ML13233A068

From kanterella
Revision as of 11:42, 4 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Monticello Nuclear Generating Plant - Response to an Apparent Violation in NRC Inspection Report 05000263/2013008 (EA-13-096)
ML13233A068
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 07/11/2013
From: Schimmel M A
Northern States Power Co, Xcel Energy
To:
Document Control Desk, NRC/RGN-III
References
EA-13-096, L-MT-13-062 IR-13-008
Download: ML13233A068 (99)


See also: IR 05000263/2013008

Text

Monticello

Nuclear Generating

PlantXcelEnergy

2807 W County Road 75Monticello,

MN 55362July 11, 2013 L-MT-13-062

EA-13-096

U.S. Nuclear Regulatory

Commission

ATTN: Document

Control DeskWashington,

DC 20555-0001

Monticello

Nuclear Generating

PlantDocket 50-263Renewed Facility

Operating

License No. DPR-22Response

to an Apparent

Violation

in NRC Inspection

Report 05000263/2013008

(EA-1 3-096)References:

1) Letter from Nuclear Regulatory

Commission

(NRC) to Mr. Mark A.Schimmel,

"Monticello

Nuclear Generating

Plant, NRC Inspection

Report 05000263/2013008;

Preliminary

Yellow Finding,"

dated June11, 2013 (Accession

Number ML13162A776)

2) Letter from Northern

States Power -Minnesota

to NRC, "Notification

of Intention

Regarding

NRC Inspection

Report 05000263/2013008

(EA-13-096),"

dated June 19, 2013By the above referenced

letter dated June 11, 2013, the NRC transmitted

Inspection

Report 05000263/2013008

for the Monticello

Nuclear Generating

Plant (MNGP). In theinspection

report, the NRC identified

one finding and apparent

violation

with apreliminary

significance

of Yellow for MNGP. In the referenced

letter, the NRC statedthat the site had failed to maintain

a flood procedure,

A.6, "Acts of Nature",

such that itcould support the timely implementation

of flood protection

activities

within the 12 daytimeframe

credited

in the design basis, as stated in the updated safety analysis

report(USAR).Northern

States Power Company -Minnesota

(NSPM) reviewed

the apparent

violation

and, pursuant

to the provisions

of the choice letter, prepared

a written response

to theapparent

violation.

NSPM agrees that the failure to maintain

a flood plan to protect thesite from external

flooding

events is a violation

of Technical

Specification

5.4.1.a.This letter submits additional

information

for the NRC's consideration

in its finaldetermination

of the significance

of the apparent

violation.

The enclosures

address thefollowing:

e-7A

Document

Control DeskL-MT-1 3-062Page 2 of 5Response

to Apparent

Violation

(Enclosure

1)NSPM agrees that the failure to maintain

an adequate

flood plan to protect the site fromexternal

flooding

events is a violation

of Technical

Specification

5.4.1 .a. NSPM is takingthis failure to protect the site from external

flooding

very seriously

and has used it toreinforce

NSPM's policy and commitment

to safety as a top priority

in our Emergency

Response

plans, response

to acts of nature, and effective

corporate

governance

andoversight.

The site and nuclear fleet are taking corrective

actions to ensure protection

ofthe radiological

health and safety of the public in the event of an external

flooding

worstcase scenario.

A summary of the corrective

actions to resolve the performance

deficiency

is presented

in Enclosure

1.As part of those actions,

NSPM is performing

cultural

assessments

focusing

on decisionmaking, effective

communication,

and closure follow-through

not only at the site levels,but across the nuclear fleet to maximize

learning

from this situation.

Probabilistic

Risk Analysis

(Enclosure

2)NSPM developed

additional

information

providing

further insight into the probability

of aProbable

Maximum Flood (PMF) at the Monticello

site for the NRC's consideration.

Thereport provides

probabilistic

risk analyses

to support a best-estimate

assessment

of thesignificance

of this finding as well as bounding

analyses

to support final significance

determination

prior to corrective

actions taken by the site. The best-estimate

analysisincorporated

the assumptions

necessary

to support the assessment

of a finding relatedto an external

flooding

event. Results are shown in the table below:Nominal,

Best Sensitivity

1: Sensitivity

2:Estimate

Bounding

Flood SPAR-H HRAFreauencv

Probabilities

CDF 1.04E-06

3.1 OE-06 1.83E-06ACDP 8.92E-07

2.66E-06

1.57E-06The full results of the event tree quantification

are summarized

in Enclosure

2.Monticello

Nuclear Generating

Plant Flood Protection

Analysis

(Enclosure

3)The postulated

PMF for the MNGP is compared

to other site Mississippi

river conditions

in the table below. The PMF is not an instantaneous

event, but rather a slowlydeveloping

evolution

that allows for plant staff to monitor,

predict,

prepare,

andimplement

appropriate

actions to provide the required

flood protection.

Since actionshave been taken to procure the bin wall and levee materials,

performance

of areasonable

simulation

demonstrated

that the levee and bin wall system can now beinstalled

within the available

time as defined in the licensing

basis.

Document

Control DeskL-MT-1 3-062Page 3 of 5Normal and Flooded River Flow Rates and Water Elevations

Mississippi

River Flow Rate (cfs) Water Elevation

Condition

(ft. msl)Normal 4,600 905Maximum Recorded

51,000 916(1965)1000 Year Flood -90,000 (1) 921Probable

Maximum 364,900 939.2Flood 364,900_

939.2A report entitled

"Monticello

Flood Protection,"

was prepared

for Monticello

andaddresses

the aspects of flood protection

for which MNGP was licensed

and is includedin Enclosure

3.Annual Exceedance

Probability

(Enclosure

4)Annual river exceedance

probabilities

based on annual peak flood estimates

at theMonticello

site were developed

to support the probabilistic

risk assessment.

Theprobability

of a PMF at the site was determined

to be extremely

low.Enclosure

4 provides

a copy of the report entitled,

"Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at the Monticello

Nuclear Generating

Plant basedon At-site Data for Spring and Summer Annual Peak Floods",

June 28, 2013, developed

by RAC Engineers

& Economists.

Stakeholder

Outreach

(Enclosure

5)NSPM hosted an open house to share information

with its community

neighbors

on itsoperations

and preparedness

to handle potential

emergencies

and how it would respondto flooding,

earthquakes

and other unforeseen

challenges.

The key message presented

to visitors

was that safety and security

at the NSPM nucleargenerating

plants are top priorities

for Xcel Energy. Further,

that we understand

theindustry,

NRC, and public's

demand of higher safety standards

and flood preparedness

at the nation's

nuclear power plants in the wake of events such as 9/11 and Fukushima

Daiichi.

The Monticello

Flood Protection

Strategy

was identified

and explained

todemonstrate

that the site is capable of withstanding

a PMF and that the site isincorporating

lessons learned from the industry

to improve and assure protection

methods.Safety Culture ReviewNSPM agrees it missed an opportunity

within its control to identify

challenges

to theimplementation

of the A.6 procedure,

leading to the identified

apparent

violation.

Assuch, NSPM assembled

an expert panel to examine the behavioral

and cultural

aspectsimpacting

decision

making within the nuclear business

unit. This activity

was chartered

Document

Control DeskL-MT-13-062

Page 4 of 5as an immediate

and interim measure preceding

the extensive

root cause evaluation

that will be performed

to identify

the full magnitude

of this issue, associated

causes, andcorrective

actions to prevent recurrence.

This expert panel assembled

to examine safety culture within its nuclear organization

was comprised

of five independent

consultants

and one Xcel representative.

The teamreported

directly

to the Vice President

of Nuclear Operations

Support.

A phasedapproach

is being utilized

to examine the behavioral

and cultural

aspects impacting

decision

making within the nuclear business

unit. Three phases are planned to examinethis subject:

Phase (1) is specifically

focused on the Monticello

flooding

issue, Phase (2)more broadly examines

Monticello

issues and Phase (3) examines

Prairie Island issues.While the phases are specific

to the individual

sites, the scope includes

developing

anunderstanding

of the corporate

culture and influence

beyond a site-centric

examination

of the behavioral

and environmental

influences.

To date Phase (1) has been completed

with scheduling

of Phase (2) and (3) expected

to commence

and complete

over the nextfew months. The initial phase identified

improvement

opportunities

in the areas ofdecision

making, leadership

behaviors,

and questioning

attitude

regarding

the station's

preparedness

for a PMF. The results of this assessment

have been insightful

and will beapplied across the nuclear fleet to ensure a healthy safety culture exists. Opportunities

have been identified

to strengthen

fleet and Nuclear Oversight

accountability

forproviding

oversight

to proactively

detect performance

gaps.Interim actions are in place for the short term to focus on the areas for improvement,

andlonger term actions are in development.

SummaryNSPM respectfully

requests

that the NRC consider

the enclosed

information

in its finaldetermination

of the significance

of the finding.

Notwithstanding

our assessment

of thesignificance

of the finding,

NSPM clearly understands

our performance

shortcomings

concerning

flood protection

for the entire spectrum

of possible

flooding

events at theMNGP. Corrective

actions have already been completed

to address the NRC's identified

performance

deficiency.

Additionally,

we unequivocally

acknowledge

the need for overallperformance

improvement

at MNGP. Actions are underway

to ensure that the lessonslearned from this finding are applied more broadly to overall performance.

Summary of Commitments

This letter contains

no new commitments

and no revisions

to existing

commitments.

Mark A. SchimmelSite Vice-President

Monticello

Nuclear Generating

PlantNorthern

States Power Company-Minnesota

Document

Control DeskL-MT-1 3-062Page 5 of 5Enclosures:

Enclosure

1 -Response

to Apparent

Violation

Enclosure

2 -External

Flooding

Evaluation

for Monticello

NuclearGenerating

PlantEnclosure

3 -Monticello

Flood Protection

Enclosure

4 -Annual Exceedance

Probability

Estimates

Enclosure

5 -Stakeholder

Outreachcc: Regional

Administrator,

Region III, USNRCProject Manager,

Monticello

Nuclear Generating

Plant, USNRCResident

Inspector,

Monticello

Nuclear Generating

Plant, USNRC

Enclosure

IResponse

to Apparent

Violation

EA-1 3-096NRC Inspection

Report 05000263/2013008

Monticello

Nuclear Generating

Plant3 Pages Follow

Northern

States Power Company -Minnesota

Response

to Preliminary

Yellow FindingNRC Finding SummaryThe inspectors

identified

a preliminary

Yellow finding with substantial

safety significance

andassociated

apparent

violation

(AV) of Technical

Specification

5.4.1 for the licensee's

failure tomaintain

a flood plan to protect the site from external

flooding

events. Specifically,

the site failedto maintain

flood Procedure

A.6, "Acts of Nature,"

such that it could support the timelyimplementation

of flood protection

activities

within the 12 day timeframe

credited

in the designbasis as stated in the updated safety analysis

report (USAR).The inspectors

determined

that the licensee's

failure to maintain

an adequate

flood planconsistent

with the USAR was a performance

deficiency,

because it was the result of the failure tomeet the requirements

of TS 5.4.1 .a, "Procedures;"

the cause was reasonably

within thelicensee's

ability to foresee and correct;

and should have been prevented.

The inspectors

screened

the performance

deficiency

per Inspection

Manual Chapter (IMC) 0612, "Power ReactorInspection

Reports,"

Appendix

B, dated September

7, 2012, and determined

that the issue wasmore than minor because it impacted

the 'Protection

Against External

Factors'

attribute

of theMitigating

Systems Cornerstone

and affected

the cornerstone's

objective

to ensure theavailability,

reliability,

and capability

of systems that respond to initiating

events to preventundesirable

consequences

(i.e. core damage).

Specifically,

if the necessary

flood actions cannotbe completed

in the time required,

much of the station's

accident

mitigation

equipment

could benegatively

impacted

by flood waters.NRC Baseline

Significance

Determination

Process ReviewAs part of the process,

the Region III Senior Reactor Analyst (SRA) developed

an event treemodel to perform a bounding

quantitative

evaluation.

The model presents

an external

flood eventthat exceeds grade level (930 ft. MSL) and requires

implementation

of Procedure

A.6, "Acts ofNature" Section 5.0.NSPM ResponseNSPM agrees that a performance

deficiency

exists. Procedure

A.6, "Acts of Nature",

at the time ofthe violation,

did not provide sufficient

guidance

to execute mitigation

strategies

for a probablemaximum flood (PMF) event. Adequate

management

oversight

and engagement

was notprovided

to ensure that the Monticello

external

flood mitigation

procedure

and strategies

metexpected

industry

standards

and licensing

basis requirements.

Actions have been completed

to reduce the flood mitigation

plan timeline

by pre-staging

equipment

and materials

required

for bin-wall

levee construction,

improving

the quality of theA.6 "Acts of Nature" procedure

and pre-planning

work orders necessary

to carry out the A.6actions.Summary of Corrective

Actions:Acquired

materials

required

for flood mitigation

including,

but not limited to:" Hardware

and components

for construction

of Bin-Wall" Clay for levee construction

(30000 cubic yards)* Rip-Rap stone for levee construction

(1700 cubic yards)Page 1 of 3

  • Sand for levee construction

and filling sandbags

(11000 cubic yards)" Sand bagging machine (Capacity

1600 sand bags/hr)* Manual sand bag filling tools (25 on site)" Gas Sump Pumps* Electric

Sump Pumps" Crushed concrete

for alternate

road access (2400 cubic yards)* Preventative

maintenance

plans are being developed

for new flood mitigation

equipment

  • Performance

of reasonable

simulation

of major steps required

by procedure

A.6 "Acts ofNature" Section 5.0, including

building

of bin-wall

sections,

sandbagging,

placement

ofvarious covers, and relocation

of vital equipment.

  • Extensive

procedure

revisions

to enhance feasibility

of actions and reduce overall timerequired

to execute the strategy.

  • Table top exercises

of new revisions

performed

to ensure practicality.

  • Development

of work orders to provide more detail for execution

of steps within procedure

A.6, "Acts of Nature" Section 5." The existing

flood prediction

surveillance

was revised to occur on a monthly basis insteadof yearly and contains

provisions

to continually

monitor river predictions

if certainconditions

are met.* Meetings

with the National

Weather Service were held to develop more robust prediction

capabilities

and options.* Enhanced

construction

drawings

of levee and bin-wall

to provide more detail* Updated existing

contracts

and memorandums

of understanding

with vendors to assureequipment

availability.

  • A modification

is also in the design phase to install the base of the bin-wall

on the westside of the Intake structure,

simplify

construction

on the east side of the Intake Structure,

and also update the steel plate design for protection

of the Intake Structure.

Review of NRC Significance

Determination

NSPM has developed

additional

information

providing

new insight into the probability

of a PMF atthe Monticello

site for your consideration.

A report entitled

"External

Flooding

Evaluation

forMonticello

Nuclear Generating

Plant" was prepared

by Hughes Associates,

Inc., for NSPM. Thereport provides

a best-estimate

assessment

of the significance

of this finding.

Two (2)sensitivities

were performed

to assess the bounding

risk, addressing

some of the uncertainty

associated

with this assessment.

The first sensitivity

study provides

the risk assessment

if a bounding

annual exceedance

probability

is assumed.

As noted in the Hughes' report, the uncertainty

associated

with extremeflooding

can be addressed

by artificially

restraining

the AEP to a value of no less than 1 E-05/year.

When this restraint

is assessed,

the ACDP is 2.66E-06.

Enclosure

4 of this letter provides

a copy of the report entitled,

"Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at the Monticello

Nuclear Generating

Plant based on At-site Data for Spring and Summer Annual Peak Floods",

June 28, 2013, developed

by RACEngineers

& Economists.

The second sensitivity

address the different

methodologies

available

for quantifying

the HumanError Probability

(HEP) associated

with the manual operation

of RCIC (Reactor

Core Isolation

Cooling)

and HPV (Hard Pipe Vent). This sensitivity

provides

quantification

using The SPAR-HPage 2 of 3

Human Reliability

Analysis

Method, NUREG/CR-6883.

When the simplified

SPAR-Hmethodology

is used, the assessment

results in a ACDP of 1.57E-06.

The result of the nominal,

best-estimate

assessment

and the two (2) sensitivities

performed

areshown in the table, below, for ease of reference.

Sensitivity

1:Bounding

FloodFrequency

Sensitivity

2: SPAR-HHRA Probabilities

Nominal Best-EstimateCDF 1.04E-06

3.1OE-06

1.83E-06ACDP 8.92E-07

2.66E-06

1.57E-06Enclosure

2 of this letter provides

a copy of a report entitled,

Report Number 1SML16012.000-1,

"External

Flooding

Evaluation

for Monticello

Nuclear Generating

Plant," developed

by HughesAssociates

for consideration.

Page 3 of 3

Enclosure

2Monticello

Nuclear Generating

Plant"External

Flooding

Evaluation

for Monticello

Nuclear Generating

Plant"ISMLI16012.000-1

Hughes Associates

62 Pages Follow

.IHUGHESEASSOCIATES

ENGINEERS

CONSULTANTS

SCIENTISTS

External

Flooding

Evaluation

for Monticello

Nuclear Generating

Plant1SML16012.000-1

Prepared

for:Xcel EnergyProject Number: 1SML16012.000

Project Title: Monticello

External

Flooding

SDPRevision:

1Name DatePreparer:

Erin Collins/Paul

Amico/Suzanne

Loyd 7/8/2013~ ~" Erin P. Collins2013.07.082018:01

-04-00-Reviewer:

Pierre Macheret

7/8/2013P.",: 2"13 007 .M0 1-. o U.Review Method Design Review E] Alternate

Calculation

E]Approved

by: Francisco

Joglar Francisco

Joglar. ,. 7/8/2013N. I l: "013.07-

ISML-16012.000-1

Table of ContentsTABLE OF CONTENTS1.0 INTRODUCTION

..................................................................................................

12.0 REFERENCES

.................................................................................................

23.0 METHODOLOGY

and analysis

........................................................................

43.1 Event Tree Analysis

.............................................................................

43.1.1 Evaluation

of Flood Frequency

...................................................

43.1.2 Early W arning Probability

...........................................................

73.1.3 Protection

of the Reactor Building

...............................................

73.1.4 Manual Local Operation

of RCIC and the Hard Pipe Vent ..........

84.0 CONCLUSIONS

.............................................................................................

15APPENDICES

TABLE OF CONTENTS

...................................................................

16Revision

I Page ii

1SML16012.000-1

Introduction

1.0 INTRODUCTION

This analysis

was developed

to address the significance

of a finding that was received

by theMonticello

Nuclear Generating

Plant (MNGP) associated

with External

Flooding

hazards.

ThisSDP is summarized

in NRC Letter EA-13-096

(Reference

5). The analysis

quantifies

the coredamage frequency

associated

with a flood exceeding

930' at MNGP.Revision

2 Page 1Revision

2Page1I

ISML16012.000-1

References

2.0 REFERENCES

1. Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at the Monticello

Nuclear Generating

Station based on At-Site Data for Spring and Summer Annual PeakFloods, David S. Bowles and Sanjay S. Chauhan,

RAC Engineers

and Economists,

June28, 2013.2. Hydrologic

Atlas of Minnesota,

Division

of Water, Department

of Conservation,

State ofMinnesota,

1959.3. US Geological

Survey, Guidelines

for Determining

Flood Flow Frequency,

Bulletin#17B, Hydrology

Subcommittee,

Interagency

Committee

on Water Data, Office of WaterData Coordination,

1982.4. A Framework

for Characterization

of Extreme Floods for Dam Safety Risk Assessments,

Robert E. Swain, David Bowles and Dean Ostenea,

Proceedings

of the 1998 USCOLDAnnual Lecture,

Buffalo,

New York, August 1998.5. NRC Letter EA-13-096,

Subject:

Monticello

Nuclear Generating

Plant, NRC Inspection

Report 05000263/2013008;

Preliminary

Yellow Finding,

United States NuclearRegulatory

Commission,

Region III, 11 June 2013.6. A Preliminary

Approach

to Human Reliability

Analysis

for External

Events with a Focuson Seismic,

EPRI 1025294,

EPRI, December

2012.7. Interim Staff Guidance

for Performing

the Integrated

Assessment

for External

Flooding,

Appendix

C: Evaluation

of Manual Actions,

JLD-ISG-2012-05,

Revision

0, U.S. NRCJapan Lessons-Learned

Project Directorate,

November

30, 2012.8. Job Performance

Measure JPM-A.8-05.01-001,

Manual Operation

of RCIC, Rev. 0, TaskNumber NL217.108

-Operation

of RCIC without Electric

Power, 3 timed exercises

performed

17 June 2013.9. Job Performance

Measure JPM-A.8-05.08.001,

Manually

Open Containment

Vent Lines,Rev. 0, Task Number FB008.007,

4 timed exercises

performed

17 June 2013.10. Hughes Associates

Record of Correspondence,

RCIC Manual Operation

e-mails withXcel Energy during June -July 2013, Hughes Associates,

Baltimore,

MD, 7 July 2013.11. Hughes Associates

Record of Correspondence,

Hard Pipe Vent Manual Operation

e-mails with Xcel Energy during June 2013, Hughes Associates,

Baltimore,

MD, 7 July2013.12. Monticello

Procedures:

" 8900, OPERATION

OF RCIC WITHOUT ELECTRIC

POWER, Revision

2" C.5-1 100, RPV CONTROL flowchart,

Revision

11" C.5-1200,

PRIMARY CONTAINMENT

CONTROL flowchart,

Revision

16" C.5-3505-A,

Revision

10* A.6, ACTS OF NATURE, Revision

43* A.8-05.08,

Manually

Open Containment

Vent Lines, Revision

1Revision

2Page 2

ISML16012.000-1

References

0 A.8-05.01,

Manual Operation

of RCIC, Revision

213. The EPRI HRA Calculator

Software

Users Manual, Version 4.21, EPRI, Palo Alto, CA,and Scientech,

a Curtiss-Wright

Flow Control company,

Tukwila,

WA.14. NUREG/CR-1278,

Handbook

of Human Reliability

Analysis

with Emphasis

on NuclearPower Plant Applications,

(THERP) Swain, A.D. and Guttman,

H.E., August 1983.15. NUREG-1921,

EPRI/NRC-RES

Fire Human Reliability

Analysis

Guidelines,

DraftReport for Public Review and Comment,

November

2009.16. NUREG- 1852, Demonstrating

the Feasibility

and Reliability

of Operator

Manual Actionsin Response

to Fire, October 2007.17. NUREG/CR-1278,

Handbook

of Human Reliability

Analysis

with Emphasis

on NuclearPower Plant Applications,

(THERP) Swain, A.D. and Guttman,

H.E., August 1983.18. Whaley, A.M, Kelly, D.L, Boring, R.L. and Galyean,

W.J, "SPAR-H Step-by-Step

Guidance",

INL/EXT-10-18533,

Revision

2, Idaho National

Laboratory,

Risk,Reliability,

and NRC Programs

Department,

Idaho Falls, Idaho, May 2011.Revision

2 Page 3Revision

2Page 3

1SML16012.000-1

Methodology

and Analysis3.0 METHODOLOGY

AND ANALYSIS3.1 Event Tree AnalysisEvent trees were developed

to calculate

the core damage frequency

(CDF) associated

withExternal

Floods. Event trees were developed

for both a best estimate

case as well as sensitivity

cases. Floods were evaluated

at three particular

heights -917' but less than 930', 930' but lessthan 935', and greater than or equal to 935'. The first flood height range (917' to 930') wasevaluated

for frequency

but was not deemed feasible

to cause core damage since much of theplant's critical

safety equipment

is not threatened

unless flood levels exceed the 930' elevation.

