in sum sam tans muss a.tnu us urn mm wins u.N. 271mm Ia urn mm u.s mm &itam in arm mm turns Hams 11143 iM isa mm tans stUns 2It4 in sun m iu.ns ass. ,,tti.u in urn mm inns mis. tiitm Ia mm mm wins sum 3.tlmm its awn mm wins SliMe 21,455 its urn mm u.s mu 211455 in urn mm ia.s ma. suisa in.it..a mm mas sutn s.iwm in inst mm wins .iu~aa 21169 in an mu aim us. s.nem in win mm tans pins &itsu in ms mm urns urSa suimm in mats mm tens stunt sum in at? mm u.s arm s.,tim in mm mm urns aria ..tieu in u.n mm wins asa aiim. an wi.ii mm wins slim ~ii4u in tim.?. mm tans mm. atisa in awn mm tans s. sitmm us u.s mm usui similE itiss in.mnim. am.. urn nun Its, -ama sa 5WW* 77.3 u4 is mw is isus'aI. Ua5W CM is mn ties tans simat? Unsti use tin wins maui tistis-a-i-a n.os an utah. ira ans ilitia ,~a.n ii,. u.s asii Sian its. hiSs iii.m mu. tnt ass a.iu.uan tim gas wine ursa tiut urns a.ni it u25SU4 UisU iii p..iiA Itat iii Pisittis litaisil tewi'mlisn --ama --auwits --in -in -in -am-- is a-ill H.-~i -~i.il ii,.41s.ts isa -~t mua ,'alrni aiim mUll maw mans ia..ta Sittlil am saYs. aa.m maw main am neens iins.m SW.I ii 5. a-Ma W.hta is isis smut am.u uumis Hielas us.Pan item tans am z.iam mita 1.3555 am am aim mu tees mum mm stint. stem tans Hata ama aiim stem tans itata hum ma aim tans mis. han aiim trim aims ma.. as...SiA win uns 1mm 1.3i55 UhI aim tani siam. 5s.w alit aim tans StiLe ,asm aim iim.u inns itiuuli hum mesa nan is-ala ~16. tilt mm--

5 5744 m m ~m 45*4 253 4 25.7i1inJ 33*15 1.3. 5-ima Ii.) 1454 Mi-be-tm-.

  • 4-4,,v twu, idp.4.ma Wma-]mlmee.--4hmem.---5.3 143 55 3 SN 34.1U U 3 f3331 amw a 33 31 Smo N 33 33su-mm at v sumN GWI-0a45m 45-4 acI-a ! e 44- Wm 4..0*4 -=J4 45 IA 4- 337*4..av S -~m Sm -I 012 3ee U4N 1.44 34004 0551 34 4534 I 531 5U83 34 5157 I aa3 345JI em tw .am 5*5.13 15 33 I 5333 3 Is .m tim 31254 334 N 1 525.5 3*64 314 mm 511*53 u ma.. slams, 31.45-15 5525* 55. 34 13.7 Pm ~ N -a t i 4 sla 115.33 33 30 33m1 Otaa. 1 33*64$1447*~ .4215 rn~5 36 3 s4 a m 34 a-tWa mm 5 4 11133 33 i4 am 33 ails i,.4 30 133 44 a-adS 1.33 $143 5 Sm am 33 14 ala 33 a¶vs m 5*6 12 25 34 331 o S 2911 0 4 3453 52543 16.5* N N 516* 521i4 37714 43 ISAIS aim?122 51414555.334513N151i11 44 4451 44beNSS I IA 455551eTS455t5*1 14.1 mm'ails aIls 514 mmSt~sam p.m.05 5,444-55 1 5~a r44344~* 515544554-I 04054.44-5 I ~I 04.444555 I -* ~3 4-55145 I 51517.4.I 1adIs4-3 4455 7 L*3 F~S 3 4-33*515-k..45ee44-440544454.5 I-'--142 a Itkls C-I 444-44 I Mka.4...a, I 51253.5534-15.45 C-Me 54 0544355555 as wu~~as pese444-as sea-m as 55adsg~as sa-as ssas~a-.55 wesia-~.g as sa44a-~uam as eta-45a-s as 1545,444-3445 as ~as sasoam 35.4 55453 45.5 564 45.34 51154 sau sias'-4 3 51 4 Se 33 Se u 3 15125.33 33 3454 M4 F-4-44.5O 44.14. 04545 as as 05~44C-am..s as as wsa-.s.asu as as 44a-5545 mm mja

~22~1 2342*3~7 282322*~3M2222We 7~2-1 I3M3M23~2.