The following

sections

describe

the development

of the flood frequency

and conditional

probabilities

of the other events that may lead to core damage events.Additionally,

it is agreed that, as stated in the NRC letter EA- 13-96 (Reference

5), the evaluation

of large early release frequency

(LERF) risk is assumed to be no more significant

than CDF-based risk; therefore,

no evaluation

of LERF was performed

for this analysis.

3.1.1 Evaluation

of Flood Frequency

MNGP teamed with industry

experts to evaluate

the frequency

of major floods in detail. Dr.David Bowles was the lead author for the flood frequency

analysis.

To ensure that the floodfrequency

of exceedance

analysis

was sound, an independent

review of the analysis

wasperformed

as part of this analysis

(Reference

1). The review resulted

in some recommendations

for improvement

that were incorporated

by Dr. Bowles and his team prior to the development

ofthe event trees that are included

in this report. This section documents

the results of that finalflood frequency

analysis.

The frequencies

of Mississippi

River floods at MNGP for flood heights of 917', 930' and 935'were estimated

using stream-flow

data from 1970 -2012. This estimation

is described

in"Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at the MNGP based onAt-Site Data for Spring and Summer Annual Peak Floods" (Reference

1).Separate

flood frequency

relationships

were developed

for spring and summer annual peakfloods based on the Hydrologic

Atlas of Minnesota

(Reference

2) and an examination

of flowrecords.a) Spring annual peak floods generally

peaked in the period March to May, but if it wasclear from examination

of the hydrograph

that a snow melt flood event peaked in Junethen that peak was used.b) Summer annual peak floods generally

peaked in June to October,

but flood peaks in Juneassociated

with snow melts were excluded

since they were assigned

to spring floods.Frequencies

were estimated

based on extrapolation

of flood frequency

relationships

developed

from at-site flow data. The mean daily annual peak stages were obtained

for spring and summerannual peak floods. The daily annual peak stages were converted

to daily annual peak flows forspring and summer floods using a combined

rating curve described

in Reference

1. TheExpected

Moments Algorithm

(PeakfqSA)

was applied using methodology

described

in thecurrent draft of the upcoming

revision

to USGS Bulletin

17B (Reference

3). The EMA softwareprovided

annual exceedance

probability

(AEP) estimates

down to 1 in 10,000/yr.

Annual peakdischarge

was plotted on a Log scale and AEPs on a z-variate

scale (corresponding

to a NormalRevision

2Page 4

ISML16012.000-1

Methodology

and Analysisprobability

distribution)

to allow AEPs lower than 1 in 10,000/yr

to be estimated

by linearextrapolation.

The resulting

median estimates

for spring and summer floods at 917', 930' and 935' river heightswere as follows:Table 3-1 Median Flood Frequency

Estimates

at MNGP Site (Ref. 1)Elevation

917' Elevation

930' Elevation

935'Spring Floods 6.3E-3/yr

<lE-9/yr

<1E-9/yrSummer Floods 1.7E-3/yr

<1E-9/yr

<1E-9/yrA full family of flood hazard curves is provided

in the Bowles report. There is a substantial

amount of aleatory

uncertainty

in the development

of these curves, resulting

in very wideconfidence

bounds as can be seen in the figures and tables in the report, especially

for the floodlevels of interest.

For example,

the elevation

917' 95th percentile

estimate

is 3.4E-2/yr

and the5th percentile

estimate

is 5.9E-7/yr

for spring floods. This is indicative

of the limited dataavailable

in the 1970 -2012 year period. In addition,

not all potential

flood influences

were seenin the 42 years of experience.

Moreover,

there is additional

epistemic

uncertainty

due tosimplifications

used in the modeling

process,

For example,

regional

flood impacts were notconsidered,

nor were the potential

effect of ice blockage

or changes in flood protective

featuressuch as dikes along the river. To address these as well as other potential

flood contributors,

themean hazard for the purposes

of quantification

will be represented

by the 84th percentile,

whichis the median plus one standard

deviation

for a lognormal

form distribution.

This is a commonpractice

to provide margin to account for the uncertainties.

As a further consideration,

there is a general consensus

that the practical

limit on AEPextrapolation

is no better than 1.OE-5/yr

no matter how much information,

including

information

on paleofloods,

is available

(see for example,

"A Framework

for Characterization

of ExtremeFloods for Dam Safety Risk Assessments"

(Ref. 4). It is believed

that all of these factors wouldtend to increase

the estimated

frequency

of floodings.

Some of these uncertainties

could beaddressed

in a more detailed

analysis,

such as a Monte Carlo rainfall-runoff

approach,

but others,such as the potential

effect of ice blockage,

would remain. In the case of this evaluation,

thereadditional

factors will be addressed

by way of a sensitivity

study, discussed

at the end of thissection.The 84th percentile

is the median plus one standard

deviation,

which is a common "marginvalue" that addresses

uncertainty

without being overly conservative.

The margin is to cover thewide statistical

uncertainty

in the distribution

plus the modeling

uncertainty

that comes fromsome of the issues we discussed,

such as not considering

ice blockage

or other downstream

flowbottlenecks,

only considering

site data, and not actually

modeling

the flows and performing

asimulation.

This results in the following

flood frequency

estimates:

The results presented

in the Bowles report support the use of the 84th %-tile as a reasonable

conservative,

but not overly conservative,

representation

of the mean. A manually

generated

approximation

of the mean (described

in Ref. 1 -the code used cannot itself generate

a mean) isshown to be in the range of the 70th percentile,

plus or minus about 10 percentile.

This is theresult of the aleatory

uncertainty.

The use of the 84th percentile

provides

some additional

Revision

2Page 5

1SM L16012.000-1

Methodology

and Analysismargin to account for epistemic

uncertainty

and give confidence

that the "true mean" is notlikely to exceed this value.Treating

the 84th percentile

as the mean, the process of developing

the initiating

eventfrequencies

is straightforward.

It is typical in external

hazard PRA to create initiating

events bydiscretizing

the hazard curve. Because for external

flooding

there are a clear series of floodlevels of concern,

the selection

of the initiating

events is clear. For MNGP, the levels of concernare 917', 930', and 935', with the exceedance

of each level causing the same impact on plantsystems until the flood exceeds the next level of concern.

Therefore

the initiating

events can bedefined as follows:" IE1 -level >917' and <930'" IE2 -level >930' and <935'" IE3 -level >935'Using the 84th percentile

values to represent

the mean, we get exceedance

probabilities

for eachlevel of concern as follows:Table 3-2 84th Percentile

Exceedance

Frequencies

(Used as Means) (Ref. 1)Elevation

917' Elevation

930' Elevation

935'Spring Floods. 2.0E-02/yr

7.5E-08/yr

<1E-09/yr

Summer Floods 8.8E-03/yr

8.8E-06/yr

9.7E-07/yr

Total 2.9E-021yr

8.9E-061yr

9.7E-071yr

The values for spring and summer can be summed because they are each calculated

on a per-calendar-year

basis and because we are using these values to represent

the "true mean" of thedistribution,

albeit conservatively.

Because these values are exceedance

(i.e., the frequency

that a flood exceeds a specified

level),the way to determine

the frequency

of a flood in a given range is to subtract

the frequency

ofexceedance

of the upper flood in the range from the frequency

of exceedance

of the lower floodin the range.One event tree was developed

to account for all floods that were greater than 930' (including

those greater than 935'). The frequency

of exceedance

for the 930' floods was used and aconditional

probability

was applied to account for the floods within the 930' to 935' range andfloods greater than 935'. The frequency

shown as IE2 in Table 3-3 was used in the event tree.The conditional

probability

that the flood was indeed greater than 935' was then applied in asubsequent

branch to determine

the CDF for sequences

specific

to floods greater than 935'(value of 0.109). Table 3-3 below shows the initiating

event frequencies

used for thisassessment.

Revision

2 Page 6Revision

2Page 6

1 SML16012.000-1

Methodology

and AnalysisI SMLI 6012.000-1

Methodology

and AnalysisTable 3-3 Best Estimate

Initiating

Event Frequencies

Initiating

Event Initiating

Event Frequency

IEl1 2.9E-02/yr

IE22 8.90E-06/yr

Not deemed feasible

for core damage sequences.

Not evaluated

for this analysis.

2This frequency

Is represented

in the event tree along with a conditional

probability

that the flood will be >935' toevaluate

the correct range of flood heights.As discussed

earlier,

there is the question

of the practical

limit of extrapolation

of flooding

data.Therefore,

in addition

to the initiating

event frequencies

presented

above, a sensitivity

analysiswas performed

limiting

the flood frequency

to no less than 1.OE-5/yr,

consistent

with theconsensus

reached in Ref. 4 concerning

the limit of credible

extrapolation

for annual floodexceedance

probability.

Table 3-4 Sensitivity

Case Initiating

Event Frequencies

Initiating

Event Initiating

Event Frequency

IE1 2.9E-02/yr

IE22 2.OE-05/yr

'Not deemed feasible

for core damage sequences.

Not evaluated

for this analysis.

2This frequency

is represented

In the event tree along with a conditional

probability

that the flood will be >935' toevaluate

the correct range of flood heights.It could be argued that the limit should apply across the 930' events (i.e., that the hazard curvegoes flat at 1E-5/yr)

and that it is sufficient

to ignore the 935' event (because

F(IE2930<=1v1<935)

=fexceed(930)

-fcxceed(935)

= 0) and simply evaluate

the 930' flood at a frequency

of lE-5/yr.

Sincethis is a sensitivity

case and not the best estimate,

it was decided to assign 2E-5/yr to IE2 forpurposes

of providing

the sensitivity

insights

and use a conditional

probability

of 0.5 to accountfor floods that are >935'.In the event trees (shown in Appendix

A), the flood frequencies

are represented

by the headings"EXTERNAL

FLOOD >930"' and "<935.' for IE2 events. In addition,

event trees used forsensitivities

have similar headings.

3.1.2 Early Warning Probability

Although

it was considered

qualitatively,

there was no basis determined

for giving credit to thepotential

for early warning of a flood >930'. The event tree model shows a failure probability

of1.0 for this node.3.1.3 Protection

of the Reactor BuildingIn the event of a major flood, such as those evaluated

in this analysis,

MNGP plans to build a binwall barrier that will protect the site from the high flood waters. If the bin wall levee issuccessful,

the safety equipment

needed to prevent core damage will be protected,

providing

defense in depth for each required

critical

safety function.

Simple flood protection

measuresmay be taken to protect the reactor building

from floodwater,

even if the bin wall levee fails.These measures

to protect the reactor building

do not need to be in place until the flood heightapproaches

the 935' elevation.

A conservative

value of 0.11 is assigned,

consistent

with the ES-13-096 NRC letter (Reference

5), to the failure probability

of protecting

the reactor building.

Revision

2 Page 7Revision

2Page 7

1SML16012.000-1

Methodology

and Analysis3.1.4 Manual Local Operation

of RCIC and the Hard Pipe VentMNGP requested

Hughes Associates

to conduct a detailed

human reliability

analysis

(HRA) toestimate

human error probabilities

for operator

manual actions to prevent core damage throughthe use of RCIC as a high pressure

injection

source and the Hard Pipe Vent (HPV) to removedecay heat from containment.

This detailed

HRA was based upon thermal/hydraulics

analyses,

battery depletion

calculations,

several Job Performance

Measure (JPM) exercises

for the specificprocedure

A8.05.01

and A8.05.01

actions (References

8 and 9) considering

flood and StationBlackout

(SBO) conditions,

and discussions

with Operations

and PRA staff (References

10 and11). This section documents

the initial conditions

assumed,

the analytical

process,

and theresults of the detailed

HRA. A comparison

between the detailed

analysis

results and thoseobtained

using SPAR-H is also provided

as a sensitivity

evaluation.

3.1.4.1 Initial Conditions

for the Operator

Manual ActionsOperations

staff at MNGP provided

the following

information

on the conditions

that would beevolving

leading up to the need for the postulated

operator

manual actions evaluated

in thisHRA.The A.6 Procedure,

"Acts of Nature" (Reference

12) that addresses

External

Flooding

directs de-energizing

the 115 KV, 230 KV and 345 KV substations

for flood levels in excess of the 930'elevation.

In the case where the flood level is above 930' this would lead to a loss of offsitepower and reliance

on the EDGs. Since the normal long term fuel oil storage (Tank T-44) for theEDG's is not evaluated

to survive flood levels above 932' elevation,

and alternate

fuel oil makeupmethods are not pre-prescribed

to support the EDG's, long term EDG operation

is not easilydefensible

utilizing

existing

procedures.

Additionally,

there are several penetrations

in the PlantAdministration

Building

that would make positive

flood proofing

of the building

difficult,

leaving three of the four station batteries

vulnerable

to flooding.

The flooding

engineer

provides

daily updates to the station on high river water levels including

potentials

to rise above any trigger points from the A.6 procedure.

At this point, heightened

awareness

of the potential

for flooding

is implemented.

When river level exceeds 921 feet an evaluation

of EALs would be performed.

If visible damagehas occurred

due to flood water rising greater than 921 feet, then an Alert per EAL HA1.6 wouldbe declared.

Prior to the river reaching

these levels, operators

would be walking down the procedures

foralternate

methods to vent primary containment

and operate RCIC remotely.

This would involvestaging of equipment

in the torus area to open the Hard Pipe Vent and verification

thatequipment

is properly

staged to operate RCIC remotely.

As water level reached the 930' elevations,

Operations

would prepare for isolation

of off-sitepower and loading essential

loads onto the emergency

diesel generators

as needed to conservefuel. Only a single EDG is required

for shutdown

cooling and inventory

makeup. Operators

would be in the EDG rooms, intake and other critical

areas ensuring

no water intrusion

andwould be pumping water out of the room as needed. Also the battery rooms in the PAB wouldbe of concern due to the high flood levels. At this point operators

would be briefed to be readyto operate RCIC without electrical

power as necessary.

Revision

2Page 8

1 SML16012.000-1

Methodology

and AnalysisThe portable

diesel fire pumps would also be staged at higher locations

with hoses stagedthrough higher elevations

of the buildings

to support alternate

RPV makeup.Operators

would be dispatched

with I&C technicians

to the 962' elevation

of the reactor buildingto install the temporary

level indication

per procedure

A.8-05.01.

This would allow for alternate

level indication

to be available

in the event that the batteries

are lost.In the response

scenario

postulated

for the performance

of the operator

manual actions evaluated

in this HRA, EDGs and batteries

are not available.

Shutdown

cooling,

HPCI, and RCIC are notavailable

from normal electrical

means. RCIC is available

for manual operation.

Operators

would have temporary

level indication

set up in the reactor building.

Pressureindication

is available

in the direct area of the level transmitters.

The building

is dark and mostlikely there is water in the basement

of the reactor building.

Additional

portable

lights areavailable

to assist with lighting

and boots staged for higher water. The operators

would utilizeprocedure

A.8-05.01

to un-latch

the governor

from the remote servo linkage and throttle

steamflow to RCIC to start the turbine rolling while coordinating

with operators

monitoring

waterlevel and reactor pressure.

Upon reaching

the high end of the level band the operators

wouldthrottle

closed the steam admission

valve and await direction

to re-start

RCIC. Local operation

of RCIC is demonstrated

each refueling

outage during the over speed test. Operation

of acoupled turbine run is less complex because the turbine is easier to control with a load.3.1.4.2 Detailed

HRAThe human error probabilities

(HEPs) for manual local operation

of RCIC and the Hard PipeVent during an extreme flooding

and SBO event have been developed

in detail utilizing

theEPRI HRA Calculator

(Reference

13). Event RCICSBOFLOOD

(Fail to manually

operateRCIC during SBO and extreme flooding

conditions),

and event HPVSBOFLOOD

(Fail tooperate the HPV using N2 bottles to provide containment

heat removal during SBO/Flood)

havevalues of 9.3E-02 and 1.3 E-02 respectively,

for a combined

value of 1.06E-01.

The HRA Calculator

reports for these events, which provide a detailed

basis for these HEPestimates,

are presented

in Appendix

A. Section A. 1 documents

RCICSBOFLOOD

andSection A.2 documents

HPVSBOFLOOD.

The cognitive

portion of these HEPs was developed

using the Cause Based Decision

TreeMethod (CBDTM) (Reference

13) and the execution

portion utilized

the Technique

for HumanError Rate Prediction

(THERP) (Reference

14). These methods are commonly

used in internalevents PRA, have been cited in the EPRI/NRC-RES

Fire HRA Guidelines,

NUREG-1921

(Reference

15) and applied in many fire PRAs, and are also cited in the following

reference:

  • A Preliminary

Approach

to Human Reliability

Analysis

for External

Events with a Focuson Seismic,

EPRI 1025294,

EPRI, December

2012.NUREG-1921

and THERP are also listed as references

to the following

document:

  • Interim Staff Guidance

for Performing

the Integrated

Assessment

for External

Flooding,

Appendix

C: Evaluation

of Manual Actions,

JLD-ISG-2012-05,

Revision

0, U.S. NRCJapan Lessons-Learned

Project Directorate,

November

30, 2012.Revision

2 Page 9Revision

2Page 9

ISML16012.000-1

Methodology

and AnalysisAppendix

C of the ISG on External

Flooding

concentrates

primarily

on demonstrating

thefeasibility

and reliability

of the manual actions consistent

with NUREG-1852

(Reference

16),"Demonstrating

the Feasibility

and Reliability

of Operator

Manual Actions in Response

to Fire."One of the key variables

in determining

feasibility

of operator

manual actions is timing. Asstated in the ISG, "For an action to be feasible,

the time available

must be greater than the timerequired

when using bounding

values that account for estimation

uncertainty

and humanperformance

variability."

In order to assess this feasibility,

the following

process isrecommended

in section C.3.2.4 Calculate

Time Margin:"The licensee

should calculate

the time margin available

for the action using the values for timeavailable

and time required

that have been developed

for the analysis."

The time margin formula provided

is:[(Tsw-Tdelay)--(Tcog+Texe))

Time Margin = (Tcog.Texe)

X 100%The terms of the equation

are defined as follows:Tdelay = time delay, or the duration

of time it takes for the cue to become available

that indicates

that the action will be necessary

(assumes

that action will not be taken in the absence of a cue);Tsw = the time window within which the action must be performed

to achieve its objective;

Tcog = cognition

time, consisting

of detection,

diagnosis,

and decision-making;

andTexe = execution

time including

travel, collection

of tools, donning of PPE, and manipulation

ofrelevant

equipment.

The HEP calculations

performed

for the RCIC and HPV manual actions involved

the estimation

of the time parameters

cited in the Time Margin formula.

These times are based uponthermal/hydraulics

analyses,

battery depletion

calculations,

several Job Performance

Measure(JPM) exercises

for the specific

proceduralized

actions and considering

flood and SBOconditions,

and discussions

with Operations

and PRA staff.Using this information,

the time margin for these two events is calculated

as:Table 3-5 Time Margin for HFEsTimes (in minutes)

RCIC HPVTsw 478.2 900Tdelay 345 330Tcog 10 10Texe 80 45Time Margin 48% 936%The HEP timing estimates

therefore

meet the criteria

that "using the calculation

under C.3.2.4,the margin must be a positive

percent value for an action to be deemed feasible."

Revision

2Page 10

1SML16012.000-1

Methodology

and AnalysisThe External

Flooding

ISG also recommends

that estimates

of time available

and time requiredshould account for sources of uncertainty

and human performance

variability.

The timingestimates

shown above are already believed

to be conservative.

For example,

the Tdelay of 345min for the RCIC event is based on 5.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> until RCIC battery depletion.

This can beconsidered

conservative

since, in reality,

it is likely that an action would be taken before waitingfor battery depletion.

For the Texe values, the highest observed

time in the JPM trials was usedfor the RCIC case and further time was added for transit time for actions in various locations.

Forthe HPV case, the Texe value was also based on JPM trial data and the results above show thatuncertainties

are covered by a significant

time margin.In addition

to feasibility,

the reliability

of the actions was evaluated

through the detailed

HRACalculator

analysis

used to quantify

HEPs.Section C4 of the ISG says that for an action to be deemed reliable,

"sufficient

margin shouldexist between the time available

for the action and the time required

to complete

it. This marginshould account for: (1) limitations

of the analysis

(e.g., failure to identify

factors that may delayor complicate

performance

of the manual action);

and (2) the potential

for workload,

timepressure

and stress conditions

to create a non-negligible

likelihood

for errors in taskcompletion...

A simplified

alternative

criterion

for determining

if the margin is adequate

to deeman action as reliable

is to establish

that the margin is not less than 100%. Such a margin may bejustified

when recovery

from an error in performing

the action could be accomplished

byrestarting

the task from the beginning."

As shown above, the time margin for the HPV manual action is greater than 100% and the timemargin for the RCIC manual action is estimated

at around 50%. The evaluation

of PRA andOperations

staff in performing

the JPMs for these actions was that there would be 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> ormore to perform the procedures,

allowing

several opportunities

to troubleshoot

and/or re-perform

steps if necessary.

In addition,

based on the HEP quantification,

the combined

probability

for theRCIC and HPV actions is estimated

to have a success rate of 89%. A sensitivity

study wasperformed

using SPAR-H estimates

to evaluate

the effect of reliability

uncertainty.