'3M.-2 ~¶ ~¶ 128 2332We 2 223We 1 7.*M 2 3232 21 3M 3M 3M 3Mo~3M 3M 3Ma 3M 3M 3M 214.2824 d 4.3. 3.34 2~ 3332 2824 0-- -WA ------Ossa LEAVe -We -4824MM MUMU 282We ~V3M 82323282 1MMA~ 2~43 -~ ~ £~ L~ 4.3 4.3 33 4.3 33 3UF3Mm~23 223 143 We2.3M3MM 3M 33p3M4~3.aM ~3M 3.We2~3M 3M 3.2343333232 3M W314i28I~223 33 W343.~i3.23 3M Wm328We434 3M 3822.42833.343.

2742M 42342 333 3.3 3.272 21*8.~2 223.7*2 We.8.232 p17341*233*~. --IA) 231238272382 We We-*52~223 7 22834. We34 23338.422 7 32322 7 ~We 2W~I3.28.7 73332sh 2 ~3M..123 7 23123 123233233 I 33321 I 743.2 ~2 21 3MW 13. 73. 73.-- -----17 23323 2332 flU 2? 3533 2253 4 2223w 213 22 24M 3323 2737 7 737273 223 27 23*223 2323 24.13 32 3M 3 6 2ft323 542312 217.32 4 73 542 233 3.531 2353, 3M 3M 33223Ao*~3M 3.33333123.3.3.

3M 3.3 W3We~3M 3M 3M 33 33323428.3.

3M 3M 333333288.38.

3M 3M w*33~We 3M 33 3332833343.

3M 3M 3333213.233.

3M 3M 333332333.

3M 3M 33332123.323 3M 3M 332.34213234223 3M 213 33 2.34323.3.3.

3M 3M 333333343.

2243 2233-um 3234 21.a..5322 2733-u 6 MM 73 213 23 743 73 33 353 3,23 272.35 213 34 37 2MM8823., 1227.71.2J 823343.1.2Z 32327.#23* ,3 73O 430 28* 23 23 43 24 334.,. 4334 i 34I 4,e 3tlS WeIl 334 0 3211 2*732 33 7 3 3*1 213 273* 3 17137 2421 3 3 3.3 235 3 27 3m 22.3 215 22.73 27*3* 4 24444 2 3*3'U 2232.32 372*21 32 M~ 73 3.72 247228332733.122 3)2 2 2 2 2 22 27.43,222 24428.32 3 3 232.427 24.72232 3 33432 3 313)4423-3321 ~3L ft 33224 33 33.4. Sm 24 31223 71333 332 723.3 233--We 223.54 33 *233.8...

22 7332 MUAI 143.2 33 23 23 23 3M 3M 33 223 73.323 731223 3218. 213mM 3M 3532323 21122)223 77.22 38.232 A 2.32 73 3.21 72*27 322*7 7*2.32.2 43238 23 22.327 738. 43.22.1 V.3..3fl 2138.7.22 237 232243.8.

33 0.38234 3334 24 24*22 23222 2.3 4253 832*2 3.3 3.3 33 22282 33.3 7223. 332332 22 2 733.2 32~2 743.2 MU 23 23 33 3M 33 3M~ 8 2533242 2,2273 3M 23.323 22.3 223*33 2222.343 27J 73 2323 3237233.324347 G.3~32.4~3.

Th8.328.542343823473537454138.322.21333..

aM ~3U2 63 73.2 32737 232.32 3 27*1531 227 733.57 723233.3 3.3 77) 23222 33222 Pd A 73 73 733 2.23 3.2.3 2333 33 #3 33 3.2.32. .27.ft 222222.18.

We flat 3.23 332 23 23 3233 232323 .331 42 233 3M 3~3.7.3 733 333.333.2124 23227 2732.32II 3 2173122 24.73,23 73 733 7543113333327 71333.3.,.37 177227..8.3..23..24.273747242.21*8.*2A2322*2322282*2 133 Usa mm 464 -lmm1. -lUsa --- -LOAWS. d... 2*4 -V -VS. -LSA. ---12.4 ~i~A Wam l~

  • Us64 Y~ Y~M lmm*4 ~ ILmm64 1.~ 1*4Us Ca. Us Us lb W.~24 V*4l. 5*.d~ C*412 Tammi Usm5 1445 ~0Us am ma. 48 515 d1 U lam 365 mm as.aja..m a.,.,. nn I14amm Urn junam. ua.inis I.7A Us.a.3~I14U A In In IOU 164 56 1.0U 16.16 15 52 Us.m4a. ad l~ I.1. MV.1 ~54ft 3141.114 Usm.1. Us Oil 3551% 21n.1s.Us a~5 ~a 116 16014 USA1a Lam W a.. P~a.. mm 134 am 146n lb 13 INasn ,m 13 am ,,,.015 m. 1 0 4 5.m n.m UISA.aml.,.0llamlU US 6* 56mm us urn U Oem mmtm mm 3E ~.l ImmOiS ~6I 1445 ma. lUam .3 6* 26154 MMMI 15*157 am am am am am 115 UsL.UsT A Us im 3665 13. 56 46*4 46'1.6.. 6444. ~ ~'1R *56455 am ~1. 5165 mm 53~mm S 1215 311 am. 3I1 am OS LOUs mm bamedd*4 lao. sam ma .~U.am 15.134 565 13. ~1464 mm Usmm a 654 5.655 U A 215 53 mm T a 6 015126 061. 16 1 tin 53 mm 01am3'in U UsM 54.16* am 1* I 16 mm mm ~ 14 Usd1 224am am 114 I 501 3a.mm a.,, 5131 U 14, 115 am U~446L22U5*5l22 16 41.8 151.053U 22312616 Im 2,6 52146*65.01 a3314 IM 146 14 446 in am 56mm In 106 564*4 ma 5 ISOZI s a a.amsa.me mm~am mm.. mm.. ~ ~mm.s ~mma mm~s rams mm a.~ am 5166 mu mu am am am am am am A 1514 .m m 0.45 I. mm.aa52.53 U II6 U 65 U Il554 5i5 aIm U 161* IlIA, 5356~5-..mm mm..am mm mm.3~amm mm mma.mm~mm amamamins 16 13 W 5.124 am 114mm ad 3*4 2*6.1 ~.ft 14.In mm mm.a..& Sm a am am Cm sin 1mm spa.71056 1.aas15sU .sau. .u am am ~d64 566 ..inam.rn .US 11656 arm am ~wam¶ 4U2m6 22610 165546 11(14 UOSII .604 IWU 314 55, am U13SmUU.U4MM216 I 853 4241512Us.sa.2241 113Me1.a.*4.

fraamam.am.,Wa..a..mm5m.a..m.,mbl.2*4e~.14*4.1.

1 1~31 *4aa2U.....meU 11*UA.a..Us 1mUs515.ama..am.3..53515Usk3I..*Usmm44~

16 2612 3512Sm.m3U41 14.1)0122.

mm mm.. mao a. Va.*4.. 03645 I)m.14l a.Sma 10(5 a. 1Jan16 236516*5 211.35 am a641J1 amJaa.3a aW*l40 am am am am am am am.5.2 ma.56smm a 54 lm EN Us am 365*. 46 11am- ...ms Us.in~A 14am.u. mm mm.a.t mm mm mmm 616 044 amIss .a.m. ImAs 20* Us 03*..inn mm Smab. mail. a.Eain C.0 114Sma 61443 7445 ma ,wm.in ma am am mu miMn maw am am am am mm am am I*~ Oe53 5 16 16 15151 13. am agOem. amm, a mm... l56a. L~1. 446.4. 11441.14.

~ mm mm...t mm mm mm am mm am talam Irn 44 mm ma. mm lao 0d1 5.45 U 5 am mm mm PIn ISo 31(0 54656 046 222 III Cm mm 1648 am me mm~ 2*o a.6 013.2 1mm; a..ga rams mm mu n.m am am 18 24163 mm~a au am am am am am am 15.4 *4~ftb 5 14 1.U 1454 Us am 4145-. Id ma mm 44a+/- mm~ mmiA. mm mmla.a. mm mm 53*464 &mm mm.. .6.16 2mm am am ~am mm mm. mu 6* .me 5126 IU am a...4in~mm mamma in. ,,am mm. mm am am ..4am 6146 am me ~ am 36. a.mma ramIla mama maLi Us' WOIWn 1.5146 mm am 11151.3 a.m ,s..lm.u mmoam am am am am am am am.u ~ 5 Us lm 22122 144 am~.,ammmlm.65U1a 35-. 56 mm ma siam.. t agm.~ft mama 424 mm amlS.L mm mm 535, am 3am lImos an n.am sam.mm 5-am. Us 265 456am .6*6 65 liP 36 ~1464.mm ~mm am am. mm as. 61465 ~3.mm a43 ~am 156' 6 L.a. SlUm en mm mmmm Us uW am mm am am ..mm 5-mmmm.. 165 IM5W am inn am 346 6160 mm 5-amm. UDU LinuS 4am m.56 V.6 Us ~6am mm mm~mm 6*1 3 am mrn en mm ~bnmamm 4am 2.64 16mm rnn'A UUd1 Sm n. 6.0am 4d5 1015 mm i mm'I, ino ,tJm sam**16 71 4.6 ma 1616 U 64121 114 55..I 7151 J..UOSma.65.U1 U8m.Uc4.a.,3.