Regarding

the evaluation

of factors such as workload

and stress that could complicate

taskperformance,

performance

Shaping Factors (PSFs) were considered

for feasibility

and addressed

in the assessment

of reliability

of the operator

manual actions.The following

table discusses

each of the PSF categories

cited in Appendix

C of the ISG, theissues related to the RCIC and HPV manual actions and how they were addressed

in thequalitative

and quantitative

analysis

of these human failure events.Revision

2 Page 11Revision

2Page 11

1SML16012.000-1

Methodology

and AnalysisTable 3-6 Performance

Shaping Factors for Human Failure EventsPerformance

Shaping Factors Specific

Considerations

for RCIC and HPV Events under SBO and(PSFs) Flooding

Conditions

Cues Cues not only were provided

by the Emergency

Operating

Procedure

flowcharts

for RPV Level and Containment

Pressure

and supporting

procedure,

but would be expected

to be provided

by the Emergency

Response

Organization

staff and STA. It is expected

that daily meetingswould be held to assess the plant situation

considering

the long termeffects of flooding

and SBO and plans would be made to implement

theRCIC and HPV actions.

The decision

to perform these actions wouldtherefore

be made by ERO and STA and the Shift Supervisor

would givethe direction

to operations

staff.Indications

Due to the Station Blackout,

impacts to the normal set of indications

wereexpected

and these effects were implemented

in the CBDTM module ofthe HRA Calculator

consistent

with the methods recommended

inNUREG-1921,

Appendix

B as well as in the Execution

PSFs and Stressmodule. In addition,

the "Degree of Clarity of Cues & Indications"

wasdegraded

from "Very Good" to "Poor".Complexity

of the Required

Action The response

is considered

to be Complex due to the flooding

and SBOimpacts to lighting

and accessibility.

The procedure

steps of the actionsthat are required

and that were evaluated

in the timed Job Performance

Measures

(JPMs) specifically

performed

for these tasks are listed in theExecution

Unrecovered

module of HRA Calculator.

Special Equipment

Flashlights,

headlamps

and boots were considered

necessary

by Trainingwhen the JPMs were performed

for these tasks, and are reflected

in thetiming estimates

for Tm and in the Execution

PSFs Special Requirements

by indicating

that Tools, Parts and Clothing

were required

and available.

Human-System

Interfaces

The interfaces

with the system will be similar,

but with impacts due to theSBO and flooding

in terms of indications

and lighting.

For the RCIC task,a hand-held

reactor level monitor is installed

and used by I&C technicians

to monitor the parameter.

These steps of the procedure

were specifically

included

in the Execution

portion of the RCIC action quantification.

TheHPV task involves

the use of air cylinders

and these steps were alsoincluded

in the Execution

portion of the quantification.

Revision

2 Page 12Revision

2Page 12

ISMLI16012.000-1

Methodology

and AnalysisTable 3-6 Performance

Shaping Factors for Human Failure EventsPerformance

Shaping Factors Specific

Considerations

for RCIC and HPV Events under SBO and(PSFs) Flooding

Conditions

Procedures

Multiple

procedures

provide for operation

of the RCIC System without theavailability

of AC or DC power. They address the lighting

and ventilation

limitations

that accompany

a SBO, and provide for alternate

means ofmonitoring

reactor water level/pressure,

controlling

turbine speed,assuring

adequate

water source is available

and accommodating

thecondensate

from the turbine condenser.

  • Procedure

8900 (Operation

of RCIC without Electric

Power)* Procedure

C.4-L; Part F (Response

to Security

Threats;

Initiate

Injection

to the RPV with RCIC)* Procedure

A.8-05.01

(Manual Operation

of RCIC)* Procedure

B.08.09-05.H.4

(Condensate

Storage System -FillingCondensate

Storage Tanks from Alternate

Source)-Procedure

A.8-05.05

(Makeup to CST)Any of the following

procedures

provide for operation

of the HPV withoutthe need for normal support systems including

electric

power andpneumatic

supplies.

All necessary

equipment

to perform this function

isspecifically

manufactured

and pre-staged

to allow opening the HPVvalves.-Procedure

B.04.01-05.H.2

(Primary

Containment

System Operation

-Alternate

N2 Supply for Operating

AO-4539 and AO-4540)-Procedure

C.5-3505;

Part A (Venting

Primary Containment;

VentThrough the Hard Pipe Vent)-Procedure

A.8-05.08

(Manually

Open Containment

Vent Lines)The relevant

procedures

were reviewed,

cues and operator

action stepswere itemized

in the quantification

and were evaluated

using multipleiterations

of the timed JPMs.Training

and Experience

The RCIC and HPV capabilities

are included

in various aspects ofperiodic

operations

training.

Training

materials

and mockup trainingdevices related to these activities

include:" JPM -B.02.03-005

(Reset RCIC Overspeed

Trip)" Training

mockup of the RCIC Turbine Trip Throttle

Valve (MO-2080)

" Lesson Plan MT-ILT-EOP-002L

(RPV Control)" Lesson Plan MT-NLO-12C-002L

(Emergency

Operating

Procedures

Overview)

  • Lesson Plan MT-NLO-EOP-001

L (EOPs for NLOs (Turbine

Building))

  • Lesson Plan MT-OPS-FB-004L

(Level 4 -Extensive

Damage Mitigation

Guidelines)

-Lesson Plan M-8107L-003

(RCIC)Additionally,

control of RCIC, using the RCIC MO-2080 Turbine TripThrottle

Valve is actually

performed

during the startup from each refueling

outage, in the performance

of procedure

1056 (RCICI Turbine Overspeed

Trip Test).Operator

training,

procedure

adequacy,

and equipment

readiness

regarding

use of these mitigation

measures

has been reviewed

by theNRC as part of the B.5.b and Fukushima

Flex response

inspections

andbeen determined

to be acceptable.

  • ML1 1235A897

(NRC Fire/B.5.b

Inspection

Report; 8/23/11)* ML1 11320400

(NRC Temporary

Instruction

2515/183;

5/13/11).

Perceived

Workload,

Pressure

Under the quantification

Execution

PSFs, Workload

has been assessedand Stress as High and PSFs of Negative,

so the overall stress is assessed

as High.Revision

2 Page 13Revision

2Page 13

ISMLI16012.000-1

Methodology

and AnalysisTable 3-6 Performance

Shaping Factors for Human Failure EventsPerformance

Shaping Factors Specific

Considerations

for RCIC and HPV Events under SBO and(PSFs) Flooding

Conditions

Environmental

Factors The environment

would be consistent

with SBO (hot, dark, damp) andsome Reactor Building

flooding

requiring

boots. These were theconditions

evaluated

during the timed JPMs and are addressed

in thequantification

under Execution

PSFs for Lighting,

Heat/Humidity

andAtmosphere.

Special Fitness Issues No special fitness issues were identified

although

the performance

ofmultiple

trials of the JPMs is considered

to address the variability

inpersonnel

fitness.Staffing

Operations

staffing

to perform the procedures

would be optimal (severaloperators

assigned

as desired to each procedure).

Discussions

were heldto evaluate

whether there would be dependencies

in staffing

between theRCIC and HPV actions and it was considered

that due to the different

timeframes,

that the actions and staffing

would be separate.

Communications

Under SBO conditions

the use of radio and walkie talkies would beexpected

to allow communications

to be maintained

between the MainControl Room and the I&C Technicians

and the staff performing

the keyactions.Accessibility

The Equipment

Accessibility

is evaluated

as "With Difficulty"

due toreactor building

lighting

and flooding

issues. The quantification

Execution

PSFs indicates

this and these issues were addressed

during the JPMtiming sessions.

A sensitivity

analysis

was also performed

by developing

human error probabilities

(HEPs) formanual local operation

of RCIC and the Hard Pipe Vent during an extreme flooding

and SBOevent utilizing

the SPAR-H module of the EPRI HRA Calculator

and recommended

practices

from the Idaho National

Laboratory

step-by-step

SPAR-H guidance

(Reference

17). UsingSPAR-H, event RCICSBOFLOOD

(Fail to manually

operate RCIC during SBO and extremeflooding

conditions),

and event HPVSBO FLOOD (Fail to operate the HPV using N2 bottles toprovide containment

heat removal during SBO/Flood)

have values of 1.4E-01 and 5.5E-02respectively,

for a combined

value of 1.95E-01.

The HRA calculator

reports associated

with these HEPs can be found in sections

A.3 and A.4 ofAppendix

A.Revision

2 Page 14Revision

2Page 14

ISML16012.000-1

Conclusions

4.0 CONCLUSIONS

The results of the analysis

are shown in Table 4-1. This table includes

the results of both the bestestimate

quantification

and the sensitivities

that were performed

in support of this analysis.

The ACDF represents

the difference

between the best-estimate

CDF and the baseline

CDF. Thebaseline

CDF is the CDF without the performance

deficiency.

The best-estimate

CDF is theresult of the event tree calculations

shown in Appendix

A. The exposure

time represents

theperiod of time the plant was exposed to the performance

deficiency.

This time period was fromFebruary

29, 2012 to February,

15, 2013 resulting

in an exposure

time of 352 days or 0.964years. The failure to build construct

a levee is assumed to be 0.11 (consistent

with theprobability

assumed by the NRC). Therefore,

the baseline

CDF is calculated

by multiplying

thebest-estimate

CDF by 0.11. ACDF is equal to the best-estimate

minus the baseline,

thus:= best-estimate

-0.11 x best-estimate

= (1-0.11)

x best-estimate

= 0.89 x best-estimate.

ACDP = exposure

x ACDF = 0.964 x 0.89 x best-estimate.

Table 4-1 Results of Event Tree Quantification

Sensitivity

1: Sensitivity

2:NRC Case Nominal,

Bounding

Flood SPAR-H HRAFrequency

Probabilities

CD Seq 1 8.41 E-07 1.06E-06

1.55E-06CD Seq 2 9.15E-08

9.43E-07

1.68E-07CD Seq 3 1.07E-07

1.10E-06

1.07E-07CDF 4.20E-05

1.04E-06

3.10E-06

1.83E-06ACDF 3.60E-05

8.92E-07

2.66E-06

1.57E-06Significance

Yellow Green White WhiteThe results of this analysis

show that by a best-estimate

analysis,

the significance

of the floodingevent is Green. Two sensitivity

studies performed

to evaluate

the effects of sources ofuncertainty

show that the significance

of the flooding

could be characterized

as low to moderatesafety or security

significance

or 'White' using bounding

assumptions.

Revision

2 Page 15Revision

2Page 15

I SML16012.000-1

Appendices

APPENDICES

TABLE OF CONTENTSA. APPENDIX

A -HRA CALCULATOR

REPORTS ........................................

A-1A.1. RCICSBOFLOOD,

Fail to manually

operate RCIC during SBO andextrem e flooding

conditions

...............................................................

A-1A.2. HPVSBOFLOOD,

Fail to operate the HPV using N2 bottles to providecontainment

heat removal during SBO/Flood

.......................................

A-19A.3. RCICSBOFLOOD,

Fail to manually

operate RCIC during SBO andextreme flooding

conditions

(SPAR-H)

.................................................

A-31A.4. HPVSBOFLOOD,

Fail to operate the HPV using N2 bottles to providecontainment

heat removal during SBO/Flood

(SPAR-H)

......................

A-36B. APPENDIX

B -EVENT TREES ...................................................................

B-1Revision

2 Page 16Revision

2Page 16

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSA. APPENDIX

A -HRA CALCULATOR

REPORTSThe following

sections

document

the HRA Calculator

reports that support this analysis.

A.1. RCIC_SBOFLOOD,

Fail to manually

operate RCIC during SBO and extremeflooding

conditions

Basic Event Summary.%Plant Data File: ':FiledSize'

File Dated. IR1ecord.

DateMonticello

Ext 913408 07/02/13

07/02/13Flooding

SDPHRAJune2013.HRA':Nam ;-DateAnalyst Erin P. Collins,

Hughes 07/02/2013

Associates

Reviewer

John Spaargaren

& Pierre 07/02/2013

Macheret,

Hug hes Associates

Table 41: RCIC_SBOFLOOD

SUMMARY______________

~HEP,-Sumay

__Pcog Pexe Total HEP ErrorFactorMethod CBDTM THERP CBDTM + THERPWithout Recovery

2.9e-02 5.2e-01With Recovery

9.2e-04 9.2e-02 9.3e-02 5Initial Cue:RPV Water Level Below 9 in.Recovery

Cue:Before RPV level drops to -149 inchesCue Comments:

The cue for action is that the TSC and the Emergency

Director

have determined

that RCIC operation

isneeded. The Control Room Supervisor

(CRS) directs operator

to initiate

RCIC and inject into the RPVusing procedure

A.8-05.01,

Manual Operation

of RCIC, Part A, Placing RCIC in Service.Due to the SBO, it is assumed that there will be multiple

impacts to indications,

so the degree of clarityhas been set at "Poor".Deqree of Clarity of Cues & Indications:

PoorProcedures:

Cognitive:

C.5-1 100 (RPV CONTROL flowchart

(Monticello))

Revision:

11Execution:

A.8-05.01

(Manual Operation

of RCIC) Revision:

2Other: A.6 (ACTS OF NATURE (Monticello))

Revision:

43Other: 8900 (OPERATION

OF RCIC WITHOUT ELECTRIC

POWER (Monticello))

Revision:

2Revision

2 Page A-IRevision

2Page A-1

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCognitive

Procedure:

Step: LEVELInstruction:

Restore and maintain

RPV water level 9 to 48 in. using Preferred

Injection

SystemsProcedure

and Training

Notes:Three JPM trials were performed

emulating

the specific

external

flooding

conditions

of this scenario

on 18June 2013. Observations

were factored

into this analysis.

Procedure

A.8-05.01

-2.0 ENTRY CONDITIONS

This strategy

is entered when one or more of the following

conditions

are met:o As directed

from A.8-01.01

(Extensive

Damage Mitigation

Strategy

Overview)

o As directed

from A.8-03.01

(Initial

Response

Actions)o As directed

from 5790-110-01

(Monticello

Emergency

Management

Guideline)

-presume this is therelevant

case since ERF is staffed and will make the call on implementing

the procedure

Training:

Classroom,

Frequency:

0.5 per yearSimulator,

Frequency:

0.5 per yearJPM Procedure:

JPM-A.8-05-01-001

(Manual Operation

of RCIC) Revision:

0Identification

and Definition:

1. Letter to Region III SRA write-up,

8 April 2013Section G -HEP Associated

with Protecting

Plant Buildings

from 930' Elevation

FloodFor the case where the site is not protected

by a ring levee, but individual

buildings

/ equipment

areprotected

by flood barriers

as called out in the A.6 (Acts of Nature) procedure,

several redundant

optionsremain available

for protecting

critical

safety functions

related to injecting

water to the reactor,

maintaining

desired reactor pressure,

and removing

decay heat from containment.

The A.6 Procedure

[Acts of Nature that addresses

External

Flooding]

directs de-energizing

the 115 KV,230 KV and 345 KV substations

for flood levels in excess of the 930' elevation.

In the case where theflood level is above 930' this would lead to a loss of offsite power and reliance

on the EDGs. Since thenormal long term fuel oil storage (Tank T-44) for the EDG's is not evaluated

to survive flood levels above932' elevation,

and alternate

fuel oil makeup methods are not pre-prescribed

to support the EDG's, longterm EDG operation

is not easily defensible.

Additionally,

there are several penetrations

in the PlantAdministration

Building

that would make positive

flood proofing

of the building

difficult,

leaving three of thefour station batteries

vulnerable

to flooding.

2. PRA-MT-SY-RCIC,

Reactor Core Isolation

Cooling System Notebook,

Revision

3.0, December2012Table 3 -IE_LOOP (Loss Of Offsite Power Initiating

Event) Impact on RCIC System: A loss-of-offsite

power does not affect RCIC, provided

AC power remains available

to the Division

1 battery chargers.

Aloss of Feedwater

would result, and RCIC operation

would be automatically

actuated

when Low-LowLevel in the RPV is reached.Key Assumptions:

It is assumed that there will be sufficient

water and fuel supply for the equipment

needed in this scenariodespite the flooding

conditions

and considering

the long term nature of the flood, which may take as manyas 12 days to recede (from the Monticello

Design Basis documentation).

This means that CST level is assumed to be maintained

via a step in this HEP and is not quantified

separately.

Another key assumption

is that because the staffing

needed for this event is separate

from that used forthe Hard Pipe Vent human failure event, and the timeframe

for HPV is much longer, no dependency

between these events was evaluated

(in other words, the timing and staffing

were considered

as totallyseparate

events).Revision

2Page A-2

1SMIL160112.000-11

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSJPM-A.8-05.01-001

(Manual Operation

of RCIC) Rev. 0INITIAL CONDITIONS:

o Extreme flooding

has led to a Station Blackout

that has existed at Monticello

for the last 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.o Div. 1 250 VDC battery system has been depleted

and is not available.

o The plant was in Shutdown

Cooling until the station blackout

and has since been slowlyrepressurizing

due to heating up.o Current RPV pressure

is 75 psig-and

slowly rising.o Current RPV water level is -40" and very slowly lowering.

o The TSC and the Emergency

Director

have determined

that RCIC operation

is needed.o HPCI is inoperable.

o RCIC suction is from the CSTs.o RCIC operation

is required

to maintain

RPV level above TAF.o Approximately

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> ago Radiation

Protection

reported

-2" of water on the Rx Bldg basementfloor.o A second operator

will be performing

Part B, Set Up and Monitor of Rx Vessel with Fluke 707.o A third operator

will be maintaining

CST level using A.8-05.05,

Makeup to the CST, and verifying

valve status in the steam chase.INITIATING

CUES (IF APPLICABLE):

o The CRS directs you to initiate

RCIC and inject into the RPV using A.8-05.01,

Manual Operation

ofRCIC, Part A, Placing RCIC in Service.o Inform the CRS when RCIC is in service with discharge

pressure

at least 76 psig greater than reactorpressure..

RCIC local manual operation

Job Performance

Measure entry condition

assumptions,

Documented

in andexcerpted

from Hughes Associates

Record of Correspondence,

RCIC Manual Operation

e-mails with XcelEnergy during June -July 2013, Hughes Associates,

Baltimore,

MD, 7 July 2013:Conditions

anticipated

following

a SBO resulting

from an external

flooding

event:o ERO has been manned for the past several days, with these procedures

predicted

and plannedto be implemented

ahead of timeo Plant is in cold shutdown

condition

(mode 4)o I&C would perform the reactor level monitoring

portion of the RCIC procedure

o Operations

staffing

to perform the procedures

would be optimal (several

operators

assigned

asdesired to each procedure)

o Environment

would be consistent

with SBO (hot, dark, damp)o There would be 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to perform the procedures,

allowing

several opportunities

to troubleshoot

and/or re-perform

steps if necessary

o The ERO would place maximum priority

on maximizing

chances of successful

performance

ofthese procedures

Operator

Interview

Insights:

Documented

in and excerpted

from Hughes Associates

Record of Correspondence,

RCIC ManualOperation

e-mails with Xcel Energy during June -July 2013, Hughes Associates,

Baltimore,

MD, 7 July2013:From Xcel Operations:

The series of events would progress

during a flooding

event such that the need forthe alternate

instrumentation

would be known before the flood completely

resulted

in a station blackoutwith loss of DC. The alternate

instrumentation

(Fluke) would be connected

to the selected

locations.

Ifthis instrumentation

did not agree with the actual permanent

instrumentation

(i.e. prior to failure),

assistance

would be obtained

to figure out the discrepancy.

It is a relatively

simple solution

to get thetemporary

instrumentation

to work by either pulling a fuse or lifting a lead. This action would be requiredRevision

2Page A-3

I SMLI16012,000-1

Appendix

A -HRA CALCULATOR

REPORTSfor the control room, cable spreading

room and EFT locations

(again not proceduralized).

The otheroption would be to use the transmitter

in the reactor building

to get the readings

which does not requirethe lifted lead or fuse pulled.The other issue that is of concern is the need to density compensate

the fluke readings

to get an actuallevel. The indicated

level can be drastically

different

from the actual level depending

on the calibration

conditions

of the instrument

(hot or cold calibration

conditions)

and the actual pressure/temperature

at thetime of the reading.

None of this information

is contained

in the A.8 procedures.

There are densitycompensation

tables in the B.1.1 operations

manual figures section six and they are also posted in thecontrol room. It would take additional

action for the on-shift

team/technical

staff to put this all together

todetermine

what actual level was from the readings

that came off the fluke.

FD "nniramanta

el

=~ :!.n cluded. Total Available

Reuired for PNotes________.......___....

..__ ... ... __ .... .. .._____ Execuition

_________________i

Reactor operators

Yes 2 1Plant operators

Yes 2 0Mechanics

Yes 2 0Electricians

Yes 2 0I&C Technicians

Yes 2 0Health Physics Technicians

Yes 2 0Chemistry

Technicians

Yes 1 0Execution

Performance

Shapina Factors:Environment:

Lighting

PortableHeat/Humidity

Hot / HumidRadiation

Background

Atmosphere

Steam (although

steam will notbe present,

this PSF was usedto indicate

an off-nominal

condition,

such as would bepresent for flood and SBO)Special Requirements:

Tools RequiredAdequateAvailable

Parts RequiredAdequateClothing

RequiredAdequateComplexity

of Response:

Cognitive

ComplexExecution

ComplexEquipment

Accessibility

Main Control Room Accessible

(Cognitive):

Equipment

Accessibility

Reactor Building

With Difficulty

(Execution):

Stress: HighPlant Response

As Expected:

YesWorkload:

HighI Performance

Shaping Factors:

NegativeRevision

2Page A-4

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSPerformance

Shaping Factor Notes:The response

is considered

to be Complex due to the flooding

and SBO impacts to lighting

andaccessibility.

Flashlights,

headlamps

and boots were considered

necessary

by Training

when the JPMswere performed

for these tasks.The Equipment

Accessibility

is evaluated

as With Difficulty

due to Rx building

lighting

and flooding

issues.Despite preparations

and training,

the flooding

scenario

is considered

to be a high stress situation.

Key Assumptions

(see that section)

regarding

the conditions

provided

to Training

for performing

the JPMfor this task said that the "Environment

would be consistent

with SBO (hot, dark, damp)". The Traininginsights

from the JPM performance

(see Operator

Interview

Insights)

stated that the operators

recommended

to "Stage additional

flashlights

and headlamps

in RCIC room", so it is clear that portablelighting

is used.Revision

2 Page A-5Revision

2Page A-5

1 SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSTiming:T S 7.97 HoursT dly5.75 Hours T / 10.00 Minutes T M 80.00 MinutesIrreversible

Cue DamageState

t=oTimingi Analysis:

TO = Station BlackoutTsw = Time from Station Blackout

to the time by which RCIC must be restored.