13m5h..ama.Sm.l1.0*4a.24Us14562*Usmmamam I 3M 2*U4Imma.U6.U41 11356U.a.a.4'1 amUs0m..am~mmmmmm.m3b56amUsmm1464.

I 1* lbUUSmasftUsl 123 d2122.,..s*..

l4*Us0b444d.mm~5356mmUsfr*42*445-ammst mm a.722 1411.222 16 36 UUSma.21.641 14.12146.I am l3Ustmmmd1.U41 1236'U,,a..*..

UsUsk1..ams.mmI2*a.444...44.a.s..mbUs.sa64lmm424.mm..

in am UUSmUU.64 l1.13Ua1.16 am 621mm. 30411.120101.

am lame.I 122.3 25U16mm107111.IVIU, In 2233 UIlUsUamSa22l1.152m 16 lISa UU14a.3U41 1511010 I flU 3SUmU.U~I Wmad1c...in.raa..

1Us446am1...SbW.514415.&

mm am 215445. mm 36mm. ~1a ~a.s.5 mmV.a 1440 65 *.mamas amom 13112 am laliaM Um6'l) 1613.14 am am am am am am am ISa mm...... dO.. 5 26 151 26*1 1.140 am ama 356' Id mm... 064 14. 44.51 1644.414.

Sm4. 124 mm ~5~1. p..p mm 5-a64ssa*4, am am am Us s~1.Ms 16 2213 313mSm)1 22 322am mm aao-.m.ma am iso U155 2mm 3.3 .4 11456 16 244.4 22135.5. .am22U4.14316 5444.322 a.01.113 1122312 amm tea amamama a ama.~. a am meisaise.~

am~amam a--Se.5is *5 LiAise -_ a.~a- am LU. ama .m am sim us. am an am a ui am am 517 5 a am am s.ai a 5A54 tArn am 1ZS 4 am. -am in a ama sam t.t am em asia saw as. am 4.4 SM.5 ~ t.d *441 is~ Se. a- 2Sii~ n.m Se. ----c ,..we we we we it..amfl Vdt.5 Tame. ame. LamM ydu..M .~

  • Ta CaE tad.~it w55 e.s41 S issama in ii, aim in us ammamita*ittu.

Lam itO m.m ma,.eg..alsamamnin Lam in intL.a.urniwits is.im Sm 58 arnams. Uft14UM am in am amam am in us am in am at,'U in am am.. am amam. ., is ama.a va.a a- am UP 4.4 MM ist17~ Wb 3mm am a. am MM mm MM MM iA7 Imamama-e La l aIa am SM Ue etVkl e.,WlR&r am gw L Llama am1eo Ifl sew us U ftp am itO 38 m*rnamm Ui5i54 SM La- itO iU Uit.a.UU&istlSM 3m 18 GM MisiM~IiU3i4 U-MIII U an -ut amamam am.am is~a. e.~ Md-. a-a. Tg.) ~5 ~t a- 4M 5W LuG MM Ig.7i SIMM Ugt4 a-am am am am MM MM MM MM a a in MN a wiam. am..am sews.. MM4.g weaa wesseft am V~wet am ti7aa MMO 141345 .34g. IMMU-MN am U'am sin MN MM ftP iN US? SMTwaMesisuM i3.iTI Ut?mi. w aiUtua SiM aI a.,ma we.a-a--as am.ame.am.