Per Monticello

MAAP Calculations,

case "SBOCase3-R1",

27 June 2013:Time to TAF = 7.17 hrsTime to -149" = 7.2 hrsTime to 1800 F = 7.97 hrsDamage is assumed to occur if the temperature

exceeds 1800 F or 7.97 hrs, so this was used for Tsw asthe time by which RCIC restoration

is required.

Tdelay = PRA battery calc (PRA-CALC-1

1-002) indicates

that there are 5.75 hrs until RCIC batterydepletion.

Also, the RCIC Water Flow (column BC) of the d41 tabs in the "SBOCase3-R1"

MAAPanalysis

spreadsheet

shows that RCIC injection

stops at approximately

the same time (5.74 hrs), so theMAAP runs agree with the calc. This Tdelay can be considered

somewhat

conservative,

since in reality,

itis likely that an action would be taken before waiting for battery depletion.

T1/2 = The cue for action is that the TSC and the Emergency

Response

Director

have determined

thatRCIC operation

is needed. Daily planning

meetings

will have been held to discuss actions to be taken assoon as the diesels are lost, so the 10 minutes is simply an estimate

of the meeting time between TSCand ERF personnel

to make the actual decision

to manually

operate RCIC. The Control Room Supervisor

(CRS) directs operator

to initiate

RCIC and inject into the RPV using procedure

A.8-05.01,

ManualOperation

of RCIC, Part A, Placing RCIC in Service.Tm = Results of RCIC local manual operation

Job Performance

Measure performed

18 June 2013. Theprocedure

was performed

three times, taking 49 minutes,

37 minutes and 50 minutes to complete

for anaverage time of 45 minutes.

50 minutes was used as the conservative

value for JPM performance.

The JPM did not include the performance

of Part B for installation

and use of the Fluke level monitoring

device; this was estimated

to require 30 minutes,

so the total time for Tm was estimated

as 50 min + 30min = 80 min.Time available

for cognition

and recovery:

53.20 MinutesTime available

for recovery:

43.20 MinutesSPAR-H Available

time (cognitive):

53.20 MinutesRevision

2 Page A-6Revision

2Page A-6

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSSPAR-H Available

time (execution)

ratio: 1.54Minimum level of dependence

for recovery:

LDRevision

2 Page A-7Revision

2Page A-7

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMII 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCognitive

Unrecovered

RCICSBOFLOOD

Table 42: RCICSBOFLOOD

COGNITIVE

UNRECOVERED

Pc Failure Mechanism;.

Birainch

'HEPPca: Availability

of Information

d 1.5e-03PCb: Failure of Attention

m 1.5e-02Pcc: Misread/miscommunicate

data e 3.0e-03Pcd: Information

misleading

b 3.0e-03Pce: Skip a step in procedure

9 6.0e-03Pcf: Misinterpret

instruction

a neg.Pcg: Misinterpret

decision

logic k neg.PCh: Deliberate

violation

a neg.Sum of Pca through PCh = Initial Pc = 2.9e-02Notes:Normal RPV water level indication

is not available

and must be monitored

with a hand held deviceinstalled

by I&C. This is clearly proceduralized

in Part B of A.8-05.01.

Presumed

that SBO causes issues with normal alarms and indications

so pc-a through -d were adjustedconsistent

with insights

from EPRI 1025294,

A Preliminary

Approach

to Human Reliability

Analysis

forExternal

Events with a Focus on Seismic,

October 2012.Revision

2 Page A-8Revision

2Page A-8

I SM L16012.000-11

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -NRA CALCULATOR

REPORTSpca: Avalabilty

of infonnation

u ,cation Aal in CR Inicalion

WaIingAlternate

'l'kaining

onCR Accurate

W Procedure

Infelators

Yes(a) neg.(b) neg.(c) neg.3.-e-03 -(d) 1.5e-0311.0e+001.0e-01 (e) 5.0e-021.0e+00 (f) 5.0e-011.0e400(g) I.0e+O01LOO1MMCR indications

may not be accurate

due to the Station Blackout,

however,

either procedural

or informalcrew information

on alternate

indications

and training

should provide operator

input to decision-making.

pcb: Falum of attention

Low vs. M Check vs. Monitor Front vs. Back Alaued vmNotWorkload

Pan el Alnnedek IO O(a) neg..e*i Back I 0(b) .5e-043.0e-0 (c) 3.0e-031.8e+.00

Front 15.0e-02

(d) I.5e-04io.00M oI (e) 3.0e-033e-03 Back 15.0e-02

(f) 3.0e-041. Cb ie 3.0e-03 (g) 6.Oe-032. Cb ice Front 15.0e-02

((h) neg.Check O.e00 e4 (i)neg.o.oeo Back 5.0e,.2 (i) 7.Se-04lh 3.0e-03 (k) 15e-02Front -(I)7.e-04

Monito r O.O+- WL -- (m) I.5e-023.e35 I50e-02 (n) 1.5e-033.0e-3 I (o) 3.Oe-021.0e4.0Revision

2 Page 9Revision

2Page 9

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpcc nicate dataIhucatom

Easy to Good&Bad

Inicator

FoanalLocateI CoImunKicaUons

S O.e 4.0 0 (a) neg.S3.0e-033.e-03

0.Oe+00 I (c) I.Oe-03YeIot.0e-0

A(d) 4.0e-033.0e-03No ---o (e) 3.0e03o.oe*Coo

(6e33F)03 6.e-03L 3Oe-033.OeO3 (g) 4.0e-031.0e-03 (3.Oe-03(h)

7.Oe-033.0e-03For this scenario,

normal reactor water level indication

is not available

and a hand-held

level monitor willbe jumpered

in. Although

procedural

guidance

on reading the monitor is clear, "not Easy" is selected

toreflect the additional

challenges

to the task posed by this alternative

source for level indication.

pcd: Infoonation

mismeming

M Cues as Stated mring of Specicr ,Rang I General Ta-anugI ~ ~Ifferences

IIo.oesoo (a) neg.No---- -- -- ----- --- --- ----- --- ----- --- (b) 3.e-031.0e+O0 (c) 1.0e-021.0e-02MCR indications

may not be accurate

due to the Station Blackout

so cues may not be as stated inprocedures.

pce: Sip a step in procedure

Obqgiousv&

Singl vs. NfUN*l Graphicaly

Placekeqing

Ad(a) 3.0e-033.3"1 (b) 3.0e-03()e-02o.Oe+O 13.0e-03

(c) 3.0e-03130e0eO0I

(e) 2.0e-03(h) 1.3e-02---------------------------

(g) .oe-o31.0e-021.0e-4D 1 01) t.Oe -01Revision

2 Page 10Revision

2Page 10

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpd' Misinterpret

instruction

Standard

or AN Required

Training

on StepAmbiguous

wording Information

I--- ------ ------- ------- ------- (a) neg.(b) 3.0e-033.0e-02 (:c) 3.0e-02Yes 1.0e4.00NO1.0e,4

(d) 3.0e-030.0e+00 (e) 3.0e-023.0e-02 1(f) 6.0e-033.0e-02 (g) 6.0e-02pcg: Misinterprt

decision

ogic"NOr Statement

'ANUD or 'Or Both "AND" & practiced

ScenarioStatement

"OW3-le0M (a) 1.6e-023.0e.02 I(b) 4.9e-021.2e-02 (c) 6.0e-030o.oe+oo

l(d) 1.9-02(e) 2.0e-03O.Oe.+O0

(t) 6.0e-03Yes 3~e-. (g) 1.0e-02NO 3.0e..02

-(h) 3.1e-02.0e4.001.0e-03 (I) 3.0e-04---O.OeO Fi) 1.0e-030.0e+00 l .0e44)3.----- (k) neg.O.Oe.F (1) neg-pch: Delbe ate Wiolation

BEleinAdequacy

Advere Reasonable

Polcy ofof Instruction

Consequenceff

Alternatives

"Vembatin"

-.---- ------- --- ------- ------- ------- --- --(a)neg.Ye15.0e-

(b) 5.oe-o1NO.e00 I.OeO (c) I.Oe-Oo1.0e+00 I O.Oe+O0 (d)neg.0.0e44)0

(e) neg.Revision

2 Page 11Revision

2Page11

1SML-16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCognitive

RecoveryRCICSBOFLOOD

Table 43: RCICSBOFLOOD

COGNITIVE

RECOVERYU- ', a_ , .E -FinalInitial HEP FinalS0) W C ValueLU OOr "(LU >S o n- -ý.'PCa: 1.5e-03 X -5.0e-01 7.5e-04Pcb: 1.5e-02 X -X X MD 3.8e-03 5.7e-05Pcc:: 3.0e-03 --X X -1.0e-02 3.0e-05Pcd! 3.0e-03 -X X X -5.0e-03 1.5e-05Pce: 6.0e-03 X X X MD 1. le-02 6.6e-05Pof, nell. -1.0e+00Pc-:. neg.- -1.0e+00Pch: : ne .-1.0e+00Sumof

Pch = Inita Pc-= 9.2e-04Notes:Due to long timeframe

and severity

of scenario,

STA and Emergency

Response

Facility

will be available.

Operations

staffing

to perform the procedures

was assessed

by Xcel as optimal (several

operators

assigned

as desired to each procedure)

so Extra Crew was credited.

Used Moderate

Dependency

due to high stress.Revision

2 Page 12Revision

2Page 12

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSExecution

Unrecovered

RCICSBOFLOOD

Table 44: RCICSBOFLOOD

EXECUTION

UNRECOVERED

Procedure:

A.8-05.01,

Manual Operation

of RCIC .Comment.

Stress- Over Ride%* .- ,.FactorStep No. instrUction/Comment

Error ..THERP -HEP... ..* .....YPe.. .. 1. Table .. I .*Item * __._ * ._.In RCIC Room, verify open valves MO-2106 and MO-2096 Depress declutch

lever and turn handwheel.

A.8-05.01,

Step 8 Location:

Reactor Building

EOM 20-7b 2 1.3e-03 5EOC 20-13 1 1.3E-3Total Step HEP 1.3e-02Remove the pin securing

the slip link to the governor

lever to preventinterference

from the hydraulic

governor

(See Attachment

1) 5A.8-05.01,

Step 9 Location:

Reactor Building

EOM 20-7b 2 1.3e-03EOC 99 1 1.OE-2Total Step HEP 5.7e-02Uncap and throttle

open RCIC-27 condenser

cooling water starting

YSA.8-05.01,

Step 20 6082 drain. Close when steam is present.

5-22 Location:

Reactor Building

EOM 20-7b 2 1.5e-03_5

-_22_EOC

20-12 5 1.3E-3Total Step HEP 1.3e-02Throttle

MO-2080 and control as necessary

A.8-05.01

Steps Location:

Reactor Building

EOM 20-7b 2 1.3e-03 517,18,25,26

EOC 20-12 5 1.3E-3Total Step HEP 1.3e-02At D31, Access Control -SET UP for Monitoring

RX Vessel level byA.8-05-01,

Step 2, opening circuits

and kick out to Part B Mat D31 Location:

Reactor Building

EOM 20-7b 3 1.3e-03_5

atD31_EOC

20-12 3 1.3E-3Total Step HEP 1.3e-02At D100, 1st Floor EFT -SET UP for Monitoring

RX Vessel level byA.8-05-01,

Step 2, opening circuits

and kick out to Part BAt ST Location:

EFT EOM 20-7b 3 1 .3e-03At EFT EOC 20-12 3 1.3E-3Total Step HEP 1.3e-02SET UP for Monitoring

RX Vessel level by selecting

level instrument

and PART B SET UP AND MONITOR OF RX VESSELattaching

Fluke 707 monitoring

device -Control Room WITH FLUKE 707Part B, Steps 29 & 29. SELECT a level instrument

from list below,30P -MCR (preference

should be given to accessibility

and 5environmental

conditions

such as radiation,

temperature,

lighting,

etc.):In Control Room;Revision

2Page A-1 3

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSSýProcedure:'A.8.45.01;

Manual Operationof.RCIC

Comment Stress. Over RideFactorStep No. Instruction/Commetn:t-:

Error THERP HEPi. " .i : .... ..... ..-" ' i , " : i :+ Tabley. ; I;. , tem ... .I. .LI-2-3-85A,

Reactor Vessel Water Level, Panel C-03, Term Strip TT-62 to TT-61.LI-2-3-85B,

Reactor Vessel Water Level, Panel C-03, Term Strip PP-70 to PP-71.LI-2-3-91A,

Fuel Zone, Panel C-03, Term Strip TT-59 to TT-58.30.

If Level Indicator

selected

for use,Then ATTACH one lead from Fluke 707 to eachterminal

point listed.Location:

Main Control Room EOM 20-7b 3 1.3e-03EOC 20-12 13 1.3E-2Total Step HEP 7.2e-02SET UP for Monitoring

RX Vessel level by selecting

level instrument

and PART B SET UP AND MONITOR OF RX VESSELattaching

Fluke 707 monitoring

device -Cable Spreading

Room WITH FLUKE 70729. SELECT a level instrument

from list below,(preference

should be given to accessibility

andenvironmental

conditions

such as radiation,

temperature,

lighting,

etc.):In Cable Spreading

Room;Part B, Steps 29.& LI-2-3-91A,

Fuel Zone, Panel C-18, Term Strip BB- 530 -CSR 57 to BB-59.If Level Indicator

selected

for use,Then ATTACH one lead from Fluke 707 to eachterminal

point listed.Location:

Cable Spreading

Room EOM 20-7b 3 1.3e-03EOC 20-12 13 1.3E-2Total Step HEP 7.2e-02SET UP for Monitoring

RX Vessel level by selecting

level instrument

and PART B SET UP AND MONITOR OF RX VESSELattaching

Fluke 707 monitoring

device -EFT WITH FLUKE 70729. SELECT a level instrument

from list below,(preference

should be given to accessibility

andenvironmental

conditions

such as radiation,

temperature,

lighting,

etc.):At 3rd Floor EFT, ASDS Panel;LI-2-3-86,

Reactor Flooding

Level, Panel C-292,Part B, Steps 29 & Term Strip (EFT 3) HH-4 to HH-5. 530 -EFT LI-2-3-91

B, Fuel Zone, Panel C-292, Term Strip(EFT 3) HH-1 to HH-2.If Level Indicator

selected

for use,Then ATTACH one lead from Fluke 707 to eachterminal

point listed.Location:

EFT EOM 20-7b 3 1.3e-03EOC 20-12 13 1.3E-2 IRevision

2Page A-14

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSProcedure:

A.8-05.01,

ManUal Operation

of R(Step No.instruction/Cot

SET UP for Monitoring

RX Vessel level by selecting

level instrument

andattaching

Fluke 707 monitoring

device -Reactor BuildingPART B SET UP AND MONITOR OF RX VESSELWITH FLUKE 70729. SELECT a level instrument

from list below,(preference

should be given to accessibility

andenvironmental

conditions

such as radiation,

temperature,

lighting,

etc.):At 962', Rx Bldg;LT-2-3-85A,

Reactor Vessel Water Level, Panel C-56.LT-2-3-85B,

Reactor Vessel Water Level, Panel C-55.LT-2-3-61,

Reactor Flooding

Level, Panel C-55.At 935', Rx Bldg;LT-2-3-112A,

Fuel Zone, Rx Bldg 935' West, PanelC-122.LT-2-3-112B,

Fuel Zone, Rx Bldg 935' East, PanelC-121.31. If level transmitter

selected

for use,Then PERFORM the following:

a. REMOVE the cover (see Attachment

5 & 6).b. LIFT positive

lead from its conductor

(seeAttachment

7).c. Slightly

ENGAGE screw threads into transmitter.

d. CLAMP Fluke 707 leads in series with liftedpositive

wire and positive

terminal

point ontransmitter.

Part B, Steps 29 &31 -RxB5Location:

Reactor Building

EOM 20-7b 3 1 .3e-03EOC 1 20-12 1 13 1 1.3E-2-t --Total Step HEP 7.2e-02MONITOR OF RX VESSEL WITH FLUKE 707 (Conducted

separately

by DETERMINE

Rx water level by performing

theI&C) following:

(see Attachment

8 -diagram of FLUKE 707CALIBRATOR

pointing

out buttons and displays)

a. PRESS green button to START Fluke 707.b. PRESS MODE button until display readsMEASURE mA and Loop Power.c. USE Attachment

9 to obtain vessel level. [readPart B, Step 32 table of RCIC -mA VS. RPV WATER LEVEL]33. If connected

to LT-2-3-61

or LI-2-3-86,

Then OPERATE RCIC turbine to maintain

steadyindication

as close to 8 mA aspossible.

34. If NOT connected

to LT-2-3-61

or LI-2-3-86,

Then OPERATE RCIC turbine to maintain

steadyindication

as close to 20 mA aspossible.

Revision

2 Page A-15Revision

2Page A-1 5

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSProcedure:-A.8-05.01,

Manual Operation

of RCIC Comment-w

.'Stress Over Ride,FactorStep INo .Instrudtion/comnment.

Error -~ THERP :F HEP.Typeý. Table,. ItemLocation:

Reactor Building

EOM 20-7b 3 1.3e-03EOC 20-11 1 1.3E-3Total Step HEP 1.3e-02Interpret

Fluke monitor readings

using density compensation

tables in E-mail from Xcel Operations

toB.1.1 operations

manual, section 6 (posted in Control Room) Xcel PRA Manager,

2 July 2013The indicated

level can be drastically

different

fromthe actual level depending

on the calibration

conditions

of the instrument

(hot or cold calibration

conditions)

and the actual pressure/temperature

atthe time of the reading.

None of this information

iscontained

in the A.8 procedures.

There are density 5Part B, Step 32c compensation

tables in the B.1.1 operations

manualfigures section six and they are also posted in thecontrol room. It would take additional

action for theon-shift

team/technical

staff to put this all together

todetermine

what actual level was from the readingsthat came off the fluke.Location:

Main Control Room EOM I 20-7b 3 1.3e-03EOC 120-10 10 1.3E-2Total Step HEP 7.2e-02Maintain

CST level and venfy valve status in the steam chase ILocation:

Reactor Building

EOM 20-7b 4 4.3e-03 5EOC 20-12 5 1.3E-3Total Step HEP 2.8e-02Feedback

from I&C Level Monitoring

i 5Recovery

1 Location:

Reactor Building

EOM 99 1 1.0e-02Total Step HEP 5.0e-02Feedback

from Control Room 1 5Recovery

2 Location:

Main Control Room EOM 20-7b .3 1 1.3e-03Total Step HEP 6.5e-03Revision

2Page A-1 6

1SML-16012,000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSExecution

RecoveryRCICSBOFLOOD

Table 4-5: RCICSBOFLOOD

EXECUTION

RECOVERYCritical

Step No.Recovery

Step No.ActionHEP (Crit)HEP (Rec).Dep. Cond. HEP Total forDe. (Recl Stan,A-8-05.01,

Step 8 In RCIC Room, verify open valves MO-2106 and MO-2096 1.3e-02 7.3e-04Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02A-8-05.01,

Step 20 -Uncap and throttle

open RCIC-27 condenser

cooling water 1.3e-02 7.3e-0422 starting

YS 6082 drain. Close when steam is present.Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02A.8-05.01

Steps 17, Throttle

MO-2080 and control as necessary

18,25,26

13e02 1.4e04Recovery

1 Feedback

from I&C Level Monitoring

5.0e-02 MD 1.9e-01Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02A.8-05-01,

Step 2, At D31, Access Control -SET UP for Monitoring

RX Vessel 1.3e-02 7.3e-04at D31 level by opening circuits

and kick out to Part BRecovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02A.8-05-01,

Step 2, At D100, 1st Floor EFT -SET UP for Monitoring

RX Vessel level 1.3e-02 7.3e-04At EFT by opening circuits

and kick out to Part BRecovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Part B, Steps 29 & SET UP for Monitoring

RX Vessel level by selecting

level30 -MCR instrument

and attaching

Fluke 707 monitoring

device -7.2e-02 1.1e-02Control RoomRecovery

2 Feedback

from Control Room 6.5e-03 MD 1.5e-01Part B, Steps 29 & SET UP for Monitoring

RX Vessel level by selecting

level30 -CSR Instrument

and attaching

Fluke 707 monitoring

device -Cable 7.2e-02 4.0e-03Spreading

Room__Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Part B, Steps 29 & SET UP for Monitoring

RX Vessel level by selecting

level 7.2e-02 4.0e-0330 -EFT instrument

and attaching

Fluke 707 monitoring

device -EFTRecovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Part B, Steps 29 & SET UP for Monitoring

RX Vessel level by selecting

level31 -RxB Instrument

and attaching

Fluke 707 monitoring

device -7.2e-02 4.0e-03Reactor BuildingRecovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Part B, Step 32 MONITOR OF RX VESSEL WITH FLUKE 707 (Conducted

1.3e-02 7.3e-04separately

by I&C)Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Part B, Step 32c Interpret

Fluke monitor readings

using density compensation

tables In B.1.1 operations

manual, section 6 (posted In Control 7.2e-02 7.0e-03I Room)Recovery

I Feedback

from I&C Level Monitoring

5.0e-02 LD 9.8e-02Revision

2 Page A-17Revision

2Page A-17

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCritical

StA.8-05.05

A.8-05.01,

ep No. Recovery

Step No. .ý.Action.

HEP (Crit) HEP (Rec) Dep. Cond. HEP sTotapfor

(Rec) : *stepMaintain

CST level and verify valve status in the steam chase 2.8e-02 1.6e-03Recovery

2 Feedback

from Control Room 6.5e-03 LD 5.6e-02Step 9 Remove the pin securing

the slip link to the governor

lever toprevent interference

from the hydraulic

governor

(See 5.7e-02 5.7e-02Attachment

1)Total Unrecovered:.

5.2e-01 Total Recovered:

9.2e-02Revision

2 Page A-18Revision

2Page A-1 8

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSA.2. HPV_SBO_FLOOD,

Fail to operate the HPV using N2 bottles to providecontainment

heat removal during SBO/Flood

Basic Event SummaryPlant DataFile

...File;Size.

File Datei ."Re&cordDate

Monticello

Ext 901120 06/28/13

06/28/13Flooding

SDPHRA June2013.HRAJohn Spaargaren

& PierreMacheret,

Hughes Associates

Table 46: HPVSBOFLOOD

SUMMARY... .._*__"___._."_

__.___ '._____HEP

Sumrnhiaty

. ..: .., .-. -.. ..Pcog Pexe Total HEP ErrorFactorMethod CBDTM THERP CBDTM + THERPWithout Recovery

3.le-02 2.3e-01With Recovery

6.1e-04 1.3e-02 1.3e-02 5Initial Cue:Drywell pressure

above 2 psigCue Comments:

The cue for action is that the TSC has recommended

venting the DW by using the Hard Pipe Vent usingprocedure

A.8-05.08,

Manually

Open Containment

Vent Lines.Initial procedure

entered on high drywell pressure

is C.5-1200.

The DW/Torus

Pressure

leg directsoperators

to C.5-3505.

For the limiting

PRA case, it is assumed that normal and alternate

nitrogen

andpower via Y-80 is not available

and operators

must therefore

use A.8-05.08

to install pre-staged

nitrogenbottles directly

to the inboard and outboard

HPV isolation

valves to open them.Due to the SBO, it is assumed that there will be multiple

impacts to indications,

so the degree of clarityhas been set at "Poor".Degree of Clarity of Cues & Indications:

PoorProcedures:

Cognitive:

C.5-1200

(PRIMARY

CONTAINMENT

CONTROL flowchart

(Monticello))

Revision:

16Execution:

A.8-05.08

(Manually

Open Containment

Vent Lines) Revision:

1Other: A.6 (ACTS OF NATURE (Monticello))

Revision:

43Other: C.5-3505-A

0 Revision:

10Cognitive

Procedure:

Step: DW/TORUS

PRESSURERevision

2 Page A-19Revision

2Page A-1 9

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSInstruction:

BEFORE DW pressure

reaches Fig. D, DW Pressure

Limit (56 psig) vent to stay below Fig. D,DW Pressure

Limit per C.5-3505Procedure

and Training

Notes:Three JPM trials were performed

emulating

the specific

external

flooding

conditions

of this scenario

on 18June 2013. Observations

were factored

into this analysis.

Training:

Classroom,

Frequency:

0.5 per yearSimulator,

Frequency:

0.5 per yearJPM Procedure:

JPM-A.8-05.08-001

(Manually

Open Containment

Vent Lines) Revision:

0Identification

and Definition:

This HFE is for the external

flooding

model for venting prior to core damage.1. Initial Conditions:

SBO due to external

flooding.

2. Initiating

Events: External

flooding

causes station blackout.

3. Accident

sequence

(preceding

functional

failures

and successes):

No containment

venting or heat removalNeed to vent to maintain

containment

integrity

prior to ultimate

containment

pressure

for RCIC injection

4. Preceding

operator

error or success in sequence:

None.5. Operator

action success criterion:

Align pre-staged

alternate

nitrogen

bottles directly

to AO-4539 andAO-4540 (located

on the torus catwalk)

to open the hard pipe vent.6: Consequence

of failure:

Failure to vent containment

leads to containment

failure.

Any subsequent

release will likely be through an unscrubbed

and unfiltered

release path.Key Assumptions:

JPM A.8-05.08-001,

Rev. 0, Manually

Open Containment

Vent LinesINITIAL CONDITIONS:

o Extreme flooding

has led to a Station Blackout

that has. existed at Monticello

for the last 10hours.o Div. 1 and Div 2 250 VDC battery systems have been depleted

and are not available.

o The plant was in Shutdown

Cooling until the station blackout

and has since been slowlyrepressurizing

due to heating up.o Current RPV pressure

is 75 psig-and

slowly rising.o H SRV has failed to reseat and indication

of the tailpipe

vacuum breaker sticking

open have led toa Drywell pressure

of 45 psig and rising about 1 psig every 30 minutes.o Efforts to align the diesel fire pump to DW sprays have been unsuccessful

due to the flooding.

o The TSC has recommended

venting the DW by using the Hard Pipe Vent using procedure

A.8-05.08, Manually

Open Containment

Vent LinesINITIATING

CUES (IF APPLICABLE):

o The CRS directs operator

to initiate

DW venting through the Hard Pipe Vent lAW procedure

A.8-05.08, Manually

Open Containment

Vent Lines, Parts A and B.Revision

2Page A-20

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSHard Pipe Vent local manual operation

Job Performance

Measure entry condition

assumptions,

Information

excerpted

from Hughes Associates

Record of Correspondence,

Hard Pipe Vent ManualOperation

e-mails with Xcel Energy during June 2013, Hughes Associates,

Baltimore,

MD, 7 July 2013:Conditions

anticipated

following

a SBO resulting

from an external

flooding

event:o ERO has been manned for the past several days, with these procedures

predicted

and plannedto be implemented

ahead of timeo Plant is in cold shutdown

condition

(mode 4)o Operations

staffing

to perform the procedures

would be optimal (several

operators

assigned

asdesired to each procedure)

o Environment

would be consistent

with SBO (hot, dark, damp)o There would be more than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to perform the procedures,

allowing

several opportunities

totroubleshoot

and/or re-perform

steps if necessary

o The ERO would place maximum priority

on maximizing

chances of successful

performance

ofthese procedures

Operator

Interview

Insights:

The JPM that was completed

by Xcel with 2 ROs and 2 NLOs was JPM A.8-05.08-001,

Rev. 0, ManuallyOpen Containment

Vent Lines. The average time to complete

the JPM was 30 minutes given theinformation

that the N2 bottles were staged on the CRD catwalk.

There were no problems

or issues thatrequired

any of the operators

to stop and get clarifying

information,

it was identified

that removing

fittingswas not the best idea it would be better if the lines had tee's installed

where the caps could be removedand the appropriate

lines connected.

This way the capped connection

could be labeled to furtherminimize

connecting

to the wrong fitting.

The operators

stated that strips of non-skid

should be placed onthe areas around the site for safety reasons.

They also mentioned

using the LED headlights

versusflashlights

to allow both hands to be free.Manpower

Requirements:

..._....._.____"_

Ci~Wei~ier

hclu~de~d::

TotaAIIVailale

4KRqiiiredfr

'Noe____________

Ex'c~itip'"in

_ _ _ __ _Reactor operators

Yes 2 1Plant operators

Yes 2 0Mechanics

Yes 2 0Electricians

Yes 2 0I&C Technicians

Yes 2 0Health Physics Technicians

Yes 2 0Chemistry

Technicians

Yes 1 0Execution

Performance

Shapina Factors:Environment:

Lighting

PortableHeat/Humidity

Hot / HumidRadiation

Background

Atmosphere

Steam (although

steam will notbe present,

this PSF was usedto indicate

an off-normal

condition,

such as would bepresent for flood and SBO)Special Requirements:

Tools RequiredAdequateAvailable

Parts RequiredI I_ AdequateRevision

2Page A-21

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSClothing

RequiredAdequateComplexity

of Response:

Cognitive

ComplexExecution

ComplexEquipment

Accessibility

Main Control Room Accessible

(Cognitive):

Equipment

Accessibility

Reactor Building

With Difficulty

(Execution):

Stress: HighPlant Response

As Expected:

YesWorkload:

HighI Performance

Shaping Factors:

NegativePerformance

Shaping Factor Notes:The response

is considered

to be Complex due to the flooding

and SBO impacts to lighting

andaccessibility.

Flashlights,

headlamps

and boots were considered

necessary

by Training

when the JPMswere performed

for these tasks.The Equipment

Accessibility

is evaluated

as With Difficulty

due to Rx building

lighting

and flooding

issues.Key Assumptions

(see that section)

regarding

the conditions

provided

to Training

for performing

the JPMfor this task said that the "Environment

would be consistent

with SBO (hot, dark, damp)". The Traininginsights

from the JPM performance

stated that the operators

recommended

the use of "LED headlights

versus flashlights",

so it is clear that portable

lighting

is used.Despite preparations

and training,

the flooding

scenario

is considered

to be a high stress situation.

The steps identified

as Critical

in JPM-A.8-05.08-001

were used for the Execution

quantification.

Timing:T SW15.00 HoursT 5.50 HoursdelayT1/2 10.00 MinutesTM 45.00 MinutesM ~ I1CueIIrreversible

DamageState

I-I.t=0Timing Analysis:

TO = Station Blackout.

Tsw = Per MAAP run Rcic-dgl

3-cts-ABS

performed

in support of an external

flooding

SDP, containment

pressure

reaches 56 psig at 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> following

a SBO (flooding

>930'). Core temperature

reaches 1800degrees F at 15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br /> due to CST depletion

and no transfer

of RCIC to the torus. This is conservative

timing as refilling

of the CST is very likely.Td = 5.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> -Based on an interview

conducted

in a prior analysis

with a senior Shift Manager,

theorder to begin the procedure

to manually

operate the hard pipe vent would be given at approximately

27psig containment

pressure.

This is due to the step in C.5-1200

(DW/Torus

Pressure

leg) that says if youcannot restore and maintain

drywell pressure

within Figure 0 (27psig for 0 ft torus level), then maintaindrywell pressure

less than Figure D (56 psig).The 5.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> is based on MAAP run Rcic-dg13-cts-ABS

as the time when drywell pressure

reaches 42psia (27 psig) [Worksheet

d43-1, column AC Drywell Pressure]

T1/2 = According

to the initial conditions

assumed by Training

for the Job Performance

Measureperformed

for this task, the ERO will have been manned for the past several days, with these procedures

Revision

2Page A-22

1 SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpredicted

and planned to be implemented

ahead of time. Daily planning

meetings

will have been held todiscuss actions to be taken, so the 10 minutes is simply an estimate

of the meeting time between TSCand ERF personnel

to make the actual decision

to vent the DW by using the Hard Pipe Vent. The controlroom supervisor

(CRS) will then direct operators

to initiate

the process.Tm = Results of HPV local manual operation

Job Performance

Measure A.8-05.08-001

performed

18June 2013. The procedure

was performed

four times, taking an average of 30 minutes.

Additional

15minutes for C.5-3505-A

steps 3 and 4.Time available

for cognition

and recovery:

525.00 MinutesTime available

for recovery:

515.00 MinutesSPAR-H Available

time (cognitive):

525.00 MinutesSPAR-H Available

time (execution)

ratio: 12.44Minimum level of dependence

for recovery:

ZDRevision

2Page A-23

1SMLII16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCognitive

Unrecovered

HPVSBOFLOOD

Table 47: HPVSBOFLOOD

COGNITIVE

UNRECOVERED

Pc Failure .Mecdhanism

... -". 1 .1 ." 1 1 .Branch : .HEP.::..Pca: Availability

of Information

d 1.5e-03PCb: Failure of Attention

m 1.5e-02Pcc: Misread/miscommunicate

data e 3.0e-03Pcd: Information

misleading

b 3.0e-03Pce: Skip a step in procedure

e 2.0e-03Pcf: Misinterpret

instruction

a neg.Pcg: Misinterpret

decision

logic c 6.0e-03PCh: Deliberate

violation

a neg.Sum of Pca through PCh = Initial Pc = 3.1e-02Notes:Presumed

that SBO causes issues with normal alarms and indications

so pc-a through -d were adjustedconsistent

with insights

from EPRI 1025294,

A Preliminary

Approach

to Human Reliability

Analysis

forExtemal Events with a Focus on Seismic,

October 2012.Revision

2 Page A-24Revision

2Page A-24

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpca: Avlabhty

of infonnation

Indiation

ail in CR Indication

bminglAlftmate

Training

onCR Accurate

in Procedure

Indcators

I.0e-01 (a) neg..Oe.00 1.0e+00 (b) neg.O.0e4.00

I .oe-o (c) neg-7- e0(d) 1-pe-03Yes 5.0e-0 (e) 5.0e-02No1.e+00

f) 5.oe-o01.0e+001.0e-+O (g) .0" WOMCR indications

may not be accurate

due to the Station Blackout,

however,

either procedural

or informalcrew information

on alternate

indications

and training

should provide operator

input to decision-making.

pcrb: Failure of attention

Low vs. Hi Check vs. Monitor Front vs. Back Aarmed vs.NotWokdload

Panel AlarmedEvout(a)

neg-O.Oe0 Back .0(b) 1.5e-4LOW 3.0e-03 (c) 3.0e-031.0e+001.0e+00 Front 5e-2(d) 1.-%-045.0e-02OMonitor I0-0e+00

l(e) 3.0e-033.0e-03 Back 5.0e-02 (f) 3.0e-041. Nice 3.0e-03 1(g) 6.0e-032. ic Fro,,t 15.,10 (h eg-5(b0n-02Check O.Oe+0 18 0(i) neg.0.0e*WBack

(.0e.so5.0e-02e-04

WIgh 3.0e-03 1Ae(k) 1.e-02Front ()7.5e-04

Monitor --- Oe --0- (m) I.5e-023 -Back 50e-02 (n) 1.5e-033.Oe-03 I1.0e0 (o) 3.0e-02Revision

2 Page A-25Revision

2Page A-25

I SM L16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpcc: Misreadftniscmmnnicate

dataInhicators

Easy to Good--ad

Indicator

Fom- --Locate cminunicafions

I O.Oe.H) (a) neg.O.Oe.)O 3i 3 (b) 3.0e-03, O-Oe+0 (c) 1.0e-030(g) 4.0e-031.0e-03 (h) 4.0e-033.0e-03o.oe-4oo

(g) 3.Oe-0313.0e-033.oe-o3 (h) 7.Oe-O3pcd: Infonmtion

fidNilngM Cuesas Stated Warnng SpecoTc Tbn,,ig e TiningDire IIo.oe+0o (a) meg.No--------------------



(b) 3Je-03.0-L-02 (c) 1.0e-021..eOe0 1..od-o (d) 1.Oe-O11.Oe+OO (e) 1.0e" 0MCR indications

may not be accurate

due to the Station Blackout

so cues may not be as stated inprocedures.

pce: Sli a step in procedure

Obvious Ms Eing s Mlle V& MUPleawaf

cekeqing

A&d13.Oe-O3(a)

1 .0e-033.3e-01 (b) 3.Oe-031.0e.-02O.e.O0 3(c) 3.0e-03.Oe.001e-0

(d) 1.8e-02-(e) 4-e-033.3e-o------.----

Yes3.0e-03

13.e-3 (g) 6.0e-031.Oe4-OI

(h) I.3e-021..0e-021.0e-01 (i) t.0e -0tRevision

2 Page A-26Revision

2Page A-26

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSpf: Misinterpret

instruction

Standard

or AM Required

7haning on StepAmbiguous

wonling Information

--- ------- ------- ---------

--- (a) neg.(b) 3.oe-033.0e-02 (c) 3.0e-02NO .0e4H (d) 3.0e-03o.e-,.o I(e) 3.0e-023.0e-02 1.0e-01 (f) 6.Oe-033.0e..02

I 0 (g) 6.0e-02pcg: Mi§sinrmpt

decision

ogicNMor statemmut

-ir*N or -ow- Both AND' & IPracticed

ScenailStatement

"OFr3.3e41 (a) 1.Ge-023.0e-02 (b) 4.9--021.2-02 -3(c) 6.0e-0333.ie-Ol-

.Oe. (d) .9e-026.0e-03 (1.0e.9.42

3.3e-1 (e) 2.0e-03O.Oe-Oe-0

Yes OO + 1.00,6 0O (f) 6.0e-03(g) t.Oe-02No 3.0e-02 --(h) 3.1e-021.0e30.-0

I.0e-03 30"1 3.0e-0M13.3e-01

(k) neg.O.OedO l- (1) neg.pch: Deliberate

violation

Belef in Adequacy

Adverse Reasonable

Poky ofof Instructon

Consequence

if Alternatis

"'Verbatic"

oew-------

--- ------- ------- ---------


------ (a) neg.Yes 5.0eM (b) 5.0"-01oI. (c) 1.0e4WI.Oe4O110e00

O.Oe,.O0

(d) neg.Io.oe.,o

(e) neg.Revision

2 Page A-27Revision

2Page A-27

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSCognitive

RecoveryHPVSBOFLOOD

Table 48: HPVSBOFLOOD

COGNITIVE

RECOVERY< a) (" I- LL '.D FinalInitiaIIl.

HE > Z 1 -'5: -r-.O Value0CO W nOa C -O) Lu ValuePc. 1.5e-03 X X -2.5e-01 3.8e-04Pcb: 1.5e-02 X X X MD 3.8e-03 5.7e-05Pc': 3.0e-03 X X MD 2.1e-02 6.3e-05PCd: 3.0e-03 X X X MD 7.3e-03 2.2e-05<PCe: 2.0e-03 X X X MD 1.0e-02 2.0e-05, :; neg. -1.0e+00P. 6.e-03 X X X MD 1.1 e-02 6.6e-05-I--neg. 1.0e+00P 6 SuoP dt 6.1e-04Notes:Due to long timeframe

and severity

of scenario,

STA and Emergency

Response

Facility

will be available.

Operations

staffing

to perform the procedures

was assessed

by Xcel as optimal (several

operators

assigned

as desired to each procedure)

so Extra Crew was credited.

Used Moderate

Dependency

due to high stress.Revision

2 Page A-28Revision

2Page A-28

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISM LI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSExecution

Unrecovered

HPVSBOFLOOD

Table 49: HPVSBOFLOOD

EXECUTION

UNRECOVERED

ProcedurYe

C:A8-5.08,eManuallyOpen

Containm

ent CvehtLines

., omment Stress Over RideI IStep.No.*

jnstructionlComnent,-,

Error' -,. HTHERP HEP Factor.,Type' Table Item -..___- _Connect and apply pressure

from AH-1 cylinder

to rupture Rupture DiskPSD-4543A.8-05.08,

Step 4 Location:

Reactor Building

EOM 20-7b 2 1.3e-03EOC 20-12 5 1.3E-3Total Step HEP 1.3e-02Connect and adjust AH-1 regulator

to less than 100 psig and slowly openAH-1 discharge

valve to open valve AO-4539 5A.8-05.08,

Step 5 Location:

Reactor Building

EOM 20-7b 4 4.3e-03EOC 20-13 5 1.3E-2Total Step HEP 8.7e-02Connect and adjust AH-2 regulator

to less than 100 psig and slowly openAH-2 discharge

valve to fully open valve AO-4540 5A.8-05.08,

Step 6 Location:

Reactor Building

EOM 20-7b 4 4.3e-03EOC 20-13 5 1.3E-2 ITotal Step HEP 8.7e-02Open and Close the HPV isolation

valves as directed

by shift supervisor

C.5-3505

Part A, Location:

Reactor Building

EOM 20-7b 1 4.3e-04 5Step 3 1 EOC 20-13 2 3.8E-3 ITotal Step HEP 2.1e-02Monitor Containment

Pressure

and Radiation

Levels in the Hard PipeC.5-3505

Part A Vent. 5Step 4 Location:

Reactor Building

EOM 20-7b 1 4.3e-04Step 4 EOC 20-10 1 3.8E-3Total Step HEP 2.1e-02Feedback

from Control Room 5Recovery

Location:

Main Control Room EOM 20-7b 3 1.3e-03 ITotal Step HEP 6.5e-03Revision

2 Page A-29Revision

2Page A-29

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSExecution

RecoveryHPV_SBOFLOOD

Table 4-10: HPVSBOFLOOD

EXECUTION

RECOVERYc it.Recovery

Step No.. -i HEP (crit)i HEP'Rec .Dep. P"Cond. :.Totalffor.

~Criticalý

'te k o .__________

_______________________________________________________

....___.... ..._(Rec) StepA.8-05.08,

Step 4 Connect and apply pressure

from AH-1 cylinder

to rupture 1.3e-02 7.3e-04Rupture Disk PSD-4543Recovery

Feedback

from Control Room 6.5e-03 LD 5.6e-02A.8-05.08,

Step 5 Connect and adjust AH-1 regulator

to less than 100 psig andslowly open AH-1 discharge

valve to open valve AO-4539 8.7e-02 4.9e-03Recovery

Feedback

from Control Room 6.5e-03 LD 5.6e-02A.8-05.08,

Step 6 Connect and adjust AH-2 regulator

to less than 100 pslg and 8.7e-02 4.9e-03slowly open AH-2 discharge

valve to fully open valve AO-4540Recovery

Feedback

from Control Room 6.5e-03 LD 5.6e-02C.5-3505

Part A, Open and Close the HPV isolation

valves as directed

by shift 2.1 e-02 1.2e-03Step 3 supervisor

Recovery

Feedback

from Control Room 6.5e-03 LD 5.6e-02C.5-3505

Part A, Monitor Containment

Pressure

and Radiation

Levels in the 2.1 e-02 1.2e-03Step 4 1 Hard Pipe Vent.I Recovery

Feedback

from Control Room 6.5e-03 LD 5.6e-02-* .: .Total ....I.- Unrecoered:-

2.3e1- .Total R 2ovIered:

1.3e2Revision

2 Page A-30Revision

2Page A-30

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSA.3. RCICSBOFLOOD,

Fail to manually

operate RCIC during SBO and extremeflooding

conditions

(SPAR-H)Basic Event Summary'Planlt;:".. i. Data :File Dati e

Rebo d
:".Monticello

Ext 909312 07/02/13

07/02/13Flooding

SDPHRAJune2013_SPAR

Hquant forsensitivity.HRA

Table 11: RCIC_SBOFLOOD

SUMMARY[Ana l, i Resu!ts:.-I4

Cognitive

Execution

[Failor

3.2e.. 9.1 e-021 .4e-01Plant:Monticello

Initiating

Event:External

Flood + SBOBasic Event Context:The flooding

engineer

provides

daily updates to the station on high river water levels including

potentials

to rise above any A.6 trigger points. At this point, heightened

awareness

of the potential

for flooding

isimplemented.

When river level exceeds 921 feet an evaluation

of EALs would be performed.

If visible damage hasoccurred

due to flood water rising greater than 921 feet, then an Alert per EAL HA1.6 would be declared.

Prior to river levels reaching

these levels, operators

would be walking down the A.8 procedures

foralternate

methods to vent primary containment

and operate RCIC remotely.

This would involve staging ofequipment

in the torus area to open the Hard Pipe Vent and verification

that equipment

is properly

stagedto operate RCIC remotely.

EDGs and batteries

are not available.

Shutdown

cooling,

HPCI, and RCIC are not available

from normalelectrical

means. RCIC is available

for manual operation.

Operators

have temporary

level indication

setup in the reactor building.

Pressure

indication

is available

inthe direct area of the level transmitters.

The building

is dark and most likely water in the basement

of thereactor building.

Additional

portable

lights are available

to assist with lighting

and boots staged for higherwater. The operators

would utilize A.8-05.01

to un-latch

the governor

from the remote servo linkage andthrottle

steam flow to RCIC to start the turbine rolling while coordinating

with operators

monitoring

waterlevel and reactor pressure.

Upon reaching

the high end of the level band the operators

would throttleclosed the steam admission

valve and await direction

to re-start

RCIC. Local operation

of RCIC isdemonstrated

each refueling

outage during the over speed test. Operation

of a coupled turbine run isless complex because the turbine is easier to control with a load.Revision

2Page A-31

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSTiming:T 7.97 HoursT delay 5.75 Hours i T1/2 10.00 Minutes TM 80.00 Minutes1Irreversible

Cue DamageState

t=oTiming Analysis:

TO = Station BlackoutTsw = Time from Station Blackout

to the time by which RCIC must be restored.