a-Ca am a-a-a-a-U-a-a-weIIam a-sm.a-ait MUam am... a- ,a~am.e a-wi am..., am.. ra.)reaM g.e gas Siam.,. Ms.u.4 .saain am an MM tam mm MM a N IM USS Ut vga- am. sE tam. Am.g.I ve.a. ft mama am e..gwet e LI. SimM Mu. MN Lit ita simm -a.. an an u.n mm. use an OASiS 05g. Gig iii am 3am mm. me ssi a m em. letS lit is' Nm. mm am a it am. am am tiaSi il.USI. IGaSa IASM NI sun am am am sun in a-.. itim ~E amiss Ts.I US.t Ta.)41MM ami in tan sauw 1)91* Mmii em am GM MM Urn MM MM u.n in item ma ma uw.tit am ..3m MM isEim am se am sa am ii asistam in ta Ii -~Mn weams am bis 116455 pJ i ii) e.mUa-u.ggsi IIIS.I.asi.e.a.

lis.aa55esMmammewaiam....55amam..a..ie.am.ama.

I tit 4~mt2S.ese.g.U4i g.Um.a.is...a~

tgsis41.minamaiam...a.e.amams.am.amam in am g in am ama SM W.Mi2am..mU41 ttn~M.is..u~.

ThSaGM.Mewa.u.iam.u.hewa.igteemamw..am.mewam in SAC s~in~ins.in in am U iam in aatIam..Uusi la4aamm,, ewa. T*a5.nea-eU-.m.amammamewsamvgame.ams..saa.

in am am we we Tae.a-u.I...in...bGeCa u.S a-am a-a.a.05.iii ..eam S5l tat a-a41e..Sat a-RE a-a-a-a-.. amm mm'is amIMa-~igamue...hadaa ii iit.5 .44we4.u am we 5s'ai Siam g awam* am. a -* am- .is..is e. 24 5s us am- a "is it am. si a.a isa-a U ewam- 535mm$ am I am-I.amltm a ktl vlsl iS A 5it~ Sm is@8 a am an am a am am am mm A 54N iM isism a gin tEb~. tam *EU..iS am we amg.a am.s.a am a-suet am NP aim am em SM lat seMise. SM lit aainwe.siuas.,sw aim ama am am am isg.fra ItO U IMweainU S.5)S an am ltD m U w u a g.m g.m am ag.g.a 5W MiMg.W a-4.55V amw...it.

G~a. sil Ta.5 saweesam 5551mn tam en mmn N5iMa-Mmi4Stam a-a sam ass anma-nmu.stin.smaai uazeia is it a 11613 aiIm nmi I amawama..I eweamew S samaa-a-a amaamseam I GitO....5 si am.I ama-I ama-I bia5sa-am I a-a.a-S ~5mis3isThM am.aisU c~a MI. ama-am....

MM amam~a-.a son ama-am....

UI. a-a-a-am.a MN amama-ame.m MM ama-a-ama..

MM ama-tame....

MM simawia-.....

MM ama-a-ge..

MM ama-a-am.lam ama-a-gm IWIdO1w¶ dI 2~*m I 7 LJ 1 ~m Sm m* m*6 116 1124514 IC

  • I~16 84453 ~A 316 *16 316 S S.* 36 2*13% ft~ C 3%~2 6144* 3 ¶16 *145 3 S 11316 14 116 3.13 3 I 6*1646 3 *16 14.13 3 4 3 34*3 3 3471 16*12 *443 1*461 ENCLOSURE 2 TO OMY-15-053 CERTIFICATION OF FINANCIAL ASSURANCE CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee: Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 72-30)321 Old Ferry Road Wiscasset, ME 04578-4922 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Maine Yankee Atomic Power Company is the licensee for the Maine Yankee Independent Spent Fuel Storage Installation (Maine Yankee ISFSI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the Maine Yankee ISFSI.During the operation of this ISFSI, spent nuclear fuel and Greater than Class C waste will be stored at the Maine Yankee 1SF SI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated casks will ultimately be removed from the ISFSI location, and Maine Yankee will dispose of other radiological waste in accordance with NRC regulations, at which time the Maine Yankee ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund Maine Yankee ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in Enclosure 1 to the letter to which this Certification is attached.That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of: Maine Yankee ISFSI $21.6 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella Maine Yankee Atomic Pd rer Company -Vice President, Chief Financial Officer, and Treasurer