Per Monticello

MAAP Calculations,

case "SBOCase3-RI",

27 June 2013:Time to TAF = 7.17 hrsTime to -149" = 7.2 hrsTime to 1800 F = 7.97 hrsDamage is assumed to occur if the temperature

exceeds 1800 F or 7.97 hrs, so this was used as the timeby which RCIC restoration

is required.

Tdelay = PRA battery calc (PRA-CALC-1

1-002) indicates

that there are 5.75 hrs until RCIC batterydepletion.

Also, the RCIC Water Flow (column BC) of the d41 tabs in the "SBOCase3-RI"

MAAPanalysis

spreadsheet

shows that RCIC injection

stops at approximately

the same time (5.74 hrs), so theMAAP runs agree with the calc. This Tdelay can be considered

somewhat

conservative,

since in reality,

itis likely that an action would be taken before waiting for battery depletion.

T1/2 = The cue for action is that the TSC and the Emergency

Response

Director

have determined

thatRCIC operation

is needed. Daily planning

meetings

will have been held to discuss actions to be taken assoon as the diesels are lost, so the 10 minutes is simply an estimate

of the meeting time between TSCand ERF personnel

to make the actual decision

to manually

operate RCIC. The Control Room Supervisor

(CRS) directs operator

to initiate

RCIC and inject into the RPV using procedure

A.8-05.01,

ManualOperation

of RCIC, Part A, Placing RCIC in Service.Tm = Results of RCIC local manual operation

Job Performance

Measure performed

18 June 2013. Theprocedure

was performed

three times, taking 49 minutes,

37 minutes and 50 minutes to complete

for anaverage time of 45 minutes.

50 minutes was used as the conservative

value for JPM performance.

The JPM did not include the performance

of Part B for installation

and use of the Fluke level monitoring

device; this was estimated

to require 30 minutes,

so the total time for Tm was estimated

as 50 min + 30min = 80 min.Time available

for recovery:

43.20 MinutesSPAR-H Available

time (cognitive):

53.20 MinutesSPAR-H Available

time (execution)

ratio: 1.54Minimum level of dependence

for recovery:

LDRevision

2 Page A-32Revision

2Page A-32

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSISMLI6OI2.000.1

Appendix

A -HRA CALCULATOR

REPORTSPART I. DIAGNOSIS

PSFss PSF ,ve;s9 %fMultlper~or<.

Available

Time Inadequate

Time P(failure)

= 1.0(recommended

choice Barely adequate

time (~ 2/3 x nominal)

10based on timing Nominal time 1information

in bold) Extra time (between

1 and 2 x nominal 0.1and > 30 min)Expansive

time (> 2 x nominal and > 30 X 0.01min)Insufficient

Information

IStress Extreme 5High X 2Nominal 1Insufficient

Information

IComplexity

Highly complex 5Moderately

complex X 2Nominal 1Obvious diagnosis

0.1Insufficient

Information

1Experience/Training

Low 10Nominal X 1High 0.5Insufficient

Information

1Procedures

Not available

50Incomplete

20Available,

but poor 5Nominal X 1Diagnostic/symptom

oriented

0.5Insufficient

Information

1ErgonomicslHMI

Missing/MisleadingJ

50Poor 10Nominal X IGood 0.5Insufficient

Information

1Fitness for Duty Unfit P(failure)

= 1.0Degraded

Fitness 5Nominal X 1Insufficient

Information

1Work Processes

Poor 2Nominal 1Good X 0.8Insufficient

Information

1Revision

2 Page A-33Revision

2Page A-33

ISM LI6012.000-1ApndxA-HACLUTORERS

Appendix

A -HRA CALCULATOR

REPORTSDiagnosis

HEP:3.2e-04PART I1. ACTIONPSFs PSF IUVeis. ~ Multi 11ýr for.__________________

griagn sisAvailable

Time Inadequate

Time P(failure)

= 1.0(recommended

choice Time available

is -the time required

10based on timing Nominal time X 1information

in bold) Time available

>= 5x the time required

0.1Time available

>= 50x the time required

0.01Insufficient

Information

1Stress/Stressors

Extreme 5High X 2Nominal 1Insufficient

Information

1Complexity

Highly complex 5Moderately

complex X 2Nominal 1Insufficient

Information

1Experience/Training

Low 3Nominal X 1High 0.5Insufficient

Information

1Procedures

Not available

50Incomplete

20Available,

but poor X 5Nominal 1Insufficient

Information

1Ergonomics/HMI

Missing/Misleading

50Poor X 10Nominal 1Good 0.5Insufficient

Information

1Fitness for Duty Unfit P(failure)

= 1.0Degraded

Fitness 5Nominal X 1Insufficient

Information

1Work Processes

Poor 5Nominal 1Good X 0.5Insufficient

Information

0.5Revision

2 Page A-34Revision

2Page A-34

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSAction Probability:

9.1e-02 [Adjustment

applied:

1.0e-3 * 1.0e+02 / (1.0e-3 * (1.0e+02

-1) + 1)]PART Ill. DEPENDENCY

caeI Im In~ mC..-mhwamccwiTask Failure WITHOUT Formal Dependence:

9.1le-02Task Failure WITH Formal Dependence:

1 .4e-01Revision

2 Page A-35Revision

2Page A-35

ISML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSA.4. HPVSBOFLOOD,

Fail to operate the HPV using N2 bottles to providecontainment

heat removal during SBO/Flood

(SPAR-H)Basic Event Summary.:Plant , :Datale FileSize"..

  • FileDate
Rerd DateMonticello

Ext 901120 06/28/13

06/28/13Flooding

SDPHRAJune2013-SPAR

Hquant for1 sensitivity.HRA

John Spaargaren

& PierreMacheret,

Hughes Associates

Table 412: HPVSBOFLOOD

SUMMARYAnalyssResults-,*

Cognitive

Execution

Fe ! rN r 1b6 1i.ii 3.2e-04 5.0e-03Total :HEP. I 5.5e-02Plant:Monticello

Initiating

Event:External

Flood + SBOBasic Event Context:The flooding

engineer

provides

daily updates to the station on high river water levels including

potentials

to rise above any A.6 trigger points. At this point, heightened

awareness

of the potential

for flooding

isimplemented.

When river level exceeds 921 feet an evaluation

of EALs would be performed.

If visible damage hasoccurred

due to flood water rising greater than 921 feet, then an Alert per EAL HA1.6 would be declared.

Prior to river levels reaching

these levels, operators

would be walking down the A.8 procedures

foralternate

methods to vent primary containment

and operate RCIC remotely.

This would involve staging ofequipment

in the torus area to open the Hard Pipe Vent and verification

that equipment

is properly

stagedto operate RCIC remotely.

EDGs and batteries

are not available.

Shutdown

cooling,

HPCI, and RCIC are not available

from normalelectrical

means. RCIC is available

for manual operation.

Revision

2 Page A-36Revision

2Page A-36

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSTimina:T S 15.00 HoursTdelay 5.50 Hours T1/2 10.00 Minutes TM 45.00 MinutesIreversible

Cue DamageState

t=oAnalysis:

TO = Station Blackout.

Tsw = Per MAAP run Rcic-dg13-cts-ABS

performed

in support of an external

flooding

SDP, containment

pressure

reaches 56 psig at 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> following

a SBO (flooding

>930'). Core temperature

reaches 1800degrees F at 15 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br /> due to CST depletion

and no transfer

of RCIC to the torus. This is conservative

timing as refilling

of the CST is very likely.Td = 5.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> -Based on an interview

conducted

in a prior analysis

with a senior Shift Manager,

theorder to begin the procedure

to manually

operate the hard pipe vent would be given at approximately

27psig containment

pressure.

This is due to the step in C.5-1200

(DW/Torus

Pressure

leg) that says if youcannot restore and maintain

drywell pressure

within Figure 0 (27psig for 0 ft torus level), then maintaindrywell pressure

less than Figure D (56 psig).The 5.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> is based on MAAP run Rcic-dg13-cts-ABS

as the time when drywell pressure

reaches 42psia (27 psig) [Worksheet

d43-1, column AC Drywell Pressure]

T1/2 = According

to the initial conditions

assumed by Training

for the Job Performance

Measureperformed

for this task, the ERO will have been manned for the past several days, with these procedures

predicted

and planned to be implemented

ahead of time. Daily planning

meetings

will have been held todiscuss actions to be taken, so the 10 minutes is simply an estimate

of the meeting time between TSCand ERF personnel

to make the actual decision

to vent the DW by using the Hard Pipe Vent. The controlroom supervisor

(CRS) will then direct operators

to initiate

the process.Tm = Results of HPV local manual operation

Job Performance

Measure A.8-05.08-001

performed

18June 2013. The procedure

was performed

four times, taking an average of 30 minutes.

Additional

15minutes for C.5-3505-A

steps 3 and 4.Time available

for recovery:

515.00 MinutesSPAR-H Available

time (cognitive):

525.00 MinutesSPAR-H Available

time (execution)

ratio: 12.44Minimum level of dependence

for recovery:

ZDRevision

2 Page A-37Revision

2Page A-37

1SML16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSPART I. DIAGNOSIS

P PSFs,6V , AfPSF vels u-ti'for-Dagposis,

Available

Time Inadequate

Time P(failure)

= 1.0(recommended

choice Barely adequate

time (~ 2/3 x nominal)

10based on timing Nominal time 1information

in bold) Extra time (between

1 and 2 x nominal 0.1and > 30 min)Expansive

time (> 2 x nominal and > 30 X 0.01min)Insufficient

Information

Stress Extreme 5High X 2Nominal 1Insufficient

Information

1Complexity

Highly complex 5Moderately

complex X 2Nominal 1Obvious diagnosis

0.1Insufficient

Information

1Experience/Training

Low 10Nominal X 1High 0.5Insufficient

Information

1Procedures

Not available

50Incomplete

20Available,

but poor 5Nominal X 1Diagnostic/symptom

oriented

0.5Insufficient

Information

1Ergonomics/HMI

Missing/Misleading

50Poor 10Nominal X 1Good 0.5Insufficient

Information

1Fitness for Duty Unfit P(failure)

= 1.0Degraded

Fitness 5Nominal X 1Insufficient

Information

1Work Processes

Poor 2Nominal 1Good X 0.8Insufficient

Information

1Revision

2 Page A-38Revision

2Page A-38

1 SML-16012.000-I

Appendix

A -HRA CALCULATOR

REPORTSI SMLI 6012.000-1

Appendix

A -HRA CALCULATOR

REPORTSDiagnosis

HEP:3.2e-04PART II. ACTION.PSFs,, PSFLevels'

s Multiplier

forS~ Diagflosis

Available

Time Inadequate

Time P(failure)

= 1.0(recommended

choice Time available

is -the time required

10based on timing Nominal time X 1information

in bold) Time available

>= 5x the time required

0.1Time available

>= 50x the time required

0.01Insufficient

Information

1Stress/Stressors

Extreme 5High X 2Nominal 1Insufficient

Information

1Complexity

Highly complex 5Moderately

complex 2Nominal X IInsufficient

Information

1Experience/Training

Low 3Nominal 1High X 0.5Insufficient

Information

1Procedures

Not available

50Incomplete

20Available,

but poor 5Nominal X 1Insufficient

Information

1Ergonomics/HMI

Missing/Misleading

50Poor X 10Nominal 1Good 0.5Insufficient

Information

IFitness for Duty Unfit P =failure)

1.0Degraded

Fitness 5Nominal X 1Insufficient

Information

1Work Processes

Poor 5Nominal 1Good X 0.5Insufficient

Information

0.5Action Probability:

5.0e-03Revision

2 Page A-39Revision

2Page A-39

ISMLI16012.000-1

Appendix

A -HRA CALCULATOR

REPORTSPART II1. DEPENDENCY

C,=, TD I E I I C ,F.-- -Cb ntin i...,=, ,w M&IMAB ~ F, ibTask. Failre WTHOUForal

D endncesocb addiiorW

khedlafr-I.-ks.

&k*T Faaulia u HD5emTask Failure WITHOUT Formal Dependence:

5.3e-03Task Failure WITH Formal Dependence:

5.5e-02Revision

2 Page A-40Revision

2Page A-40'

ISML16012.000-1

B. APPENDIX

B -EVENT TREESAppendix

B -EVENT TREESRevision

2 Page B-IRevision

2Page B-1

EXTERNAL

FLOOD >930' < 935' EARLY WARNING REACTOR BUILDING

PROTECTED

RCIC/RPV

& HARD PIPE VENT Prob NameSUCCESSFUL

EARLY WARNINGO.OOE+00FLOOD <935'0.891RCIC SUCCESS0.894EXTERNAL

FLOOD >930'[8.90E-06]

[1]SUCCESSFUL

EARLY WARNING[0.106]O.00E+007.09E-068.41 E-070.OOE+007.72E-070.15E-081 07F-07DKOK'D Seq 1:)KDK,D Seq 2MD Seq 3O.00E+00FLOOD > 935'[0.109]RCIC SUCCESSREACTOR BLDG PROTECTED

0.8940.89FAILURE TO PROTECT RB[0.106]1lI[0.11]IMonticello,

Flood SDP 930-935.eta

17/3/2013

1 Page 1IMonticello

Flood SDP 930-935.eta

7/3/2013

Page 1

EXTERNAL

FLOOD >930' < 935' EARLY WARNING REACTOR BUILDING

PROTECTED

RCIC/RPV

& HARD PIPE VENT Prob I NameSUCCESSFUL

EARLY WARNINGO.OOE+00FLOOD <935'0.5in flflF4flf

RCIC SUCCESS1

a; mai--fnr,

[1]0.894'I .uhlt--ub

EXTERNAL

FLOOD >930'[2.00E-05]

[0.106]SUCCESSFUL

EARLY WARNING:)K::)K,D Seq 1:)K,D Seq 2'D Seq 3O.00E÷00FLOOD > 935'[0.5]RCIC SUCCESSREACTOR BLDG PROTECTED

0.8940.89FAILURE TO PROTECT RB7.96E-06-9.43E-07

1.10E-06[0.106][1][0.11]Monticello

Flood SDP 930-935 Sens Freq.eta17/3/2013

1 Page 1

EXTERNAL

FLOOD >930' < 935' EARLY WARNING REACTOR BUILDING

PROTECTED

RCIC/RPV

& HARD PIPE VENT Prob NameSUCCESSFUL

EARLY WARNINGIO.OOE+00FLOOD <935'0.891 1RCIC SUCCESS0.805D.O0E+005.38E-061.55E-06EXTERNAL

FLOOD >930'[8.90E-06]

[1]SUCCESSFUL

EARLY WARNING[0.195]ILl=t =IPI Jt I:)K:)K,D Seq 1:)K:)K'D Seq 2'D Seq 30.OOE+00RCIC SUCCESSFLOOD > 935'[0.109]REACTOR BLDG PROTECTED

0.805[1]0.89] FAILURE TO PROTECT RB[0.195]5.95E-071 .68E-071.07E-07[0.11]Monticello

Flood SDP 930-935 Sens SPAR-H.eta

7/3/2013

Page 1

Enclosure

3Monticello

Nuclear Generating

Plant"Monticello

Flood Protection"

11 Pages Follow

Monticello

Flood Protection

1.0 PURPOSEThe purpose of this document

is to evaluate

the flood protection

provided

at Monticello

Nuclear Generating

Plant (MNGP).Nuclear power plants are designed

to meet robust design criteria,

referred

to as GeneralDesign Criteria

(GDC); which are now codified

as part of NRC regulations

in 10 CFRPart 50. The GDC have existed in various forms prior to being codified

in part 50 andplant commitments

to meet the GDC (or pre-existing

requirements)

depend on the ageof the plant.MNGP was designed

before the publishing

of the 70 General Design Criteria

(GDC) forNuclear Power Plant Construction

Permits proposed

by the Atomic Energy Commission

(AEC) for public comment in July 1967, and constructed

prior to the 1971 publication

ofthe 10 CFR 50, Appendix

A, GDC. As such, MNGP was not licensed

to 10 CFR 50Appendix A, GDC. The MNGP USAR, Section 1.2, lists the Principal

Design Criteria(PDC) for the design, construction

and operation

of the plant. MNGP USAR Appendix

Eprovides

a plant comparative

evaluation

to the 70 proposed

AEC design criteria.

It wasconcluded

in the USAR that the plant conforms

to the intent of the GDC. A listing of thePDC and AEC GDC (by number and title) pertaining

to external

flooding

is providedbelow:PDC 1.2.1 .c "General

Criteria"

"The design of those components

which are important

to the safety of the plantincludes

allowances

for the appropriate

environmental

phenomena

at the site.Those components

important

to safety and required

to operate during accidentconditions

are designed

to operate in the post accident

environment."

AEC Criterion

2 -Performance

Standards

(Category

A)"Those systems and components

of reactor facilities

which are essential

toprevention

of accidents

which could affect the public health and safety or tomitigation

to their consequences

shall be designed,

fabricated,

and erected toperformance

standards

that will enable the facility

to withstand,

without loss ofthe capability

to protect the public, the additional

forces that might be imposed bynatural phenomena

such as earthquakes,

tornadoes,

flooding

conditions,

winds,ice, and other local site effects.

The design bases so established

shall reflect:

(a)appropriate

consideration

of the most severe of these natural phenomena

thathave been recorded

for the site and surrounding

area and (b) an appropriate

margin for withstanding

forces greater than those recorded

to reflectuncertainties

about the historical

data and their suitability

as a basis for design."This evaluation

addresses

the following

aspects of flood protection

that are provided

forthe MNGP to meet AEC Criterion

2:* Flood Analyses

-this discussion

describes

the site location,

hydrology

anddetermination

of the maximum predicted

flood water elevations

and timing.Page 1 of 11

  • Flood Mitigation

Strategy

-this discussion

describes

the aspects provided

topreclude

the design bases flood from adversely

impacting

the site. Thisprotection

is provided

by structural

design and procedural

actions.* Flood Protection

Implementation

-this discussion

describes

the actions taken atthe site to provide reasonable

assurance

that flood protection

strategy

can beeffectively

implemented

in a design bases flood scenario.

2.0 FLOOD ANALYSISThis section describes

the site location

and hydrology,

and a summary of current designbasis flood elevations.

Information

in this section is based on information

in the MNGPUpdated Safety Analysis

Report (USAR) (Reference

1); specific

sections

are identified

below.2.1 Site Location

and Description

The plant is located within the city limits of Monticello,

Minnesota

on the right (west)bank of the Mississippi

River. The topography

of the MNGP site is characterized

byrelatively

level bluffs which rise sharply above the river. Three distinct

bluffs exist at theplant site at elevations

920, 930, and 940 ft. above msl. The finished

plant grade isapproximately

930 ft. msl. The plant grade surrounding

Class I and Class II structures

housing Class I equipment

varies between 935 ft. msl and 930 ft. msl. The sitedescription

and topography

is described

in detail in the MNGP USAR, Section 2.2.Hydrology

The Mississippi

River is the major hydrologic

feature for the site. The river poses thesignificant

flooding

source for the site. Table 1, below, summarizes

normal and floodedriver flow rates and water elevations.

Table 1Normal and Flooded River Flow Rates and Water Elevations

Mississippi

River Flow Rate (cfs) Water Elevation

Condition

(ft. msl)Normal 4,600 905Maximum Recorded(1965) 51,000 9161000 Year Flood -90,000 (1) 921Probable

Maximum 364,900 939.2Flood 364,900 _ 939.2(1) Estimated

using USAR Appendix

G, Exhibit 8, for a waterelevation

of 921 ft.Normal river level at the MNGP site is about 905 ft. msl at a distance

1.5 milesupstream,

the normal river elevation

is about 910 ft. msl and at an equal distancedownstream,

the river is at 900 ft. msl. The following

flow statistics

are estimated

for theMississippi

River at the MNGP site:Page 2 of 11

Average Flow -4,600 cubic feet per second (cfs)Minimum Flow -240 cfsMaximum Flow -51,000 cfsThe maximum reported

high water level at the MNGP site was about 916 ft. msl whichwas recorded

during the spring flood of 1965 with an estimated

river flow of 51,000 cfs.The results of flood frequency

study for the 1000 year flood estimated

a peak stage of921 ft. msl (USAR Section 2.4)2.2 Design Basis Flood HazardThe following

flood scenarios

are evaluated

as part of the MNGP licensing

basis [USARAppendix

G]:* Flooding

in Streams and Rivers* Flooding

due to Downstream

Ice Dam Build-UpA summary of the results as described

in Reference

2 for each of these floodingscenarios

is provided

below; specific

sections

from Reference

2 are identified

with theassociated

discussion.

2.2.1 Flooding

in Streams and RiversThe probable

maximum discharge

was determined

to be 364,900 cfs and acorresponding

peak stage of elevation

939.2 ft. msl. The flood would result frommeteorological

conditions

which could occur in the spring and would reach maximumriver level in about 12 days. It was estimated

the flood stage would remain aboveelevation

930.0 ft. msl for approximately

11 days.The most critical

sequence

of events leading to a major flood would be to have anunusually

heavy spring snowfall

and low temperatures

after a period of intermittent

warmspells and sub-freezing

temperatures

has formed an impervious

ground surface andthen a period of extremely

high temperatures

followed

by a major storm. The snowmeltand rainfall

excesses

were then routed to the plant site by computer

modeling.

A stagedischarge

rating curve was then constructed.

The probable

maximum discharge

wasdetermined

to be 364,900 cfs with a corresponding

peak stage elevation

of 939.2 ft. mslfrom the discharge

rating curve.A probable

maximum summer storm over the project area was also studied in detail andthe resulting

flood at the project site determined.

Although

the summer storm was muchlarger than the spring storm, the initial retention

rate of zero for spring conditions,

andthe snowmelt

contribution

to runoff, resulted

in the spring storm producing

the morecritical

flood.Key Assumptions

Used to Determine

Design Basis Flood HazardThe PMF evaluation

for the spring storm conservatively

maximizes

the potential

snowcover and precipitation.

A limiting

temperature

sequence

that results in an impervious

ground surface due to subfreezing

temperatures

is assumed.

This is followed

byextreme high temperatures,

and a subsequent

major spring storm. The snowmelt

andPage 3 of 11

rainfall

maximizes

the runoff to the river basin. This sequence

of events is postulated

toproduce a PMF. Additional

details regarding

key assumptions

used in the analyses

aredescribed

in USAR Appendix

G.Methodology

Used to Develop Design Basis Flood HazardThe predicted

flood discharge

flow and PMF level at the MNGP site was defined usingDepartment

of the Army, Office of the Chief of Engineers,

the U.S. Army Corps ofEngineers,

Engineer

Circular

No. 1110-2-27,

Enclosure

2, "Policies

and Procedures

Pertaining

to Determination

of Spillway

Capacities

and Freeboard

Allowances

for Dams,"dated August 1, 1966 (Reference

2).The PMF at the MNGP site was determined

by transposing

an actual critical

springstorm to the drainage

basin and maximizing

the precipitation

for potential

moisture.

Potential

snow cover and a critical

temperature

sequence

were developed

fordetermining

snowmelt

contribution

to flood runoff.The study area was divided into four major sub-basins

and synthetic

unit hydrographs

were developed

for each, using Snyder's

method, which is derived from the variousphysical

basin characteristics.

Unit hydrograph

peaks were also increased

by 25 percentand basin lag decreased

by one-sixth,

in accordance

with standard

Corps of Engineerpractice.

Snowmelt

and rainfall

excesses

were applied to unit hydrographs

and the resulting

hydrographs

determined

for each sub-basin.

Sub-basin

hydrographs

were then routed tothe project site by computer

program using the modified

Wilson method. Travel times forflood routing were taken from Corps of Engineers

recorded

travel times for large floods.Base flow was determined

from long-term

records of stream flow for nearby stations.

Base flow was then added to the total of the routed flood hydrographs.

The stage-discharge

curve at the MNGP Site was extended

above the range of historical

experience

by means of hydraulic

computations

based on the river channel downstream.

This was done by a series of backwater

computations

based on a range of discharges.

Backwater

computations

were made using water surface elevations

and theircorresponding

discharges

as determined

from the rating curve downstream

fromMonticello.

Using the discharges

and the resulting

water surface elevations,

a stagedischarge

curve was constructed

for the site.ResultsThe detailed

analysis

results are presented

in USAR Appendix

G. To summarize,

theanalysis

predicts

a probable

maximum discharge

of 364,900 cfs and a corresponding

peak stage of elevation

939.2 ft. msl. The flood would reach maximum river level inabout 12 days after the beginning

of high temperatures,

and it was estimated

the floodstage would remain above elevation

930.0 ft. msl for approximately

11 days.It is noted that the 12 day time period is for the river elevation

to reach the peak level.Other important

levels are the elevation

of the Intake Structure

(919 ft.) and Plant Grade(930 ft.). Based on USAR Appendix

G Exhibits

8 and 9, water elevation

of 919 ft. couldbe exceeded

at about the fourth day and water elevation

of 930 ft. could be exceeded

atthe eighth day.Page 4 of 11

2.2.2 Floods due to Ice Dam Build-UpFlooding

due to backwater,

usually caused by ice jams, was considered.

USAR,Appendix

G, Chapter II, Page G.2-5 states that two types of flooding

occur in the basin --open-water

flooding

and backwater

flooding.

Flooding

while open-water

conditions

prevail is caused by runoff producing

rains, or by melting snow, or by a combination

ofthe two. Flooding

because of backwater

is usually caused by ice jams. The most seriousflooding

throughout

the basin has been associated

with excessive

snowmelt

and rainfall.

Thus, the open-water

flooding

was considered

to be more limiting

that the backwater

flooding,

and was analyzed

in detail in the USAR.3.0 FLOOD MITIGATION

STRATEGYFlood protection

features

and flood mitigation

procedures

are described

below. The PMFevent is applicable

to all modes of operation

(i.e., power operation,

startup,

hotshutdown,

cold shutdown,

and refueling).

Flood Protection

requirements

necessary

toprevent external

flooding

or flood damage to Class I Structures

or Class II structures

housing Class I equipment,

are identified

in USAR Section 12.2.1.7.1.

Flood protection

features

utilized

at MNGP in the event of a PMF include both incorporated

(installed)

andtemporary

active and passive barriers.

MNGP does not rely upon any flood protection

features

external

to the immediate

plant area as part of the current licensing

basis thatprotect safety related systems,

structures

and components

from inundation

andstatic/dynamic

effects of external

floods.Incorporated

engineered

passive or active flood protection

features

are features

that arepermanently

installed

in the plant that protect safety related systems,

structures,

andcomponents

from inundation

and static/dynamic

effects of external

flooding.

Examplesinclude external

walls and penetration

seals that are permanently

incorporated

into aplant structure.

Temporary

passive or active flood protection

features

at MNGP include portable

pumps,sandbags,

plastic sheeting,

steel plates, levees, etc., that protect safety related systems,structures

and components

from the effects of external

flooding.These

features

aretemporary

in nature, i.e., they are installed

prior to design basis external

flood levelsattaining

specific

levels.The following

Class I and II structures

are protected

from flooding

up to 939.2 ft. msl:1. Reactor Building

(including

High Pressure

Coolant Injection

(HPCI) structure)

2. Turbine Building3. Intake Structure

(including

access tunnel)4. Off-gas Stack and Compressed

Gas Storage Building5. Radwaste

Building6. Diesel Generator

Building7. Plant Control and Cable Spreading

Structure

8. Emergency

Filtration

Train (EFT) Building9. Diesel Fuel Oil Pump House10. Diesel Oil Storage TankPage 5 of 11

Flood preparations

at the site begin with a flood surveillance

procedure

(Reference

6).During the time period of interest

the surveillance

was initiated

by procedure

annually

inthe late winter. The procedure

is currently

performed

monthly for river level predictions

and an annual performance

includes

inventory

and inspection

in addition

to the riverlevel prediction.

The purpose of this procedure

is to determine

if the potential

for plantflood exist prior to and during the spring flooding

season to ensure adequate

steps aretaken to protect the plant if the potential

for flooding

exists. The actions taken inReference

6 are summarized

as follows:* Based on the nature of the design basis flood (heavy snow pack,thawing/freezing

cycle, coupled with heavy rain) the flood scenario

is slowdeveloping

and flood levels are generally

predictable.

Reference

6 determines

the potential

for flooding

based on forecast

information

from the NationalWeather Service and river level monitoring.

Procedure

A.6 (Reference

7), Noteto Step 5.2.1, indicates

that the National

Weather Service Flow Exceedance

Probability

Forecast

on internet

http://www.crh.noaa.qov

is used to forecast

riverelevations.

The information

for the St. Cloud and Anoka measurement

stations

isprovided

on a weekly basis in terms of the probability

that the river flow willexceed a given flow rate. The prediction

information

at the website is for the next90 days based on current conditions.

A flow discharge

curve in Reference

7 isused to determine

predicted

river water elevation

based on the predicted

flowrate. Given the conditions

that precede the PMF; i.e., snowpack

with thawing andrefreezing,

it is reasonable

to expect that the responsible

individuals

at the plant(engineering,

operations,

management)

would be keenly aware of the need tomonitor river water elevations

for predicted

flood conditions.

Increased

monitoring

and use of the predictive

National

Weather Service tools wouldincrease

the time available

to implement

flood protective

actions." Flood preparation

measures

are taken as part of Reference

6 to ensure that floodprotection

materials

such as sandbags,

steel plates, covers and gaskets,

andplugs are available.

Contact information

for vendors that would be used as part offlood preparation

activities

are confirmed

to still be valid. This contact information

includes

vendors that would be involved

with construction

of the bin wall andearthen levee. These actions are implemented

even if flood conditions

are notpredicted.

A memorandum

of understanding

is in place with VeitVeit

& Company,a local construction

firm, to provide construction

related services

in the event of asite emergency,

and would cover activities

such as construction

of the earthenlevee." In the event that the potential

for flood conditions,

dump trucks and excavators

are ensured to be available

for installation

of the levee, and a detailed

flood planis developed.

MNGP Procedure

A.6 (Reference

7), "Acts of Nature,"

(Part 5 -.External

Flooding)

stipulates

the actions to be taken in the event flood waters are predicted

to exceedelevation

918 ft. Revision

41 through Revision

45 of Procedure

A.6 (Reference

7) werein effect during the period of time from February

29, 2012 through February

15, 2013.Revision

41 was issued on February

28, 2012 and Revision

45 was issued on February14, 2013.Page 6 of 11

The following

summarize

the actions in A.6 based on the different

predicted

flood waterelevations.

  • Step 5.2.8, river level is predicted

to exceed elevation

918 ft. Notification

ofUnusual Event is declared.

Actions are taken to protect equipment

such as thedischarge

structure

substation.

  • Step 5.2.9, river level is predicted

to exceed elevation

919 ft. Actions are taken toprotect the Intake Structure

from flooding.

As noted above the Intake Structure

isat elevation

919 feet.* Step 5.2.10, river level is predicted

to exceed elevation

921 ft. An Alert isdeclared

and the plant is shutdown

and cooled down to cold shutdownconditions.

Actions are taken to ensure a supply of service water is available.

  • Step 5.2.11, river level is predicted

to exceed elevation

930 ft. The bin walls andearthen levee are built. Steel plates are installed

on the outside roof areas of theIntake Structure.

Yard drains and other paths that could result in a water pathwaythat bypasses

the levee are closed. An alternate

access route to the plant isprovided

from higher ground in the event that the normal access road is flooded.The levee is designed

to provide flood protection

up to a river elevation

of 941 ft.Backup flood protection

to the levee can be provided

by closing up the variousbuildings

using steel plates, installing

sand bags, etc. It is noted that the levee isidentified

in the procedure

as the preferred

option but, per the procedure,

thebackup flood protection

can be used in lieu of constructing

the levee. This isdiscussed

in more detail below." The remaining

Steps 5.2.12 and 5.2.13 provide additional

backup floodprotection

for predicted

river elevations

above 930 feet. These are backup floodprotection

measures

to the levee.As described

in A.6, Step 5.2.11, Note 2, the preferred

flood protection

measure isconstruction

of a levee around the plant. The decision

to use the levee as the preferred

flood protection

is based on a recommendation

from the US Army Corps of Engineers

(USACE),

letter dated November

8, 2001. This USACE letter is referred

to in the Basesdiscussion

for Part 5 of Reference

7. However,

Reference

7 includes

an option forproviding

flood protection

in lieu of construction

of the levee. This optional

floodprotection

means involves

installing

barriers

(steel plates, etc.), sandbags,

and sealingpenetrations.

Resource

loaded schedules

developed

in support of the A.6 procedure

demonstrate

that the activities

were achievable

in the time required.

Recent simulations

and demonstrations

confirm the construction

time for the bin wall, steel plate installation

and sand bagging.As shown on Figure 13.10 of Reference

7, construction

of the levee includesconstruction

of a bin wall to the immediate

east and west of the Intake Structure.

The binwall was added as part of Revision

41 to A.6 on February

28, 2012. Prior to Revision41, the levee was made entirely

of earthen material.

The decision

to use the bin wall wasbased on an analysis

performed

by Short Elliot Hendrickson,

Inc., (SEH) (Reference

8).As part of this same change, the configuration

of the levee was modified

from a ringlevee entirely

around the plant to a horseshoe

design that ties into areas of the site thatPage 7 of 11

are above the peak PMF water elevation.

The recommendation

to use the bin wall wasmade as part of Reference

8 after considering

various options for the tie to the IntakeStructure.

Reference

8 included

the following

recommendations:

  • Secure a borrow source of levee fill within 15 minutes of the site or purchase

andstore on site.* Purchase

bin wall materials,

assemble

in modules to reduce installation

timeframe, and store on site.The deficiencies

identified

in Reference

5 have subsequently

been addressed.

Inaddition

to the noted deficiencies,

other areas were also identified

for improvement

tothe plant and procedures.

All of these areas for improvement

were entered into the plantcorrective

action system.Additional

actions have been implemented

to further improve the flood protection

at thesite. These additional

actions are summarized

below:* Bin wall materials

have been procured

and are now stored on site. Theprocurement

of the bin walls took approximately

eight weeks; however,

this wastreated as a normal procurement.

The bin walls were supplied

by ContechEngineered

Solutions.

Based on discussions

with Contech Engineered

Solutions

it is estimated

that the bin wall sections

could be provided

in approximately

14days in an emergency

situation.

As discussed

above, in the event that the binwalls cannot be constructed

due to unavailability

of materials,

flood protection

could still be provided

as stipulated

in the procedure

using the sandbag and floodbarrier option. This option is independent

of the levee and bin walls.* Levee materials

have been procured

and are now stored on site. Levee materials

were delivered

to the site within four 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shifts.* External

flood surveillance

procedure,

1478, (Reference

6) has been improved

toincrease

the frequency

of river level monitoring

during potential

floodingconditions.

The additional

river level monitoring

ensures timely plant preparation

for a potential

flood. The increased

river level monitoring

serves to provide earlierwarning of predicted

flood levels and increases

available

time to implement

protective

actions.* Procedure

A.6 (Reference

7) has been revised to improve the procedure

clarity,remove unnecessary

steps, and ensure completeness

of protective

actions." Detailed

work instructions

have been developed

to implement

actions in A.6.The work instructions

provide the technical

detail necessary

to implement

therequired

action. Pre-staging

the work instructions

prior to the event reduces therequired

time frames to implement

the required

actions in A.6.* Monticello

conducted

a self-assessment

of the site flood protection

response

totake an additional

critical

review. The self assessment

was performed

by a teamof Xcel and contract

professionals

experienced

in areas of flood protection.

Page 8 of 11

Specific

areas for improvement

were identified

during the self assessment

andwere entered in the corrective

action program and are being actively

addressed.

4.0 FLOOD MITIGATION

STRATEGY

-FURTHER DEMONSTRATIONS

Table top walkthroughs

of procedure

A.6 have been performed

to demonstrate

feasibility

of performance

of the required

actions.

A detailed

schedule

is developed

for the actionsin A.6 using input from the site departments

who would execute the actions.

Theschedule

shows actions to be performed,

time frames, and sequencing,

anddemonstrates

that the actions can be completed

within the available

time period.Detailed

work instructions

have been developed

to implement

the actions in A.6. Pre-staging of the work instructions

reduces the overall time to perform the tasks byremoving

the time associated

with work planning,

identifies

that materials

that may beneeded to accomplish

the work, and identifies

any potential

interferences

orimpediments

to completing

the required

task ahead of time.As described

in Section 3.0, above, the materials

to construct

the bin wall sections

andthe earthen levee have been procured

and are stored on site. As previously

discussed,

amemorandum

of understanding

(MOU) is in place with VeitVeit

& Company,

a localconstruction

firm, to provide equipment

and services

for construction

of the bin wall andearthen levee.Reasonable

simulation

of construction

of several of the actions believed

to be more timeconsuming

was performed

in order to demonstrate

that the actions could be performed

within the available

time frame. Specific

actions examined

were construction

and fillingof the bin walls, construction

of the steel plates around the roof of the Intake Structure,

and filling of sandbags.

The results from these reasonable

simulations

are summarized

below.* Construction

of bin walls. For the reasonable

simulation,

approximately

5% of thetotal bin wall sections

were constructed

and filled. The simulation

was contracted

to Veit to add realism per our MOU and exercise

the mobilization

of personnel.

The reasonable

simulation

took 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> for one crew to fully construct

and fill.Based on using six crews, available

per our MOU, to construct

and fill the binwalls during implementation

of procedure

A.6, this would indicate

that the entirebin wall sections

could be fully constructed

within 1.4 days. Accounting

for issuessuch as excavation,

inclement

weather,

security

concerns,

coordination,

totalconstruction

time of four days is reasonable.

  • Steel plates around roof of Intake Structure.

As part of procedure

A.6 steel platesare attached

to the wall of the Intake Structure

with anchors and the seamsbetween the plates welded to form part of the flood protection

barrier.

For thereasonable

simulation,

approximately

20% of the plates were installed

on amock-up.

The reasonable

simulation

took 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> and 11 minutes.

Based on onewelder all of the plates could be installed

within 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />. Using two welderswould reduce this time to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Additional

welders would reduce this timeeven more. This time period is much less than the available

time and providesmargin for working in inclement

weather conditions.

Page 9 of 11

Sandbagging.

Per procedure

A.6, approximately

100,000 sandbags

are filled.Sandbags

are used in several steps in A.6 to seal openings,

provide backupflood protection.

Sandbags

are critical

in the event that the sandbag and floodbarrier option were implemented

in A.6 in lieu of the levee option. Reasonable

simulation

indicates

that 600 sandbags

can be filled per hour using one machineand 8 people. Go-Baggers

are a manual bagging apparatus

with which anindividual

can fill 55 bags an hour. With one machine and 20 people workingaround the clock, the 100,000 sandbags

can be filled in 2 1/2 days. Reasonable

simulation

also showed that a steel double door can be sandbagged

by fivepersonnel

in 34 minutes.

Furthermore,

it was shown that laying lumber andsandbagging

1 EDG room can be accomplished

by 14 personnel

in four hours.In the three cases discussed

above, the reasonable

simulation

concluded

that therequired

actions can be accomplished

within the available

time frame.5.0 CONCLUSIONS

The following

conclusions

are drawn from the above discussion:

  • The postulated

flood scenario

for the MNGP is considered

to be veryconservative.

The methodology

employed

provides

conservative

results.

Thiscan be seen from the comparison

of river flow rates and water elevations

inTable 1 in Section 2.1, above.* The flood is a relatively

slow developing

evolution

that allows time for plant staffto monitor,

predict and implement

appropriate

actions to provide the requiredflood protection.

  • The flood mitigation

procedure

clearly identifies

actions for plant staff toimplement

to provide the required

flood protection.

  • In the event that the levee were not able to be constructed

due to not having thebin wall materials

available,

the procedure

provides

an optional

approach

toimplement

flood protection

without relying on the levee and bin wall system.Table top review of the steps to implement

this optional

means of floodprotection

demonstrated

that the protection

could be provided

within theavailable

time.* Subsequently

actions have been taken to procure the bin wall and leveematerials.

Reasonable

simulation

has demonstrated

that the levee and bin wallsystem can be installed

well within the available

time.Page 10 of 11

6.0 REFERENCES

1. Monticello

Nuclear Generating

Plant, Updated Safety Analysis

Report (USAR), Revision

29.2. Department

of the Army, Office of the Chief of Engineers,

the U.S. Army Corps ofEngineers,

Engineer

Circular

No. 1110-2-27,

Enclosure

2, "Policies

and Procedures

Pertaining

to Determination

of Spillway

Capacities

and Freeboard

Allowances

for Dams,"dated August 1, 1966.3. NRC Letter to Licensees,

dated March 12,2012,

"Request

for Information

Pursuant

to Title10 of the Code of Federal Regulations

50.54(f)

Regarding

Recommendations

2.1,2.3,

and9.3 of the Near Term Task Force Review of Insights

from the Fukushima

Daiichi Accident"

(ADAMS Accession

No. ML 12053A340).

4. NEI 12-07, Revision

O-A, "Guidelines

for Performing

Verification

Walkdowns

of Plant FloodProtection

Features,"

dated May 2012 (ADAMS Accession

No. ML 12173A215).

5. Xcel Energy Letter L-MT-1 2-097, "MNGP Final Response

to NRC Request for Information

Pursuant

to 10 CFR 50.54(f)

Regarding

the Flooding

Aspects of Recommendation

2.3 of theNear-Term

Task Force Review of Insights

from the Fukushima

Dai-ichi

Accident,"

datedNovember

27, 2012.6. Procedure

1478, "External

Flood Surveillance,"

Revision

7. [Revision

7 is the procedure

revision

currently

in effect. During 2012, Revisions

4 through 6 was in effect and theprocedure

was titled "Annual Flood Surveillance."]

7. Procedure

A.6, "Acts of Nature,"

Revision

46. [Revision

46 is the procedure

revisioncurrently

in effect. When used, previous

revision

numbers are identified

in the text.]8. Xcel Contract

No. 38398, SEH No. MONNE 117980, "Monticello

Nuclear Generation

Plant,External

Flooding

Plan Update: Alternative

Analysis

and Final Design Report,"

datedJanuary 5, 2012.Page 11 of 11

Enclosure

4Monticello

Nuclear Generating

Plant"Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at theMonticello

Nuclear Generating

Plant based on At-site Data for Spring and SummerAnnual Peak Floods"12 Pages Follow

Annual Exceedance

Probability

Estimates

for Mississippi

River Stages at the Monticello

NuclearGenerating

Plant based on At-site Data for Spring and Summer Annual Peak FloodsDavid S. Bowles and Sanjay S. ChauhanRAC Engineers

& Economists

June 28, 2013Purpose:To estimate

the annual exceedance

probabilities

(AEPs) for Mississippi

River Stages 917, 930 and 935 ft.NGVD 29 at the Monticello

Nuclear Generating

Plant (MNGP) using at-site data for spring and summerfloods.These estimates

are intended

to improve on the previous

annual peak flood estimates

that weresubmitted

on April 8, 2013. The previous

estimates

were was based on an at-site flood frequency

curveconstructed

using a) a conservatively

assigned

AEP to the Harza spring PMF, and b) at-site floodfrequency

estimates

obtained

from a drainage-area

weighted

interpolation

between provisional

USGSannual peak flood frequency

estimates

for the upstream

and downstream

Mississippi

River gages at St.Cloud and Elk River, respectively.

Given more time, we recommend

that a Monte Carlo rainfall-runoff

approach

should be used to developestimates

of extreme flood frequencies

to make use of regional

precipitation

data and a morephysically-based

transformation

of rainfall

to runoff, including

snow melt and explicit

consideration

ofuncertainties.

Available

Information:

Observed

mean daily flows at the following

locations:

1) Station Number 05270700

Mississippi

River at St. Cloud, MN with a period of record from 1989to 2012.2) Station Number 05275500

Mississippi

River at Elk River, MN with a period of record from 1916to 1969.3) Monticello

Nuclear Generating

Plant (at-site)

with a period of record from 1970 to 2012.Flood frequency

estimates

of annual peak discharges:

4) Provisional

2013 USGS annual peak discharge

flood frequency

analyses

with estimates

of AEPsranging from 1 in 1.005 to 1 in 500 based on maximum daily flow rates for the annual peakflows:1

a. Station Number 05270700

Mississippi

River at St. Cloud, MN with drainage

area of13,320 sq. miles.b. Station Number 05275500

Mississippi

River at Elk River, MN with drainage

area of14,500 sq. miles.Probable

maximum flood (PMF) peak discharge

and stage estimates:

5) Harza 1969 (spring)

PMF peak discharge

and river stage at the Monticello

Nuclear Generating

Plant -1912 Datum.6) Bechtel 20121 spring and summer PMF peak discharges

and river stages at the Monticello

Nuclear Generating

Plant -NAVD88 Datum.Discharge

rating relationships:

7) Harza 1969 relationship

between river stage (1912 Datum) and river discharge

(cubic feet persecond, cfs) over the range 26,000 to 437,000 cfs.8) Ops manual equation

between river discharge

(cubic feet per second, cfs) up to 4,000 cfs andriver stage (NGVD 29 Datum): Q = 122(Stage

-901)2.2.Datum conversions

for river stages:9) NGVD 29 Datum = 1912 Datum -0.36 ft.10) NGVD 29 Datum = NAVD 88 Datum -0.4 ft.Procedure:

The following

two approaches

were examined

for developing

improved

at-site estimates

of annualexceedance

probabilities

(AEPs) for the spring and summer annual floods in the Mississippi

River at theMNGP:1) Drainage-area

weighted

interpolation

of flood frequency

estimates

for the upstream

anddownstream

USGS gages: Similar to the April 8, 2013 approach,

an at-site flood frequency

curvewas obtained

from a drainage-area

weighted

interpolation

between flood frequency

estimates

for the upstream

and downstream

Mississippi

River gages at St. Cloud and Elk River,respectively.