-, Phone (860) 267-6426 x304 Corporate Seal Date \

ENCLOSURE 3 TO OMY-15-053 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRADIATED FUEL AND GTCC WASTE Maine Yankee 12222015 2013130? Budget Maine Yankee Atonio PeoenrComanry Spent Feel Managennnt and ISF21 Dnem Estimate-OEC~sanmeal Sumof62060 Sumaf2all Somal201 Sumneoele¶ Bumne2020 SanneOOOI2 5umof202~2 Suofoe2022 S~oaeel02 5wna62025 5umno62226 Suno62027 Sumnol202a 9ame12029 Sumoe62010 S~onnelO t smonteta3a aunnaof20 SrnetTalteale20132e.abat.-Sn-Manual latlrniab Supple.3o22d* Serreos- Fuel Leedina)22aso Saraos -ISF510CPa>226ad aauoans- 222-RAiD 252 atl1FSl Dupaaa Saeraica -29 P6D DaloISFSl logulalary Fe,.522,216$1,943,522

$2.750.762

$105,0473 Ila,274$-$-$225,275$612.452 $et5.5sa $ 455.3701 4220947 $ 474,522 55.O200 $ 522,2106 5022216 0 505.21$6.203,205

$ 1.243,20 $ 1.043.922 1,203.922 3.225.704

$ 3.225.724 3 .025.704 $32025,784 52,125 $ 22,025 $ 92,125 $ 162,247 113.207 $ 113.074 5 113.274 $ 113.074 552.223 $ 552,9223 522.223 $ 552,223-$ -.$3.932.235 5 7322282 725.203 $ n4.590 305.272 $ 219,2728 7534823 5 424,621-3 -$- $ --$ -$ 6 1,.0229$22 1,022,2229 0,222.2229 1.0802222 225.275 $ 225.275 2 25.275 5 825,975 018.452 2 112,4258 118.452 112,452$ 4L55.270 2 452,271 $ 455.270 3 455,371 0 425.754 2 455,371 $ 455,371 $ 452,271 $ 4552371 $ 422.232 0 1,52487e2 0 522,216 2 502,202 $ 5220,21 2 022.216 2 520,202 5052,216 5 54,219 $ 522.216 $ 532,216 $ 592,219 $ 222016$$ 1,843,906 0 1,823.922

$

2 1.043.922 5 1.543.922 1,243,326

$1,943.902

$ 1,843,922

$ 1.943,222

$10.43.222

$ 1.23.92,36$

3 22,1225 92.025 $ 92[2,12 92,122 $ 92,125 5 0,125 $ 2,0225 92.125 $ 22,025 5 2,122 $ 92.0225 9 052,223 2 5029,2 $ 5523238 0 5529,93 0 52522 $ 552,523 529,923 $ 2359293 $ 5529,223 052,222 2 205,076 2 205,272 2052372 215,372 0 0.0323.04

$ 215,372 205,272 210,272 215.279 424,221 0 723,8230........$ $ -" $ " $ " $ ...6,212,2..3 $ -$- 2 -$ -$ -$ .0 -$ -$727.522$14.el,.32o

$ 1.040229 $ 1.0802.32

$ 1.0222250,2,229$2 0,022,229

$ 0.9222229$

0.022229 $ 0.002.222

$ 0.020.229

$ 1.222291,80229 0 1.08022,229 O Ilo45 112,452 $ 118,4,58 116,452 012.402 019.452 108,4528 112,452 112,452 011.4528 161.5342 231,929 277.923$52,12352 241.525$90,727$9292068$226,22$9,126.822 1.,02.,376 722301,25 2,1092.470 17,5222221 6,14.2352, 1.921225e OrancdTotal

$ 12761494 $ 12606G720 8 91622223 61220992282

$ 91992492 $ 8i522263 $ etE62r78 $ 69r22780 $ $ laal10e8n 6 95622760 $ e912172e 0 29626278 $ 892.21700

$ 9242i6 $ 22202337a 32$2i316010

$ 0 946123 0 ieeoo26uae Noba 6: 75 et et managae~nt af Irtdiulod fust and GTOC Costes clonnatad as tosaa:$ 004.722,222 Grand TotalfSomajbooo

$ (9.013.2021 Naon-Rd 0&D ISF51 L.25571Rod 022 ISF51$671,217,616 Managesrnantallradluled Fuel 2722 Waste Noloa2: Th~olestofRAD and NsN.RAD 56BoftherSFSlpn201adlodaas auproidedpod haealunes labalad "Sumaot2203Pand"Sunlot2203T"Isaeorved by esaaua~ng tvalUe espn~osrodsd n E~ondor 027y2.5%.N90o 3: Ti~s Saronon C32rles MOYe 2013 Approaod 0365 Role Case rai tha Knight Cost Enginoeelng Seslos 2215 RAG end NO2N-Rud 0S700 Doam Cost Eusnoate