However,

this revised approach

was conducted

separately

for spring and summerannual peak floods and it did not conservatively

assign an AEP to the Harza PMF as was done inthe April 8, 2013 approach.

Instead the flood frequency

curve was extrapolated

to extremefloods thus providing

estimate

of the AEPs for the spring and summer PMF peak flow estimates

and for the three elevations

of interest.

1 The report, Bechtel 2012 spring and summer PMF peak discharges

and river stages at the Monticello

NuclearGenerating

Plant -NAVD88 Datum, has been provided

to NSPM. This study provides

bounding

estimates

to sitepeak flood elevations

applicable

to the development

of annual exceedance

probabilities

at the Monticello

NuclearGenerating

Plant.2

2) Flood frequency

analysis

based on at-site flow data: A flood frequency

analysis

was conducted

on the available

at-site streamflow

data for the period 1970 to 2012 with extrapolation

toextreme floods. This provided

estimate

of the AEPs for the three elevations

of interest

and forthe PMF peak flow estimates

for spring and summer annual peak floods.Both of the above approaches

included

estimating

separate

flood frequency

relationships

for spring andsummer annual peak floods. Data for estimating

these relationships

were obtained

using the following

definitions

of spring and summer floods based on discussions

in the Hydrologic

Atlas of Minnesota

(Stateof Minnesota

1959) and examination

of the flow records:1) Spring annual peak floods generally

peaked in the period March to May, but if it was clear fromexamination

of the hydrograph

that a snow melt flood event peaked in June then that peak wasused.2) Summer annual peak floods generally

peaked in the June to early October period, but floodpeaks occurring

in June, which were clearly associated

with snow melt events, were excluded

asmentioned

in 1). Since the recession

limb of the annual snow melt hydrograph

extends throughthe summer, the peak flow rates for summer floods, which are associated

with convective

storms, are dependent

to some degree on the magnitude

of flow on this recession

limb at thetime of the summer flood.The two approaches

are discussed

in more detail below.Approach

1): Drainage-area

weighted

interpolation

of flood frequency

estimates

for the upstream

anddownstream

USGS gagesThe provisional

USGS annual peak flow flood frequency

estimates

for the Mississippi

River gages at St.Cloud and Elk River were verified

using USGS flood frequency

software

following

Bulletin

  1. 17B floodfrequency

analysis

procedures

(USGS 1982). The following

softwares

were applied to the maximumdaily annual peak streamflow

data assembled

by the USGS to verify their results:1) PeakFQ: Bulletin

  1. 17B procedure

based on method of moments parameter

estimation

for a LogPearson Type 3 probability

distribution

(Flynn et al 2006)2) PeakfqSA:

The more efficient

Expected

Moments Algorithm

(EMA) applied to the Bulletin

  1. 17Bmethodology

(Cohn 2012)Following

the USGS provisional

analysis,

the Bulletin

  1. 17B (PeakFQ)

software

was applied to the St Cloudgage and the EMA (PeakfqSA)

software

was applied to the Elk River gage for the verification

step.Separate

flood frequency

analyses

were then conducted

for spring and summer annual peak flow dataat the St. Cloud and Elk River USGS gages. The maximum daily annual peak streamflow

data wereassembled

by the USGS and provided

with their provisional

flood frequency

analyses.

These datacomprised

a mixture of spring and summer floods. These data were separated

into spring and summerfloods and mean daily peak flow data were obtained

from USGS flow records at both gages for thosecases that were not covered by the maximum daily annual peak streamflow

data assembled

by the3

USGS. An additional

year (2012) of data was added for the St Cloud gage. Maximum daily annual peakflows were estimated

from mean daily annual peak flows for those data not included

in the USGSprovisional

analyses

using regression

relationships

established

between maximum daily annual peakflow data and mean daily annual peak flow data for spring and summer flows for each gage.The PeakfqSA

software

containing

improved

EMA parameter

estimation

(Stedinger

2013) was applied toboth spring and summer flood data for both gages. No outliers

were identified.

The EMA softwareprovided

AEP estimates

from I in 1.0001 to I in 10,000. Estimates

of annual peak discharge

on theMississippi

River at the MNGP were then obtained

based on linear interpolations

between variousfrequency

(AEP) estimates

developed

for the St Cloud and Elk River gages as a function

of drainage

areawith the drainage

area at the MNGP being 14,071 sq. miles. This interpolation

the procedure

is thesame as developed

for the April 2013 AEP estimates.

The at-site annual peak discharge

estimates

wereconverted

to at-site river stages using a combination

of the Harza and Ops Manual equation

ratingcurves shown in Figure 1.Examination

of the relationship

between flood estimates

for various AEPs and drainage

area shown inFigure 2 showed an inconsistent

relationship

that was increasing

or decreasing

with drainage

area. As aresult we have not relied on these estimates

in favor of using the flood frequency

estimates

obtainedfrom analysis

of at-site data in the second approach.

947942937* 9320JS927 _______.5922 __________

0JS917912907 1 1 _________

9021100 1,000 10,000 100,000 1,000,000

Discharge

In cfs-Ops Man Eqn, Q= 122(Stage-901)^2.2

-Harza Discharge

Rating -- Transition

-.Final curveFigure 1. Combined

Harza and Ops Manual Equation

stage-discharge

rating curve4

80,00070,00060,00050,0000 40,000E.30,00020,00010,000Interpolation

of at-site quantiles

-TFU-------- ----- ----*0.995-0.99-0.95-0.9.--0.6667ý0.5--*-0.4292-o-0.2-0.04-0.02-.--0.01-0-0.005-4-0.002-MNGS5,000U13,00013,50014,000Drainage

Area (sq. miles)14,600IFigure 2. Relationships

between flood estimates

for various AEPs and drainage

area for Approach

1Approach

2): Flood frequency

analysis

based on at-site flow dataThe second approach

is based on extrapolation

of flood frequency

relationships

developed

from at-siteflow data. The mean daily annual peak stages were obtained

for spring and summer annual peak floodsfollowing

the process summarized

above. Since only single observations

have been recorded

for eachday it was not possible

to obtain maximum daily annual peak stages. The daily annual peak stages wereconverted

to daily annual peak flows for spring and summer floods using the combined

rating curveshown in Figure 1. The EMA (PeakfqSA)

software

was applied to estimate

the flood frequency

relationships

for spring and summer annual peak floods. No outliers

were identified

for the springseason, but one low outlier (2,416 cuffs) was identified

for the summer season using the MultipleGrubbs-Beck

Test) low outlier identification

method. The EMA software

provided

AEP estimates

for therange 1 in 1.0001 to 1 in 10,000.Annual Exceedance

Probability

Estimates:

Figures 3 and 4 show the resulting

flood frequency

estimates

for the spring and summer annual peakfloods obtained

from the second approach.

The annual peak discharge

is plotted on a Log scale andAEPs are plotted on a z-variate

scale (corresponding

to a Normal probability

distribution).

In addition

to5

Monticello

NGS -Spring1,000,000

B el 2012 PMF estim tean--- ----a--T9. nbrPes-Tma

--e .--., e.0l vafion 93SEl, -atlon 930100,000 ...... ...-, -..-'":! ...

""h...=-- -- ~ ~... :...........

10,000 v-Exce dance Probability

1E I 1E-1 1E-2 E-3 1E-4 iE-5 1E-6 1E-7 1E-8 1 91,000 .I I I" I 1- 1-4.0 -3.0 -2.0 -1.0 0.0 1.0 2.0 3.0 4.0 5.0 6.0z-variate

Figure 3. Spring Annual Peak Flood Frequency

(approximate

mean shown by black dashed line)6

Monticello

NGS -Summer1,000,000

N024)4)4)a.100,00010,0001,000-4.0 -310 -2.0 -1.0 0.0 1.0 2.0 3.0 4.0 5.0 6.0z-variate

Figure 4. Summer Annual Peak Flood Frequency

(approximate

mean shown by black dashed line)7

providing

median (50th percentile)

and approximate

mean2 estimates,

the 20% (40th and 60thpercentiles),

40% (30th and 70th percentiles),

60% (20th and 80th percentiles),

80% (10th and 90thpercentiles),

and 90% (5th and 95th percentiles)

confidence

interval

estimates

are provided

with linearextrapolation

to smaller AEPs beyond 1 in 10,000. The site elevations

of 917, 930 and 935 are shown byhorizontal

lines based on the NGVD 29 datum matching

the datum used on the site drawings.

Also theHarza and Bechtel PMF estimates

are shown by horizontal

lines corresponding

to peak elevations

forthese events.It is noted above that only single daily river stage observations

have been recorded

at site and therefore

it was not possible

to obtain maximum daily annual peak stages. Since the difference

between meandaily and maximum daily peak stages decreases

with smaller AEPs, it is likely that the flood frequency

relationships

are slightly

steeper than shown. This effect would tend to make AEP estimates

forextreme flows slightly

conservative

(i.e. slightly

larger) than of this effect were removed.Tables 1 and 2 contain numerical

AEP estimates

for spring and summer annual peak floods, respectively,

for river stages 917, 930 and 935 ft. NGVD 29 for the median (50th percentile)

and approximate

mean,and for various confidence

percentiles.

Table 1. Spring Annual Peak Flood Frequency

Estimates

Elevation

91795th I ge 1 84th 1 0th I 70th I 60 I Median 50e 5th Approx MeanAEP Estimates

3.4E-02 2.5E-02 2.0E-02 1.7E-02 1.2E-02 8.9E-03 6.3E-03 5.9E-07 7.9E-03i in Tyears 29 40 51 59 82 112 158 1,680,000

127Elevation

93095t' 90 84th 80' 70 60h Median 50 5t Approx MeanAEP Estimates

7.OE-06 7.6E-07 7.5E-08 1.7E-08 < 1E-9 < 1E-9 < 1E-9 < 1E-9 < 1E-91inTyears

143,0001

1,320,0001

13,400,0001

60,500,0001

>1E+9 I >1E+9 [ >1E+9 I >1E+9 [ >1E+9I _Elevation

935F-9 90 o 84th 806 70& 60' Median 506' 51 Approx MeanAEP Estimates

4.3E-07 2.OE-08 < 1E-9 < 1E-9 < 1E-9 < 1E-9 < 1E-9 < 1E-9 < 1E-91 in T years 2,350,000

51,100,000

>1E+9 >1E+9 >1E+9 >1E+9 >1E+9 >1E+9 >1E+9Table 2. Summer Annual Peak Flood Frequency

Estimates

___Elevation

9179Sth 90t 84th 80 th 70 th 60d Median 50th 5th Approx MeanAEP Estimates

1.9E-02 1.3E-02 8.8E-03 7.2E-03 4.4E-03 2.8E-03 1.7E-03 8.5E-07 3.OE-031 in Tyears 52 79 113 140 225 358 590 1,180,000

328_ _Elevation

930_95_ 90go 84th 80eh 70th 60e Median 506h 5th Approx MeanAEP Estimates

2.1E-04 4.3E-05 8.8E-06 3.1E-06 2.4E-07 1.5E-08 < 1E-9 < 1E-9 1.6E-061in Tyears 4,7201 23,4001 11,00 324,000 4,160,000

65,100,000

>1E+9 >1E+9 641,000I-_ Elevation

93595h 90 o 841 80h 70 60'h Median 50' 5 h Approx MeanAEP Estimates

6.1E-05 7.9E-06 9.7E-07 2.5E-07 8.9E-09 < 1E-9 < 1E-9 < 1E-9 2.OE-07I in T years 16,500 127,000 1,030,000

4,000,000

112,000,000

>1E+9 >1E+9 >1E+9 1 4,930,000

2 The approximate

mean estimates

were obtained

by weighting

the various percentile

estimates

by theirrespective

intervals

of probability

that each represents.

For example,

the 60th percentile

represents

the intervalbetween the mid-points

of the 50th -60th and 60th -70th percetile

intervals

and hence is weighted

by thedifference

between the percentiles

associated

with the mid-points

of these two intervals,

i.e. 0.65-0.55

= 0.10.8

The following

is a summary of the median estimates

and ranges (Upper -95th percentile

and Lower -5thpercentile)

of the AEP estimates

for the river stages of 917, 930 and 935 ft. NGVD 29 at the Monticello

Nuclear Generating

Plant for spring and summer annual peak floods and for the Harza and Bechtel PMFestimates.

The April 8, 2013 spring estimates

are shown in italics for comparison.

The comparison

shows that these estimate

were conservative

relative

to those obtained

using the second approach.

Spring Floods:Elevation

917 ft. NGVD 29:* Upper (95th): 3.4E-02 (1 in 29/year)

4.OE-02 (1 in 25/year)" Median (50th): 6.3E-03 (1 in 158 /year) 7.2E-03 (1 in 140/year)

  • Lower (5th): 5.9E-07 (1 in 1,680,000

/year) 9.5E-04 (1 in 1,100/year)

Elevation

930 ft. NGVD 29:* Upper (95th): 7.OE-06 (1 in 143,000 /year) 1.6E-04 (1 in 6,300/year)

  • Median (50th): < 1E-9 (1 in >1E+9 /year) 1.6E-05 (1 in 61,000/year)
  • Lower (5th): < 1E-9 (1 in >1E+9 /year) 2.2E-06 (1 in 460,000/year)

Elevation

935 ft. NGVD 29:* Upper (95th): 4.3E-07 (1 in 2,350,000

/year) 3.OE-05 (1 in 33,000/year)

  • Median (50th): <1E-9 (1 in >1E+9 /year) 3.1E-06 (1 in 330,000/year)
  • Lower (5th): <1E-9 (1 in >1E+9 /year) 3.4E-07 (1 in 2,900,000/year)

The Harza Spring PMF AEP estimates

are shown below with the April 8, 2013 AEPs assigned

to the Harza(spring)

PMF shown in italics for comparison.

  • Upper (95th): 5.9E-08 (1 in 16,900,000)

1 in 10,000,000

  • Median (50th): < 1E-9 (1 in >1E+9 /year) 1 in 1,000,000

" Lower (5 h): <1E-9 (1 in >1E+9 /year) 1 in 100,000The estimates

of AEPs assigned

to the Harza PMF in the April 8, 2013 work are therefore

confirmed

tobe conservative

(i.e. larger than now estimated).

The AEP Bechtel spring PMF estimates

are shown below:" Upper (95th): 1.8E-08 (1 in 54,500,000)

  • Median (50th): < 1E-9 (1 in >1E+9 /year)* Lower (5th): < 1E-9 (1 in >1E+9 /year)9

Summer Floods:Elevation

917 ft. NGVD 29:* Upper (95th):* Median (50th):* Lower (5th):1.9.4E-02

(1 in 52 /year)1.7E-03 (1 in 590 /year)8.5E-07 (1 in 1,180,000

/year)Elevation

930 ft. NGVD 29:* Upper (95th):* Median (50th):" Lower (5th):2.1E-04 (1 in 4,720 /year)< 1E-9 (1 in >1E+9 /year)<1E-9 (in >1E+9/year)

Elevation

935 ft. NGVD 29:000Upper (95th):Median (50th):Lower (5th):6.1E-05 (1 in 16,500 /year)< 1E-9 (1 in >1E+9 /year)< 1E-9 (1 in >1E+9/year)

The AEP Bechtel summer PMF estimates

are shown below:* Upper (95th):* Median (50th):* Lower (5th):5.7E-04 (1 in 1,750/year)

3.3E-08 (1 in 29,900,000

/year)< 1E-9 (1 in >1E+9/year)

The second approach

used to develop these revised AEP estimates

is preferred

to the initial approachused to develop our April 2013 estimates

for the following

reasons:1) It separates

the spring and summer flood events.2) It relies on at-site date rather than a drainage-area

weighted

interpolation

of AEP estimates

atupstream

and downstream

Mississippi

River USGS gages.3) It does not rely on an assignment

of an AEPtothe

PMF.A graphical

comparison

of the April 2013 and the current estimates

is presented

in Figure 5. It indicates

that the April 2013 AEP estimates

are likely overly conservative

as a result of the assignments

of theAEPs to the Harza PMF.Figure 5 is similar to Figure 3 but includes

the USNRC (2013) AEP estimates:

9.37E-05

for Elevation

930and 2.72E-05

for Elevation

935 (based on 6.65E-05/year

for Elevation

930-935).

The NRC estimates

exceed our current 95th percentile

estimates

but are very similar to our April 2013 95th percentile

estimates,

which were based on assigning

an AEP of 1E-5 to the Harza PMF. According

to USNRC (2013)their estimates

are based on flood frequency

estimates

from the Monticello

USAR and IPEEE but we arenot clear about the origin of those estimates

or the curve fitting approach

that was used by the USNRC(2013). Therefore

it is not possible

to make a more informed

comparison

with our estimates;

although

it10

Monticello

NGS -Spring1,000,000

z99LaJtU.X100,00010,0001,000-4.0-3.0 -2.0 -1.0 0.0 1.0 2.0 3.0 4.0 5.0z-variate

-April 2013 Best Estimate

--April 2013 Upper Estimate

--April 2013 Lower Estimate

  • NRC Estimates

-Approx Mean6.0Figure 5. Comparison

of the current Spring Annual Peak Flood Frequency

with the April 2013 estimates

and the NRC (2013) estimates

11

would appear that our estimates

rely on more recent site-specific

data than the NRC had available.

Inaddition

they use the Bulletin

  1. 17B flood frequency

approach,

which is the standard

for flood frequency

analysis

in the US. We also used the improved

EMA parameter

estimation

approach

that will beincluded

in the revision

of the Bulletin

  1. 17B procedure

that has been drafted.However,

we recommend

that a Monte Carlo rainfall-runoff

approach

be considered

to developestimates

of extreme flood frequencies

with explicit

consideration

of uncertainties

in the future. Thisapproach

can be expected

to provide improved

estimates

based on the use of regional

rainfall

analysis,

and a more physics-based

representation

of the rainfall-runoff

(including

snow melt) processes

forextreme floods than is associated

with the current extrapolation

approach.

References

Cohn, T. 2012. User Manual for Program PeakfqSA

Flood-Frequency

Analysis

with the ExpectedMoments Algorithm

DRAFT. September.

Flynn, K.M., Kirby, W.H., and Hummel, P.R., 2006, User's Manual for Program PeakFQ Annual Flood-Frequency

Analysis

Using Bulletin

17B Guidelines:

U.S. Geological

Survey, Techniques

andMethods Book 4, Chapter B4; 42 pgs.State of Minnesota.

1959. Hydrologic

Atlas of Minnesota.

Davison of Water, Department

ofConservation,

State of Minnesota.

Stedinger,

J.R. V. Griffis,

A. Veilleux,

E. Martins,

and T. Cohn. 2013. Extreme Flood Frequency

Analysis:

Concepts,

Philosophy

and Strategies.

Proceedings

of the "Workshop

on Probabilistic

FloodHazard Assessment

(PFHA)" sponsored

by the U.S. Nuclear Regulatory

Commission's

Offices ofNuclear Regulatory

Research,

Nuclear Reactor Regulation

and New Reactors

in cooperation

withU.S. Department

of Energy, Federal Energy Regulatory

Commission,

U.S. Army Corps ofEngineers,

Bureau of Reclamation

and U.S. Geological

Survey organized.

Rockville,

Maryland.

January 29 -31.USGS (US Geological

Survey).

1982. Guidelines

for Determining

Flood Flow Frequency.

Bulletin

  1. 17B,Hydrology

Subcommittee,

Interagency

Advisory

Committee

on Water Data, Office of Water dataCoordination.

USNRC (U.S. Nuclear Regulatory

Commission).

2013. Monticello

Nuclear Generating

Plant, NRCInspection

Report 05000263/2013008;

Preliminary

Yellow Finding.12

Enclosure

5Monticello

Nuclear Generating

Plant"Stakeholder

Outreach"

I Page Follows

Stakeholder

OutreachNSPM hosted an open house on Thursday,

June 6, from 4 p.m.-8 p.m. to shareinformation

with its community

neighbors

on operations

and preparedness

to handlepotential

emergencies

and how we would respond to flooding,

earthquakes

and otherunforeseen

challenges.

The Site employed

numerous

methods to publicize

the event:personal,

direct invitations

to community

leaders,

a full page ad was purchased

inweekly newspapers,

a news release was distributed

to local media and 14,000postcards

were mailed to neighbors

in surrounding

communities.

The outreach

eventhad full corporate

support and the Xcel Energy Chairman,

President

and CEO, and theChief Nuclear Officer attended,

as well as numerous

senior members of the corporate

nuclear staff. The Monticello

Site Vice President

and Plant Manager were also joined bythe site's senior leadership

team at the event.A total of 515 persons from Monticello

and surrounding

communities

attended

the eventat the Monticello

Training

Center.The key message presented

to visitors

was that safety and security

at the NSPM nucleargenerating

plants are top priorities

for Xcel Energy. Further,

that we understand

theNRC's increased

scrutiny

of safety and flood preparedness

at the nation's

nuclear powerplants in the wake of events such as 9/11 and Fukushima

Daiichi.

The Monticello

FloodProtection

Strategy

was identified

and explained

to demonstrate

that the site is designedto withstand

a hypothetical

flood beyond anything

reported

in the Monticello

area. Thebroad underlying

key messages

were reinforced

and manifest

in specific

subject itemssuch as: B.5.b Pump/Electrical

Generator/Trailer,

Portable

Emergency

ResponseEquipment,

Backup Power Sources including

description

of backups to the backup(Battery

Systems)

and the continual

focus on improving

emergency

preparedness

capabilities.

Page 1 of 1