| Q | CCA | Title |
---|
05000323/FIN-2014005-01 | 2014Q4 | H.5 | Failure to Implement Fire Protection Program |
05000275/FIN-2014005-03 | 2014Q4 | H.11 | Failure to Effectively Implement Risk Management Actions Associated with Safety-Related Emergency Diesel Generators |
05000275/FIN-2014502-01 | 2014Q4 | | Failure to Obtain Prior Approval for a Change Which Decreased the Effectiveness of the Emergency Plan |
05000275/FIN-2014005-02 | 2014Q4 | H.12 | Failure to Control Access to a High Radiation Area with Dose Rates Greater Than 1 Rem/Hour |
05000323/FIN-2015001-01 | 2015Q1 | | Failure to Provide Adequate Design Review of EDG 2-3 |
05000275/FIN-2015002-05 | 2015Q2 | | Failure to Appropriately Scope 230 KV Switchyard into the Maintenance Rule Monitoring Program |
05000275/FIN-2015002-06 | 2015Q2 | H.5 | High Voltage Insulator Flashover Resulted in Loss of 230 kV Offsite Power and Start of Emergency Diesel Generators |
05000275/FIN-2015002-01 | 2015Q2 | H.6 | Failure to Appropriately Pre-plan and Perform Maintenance on Hydrogen Guard Piping |
05000275/FIN-2015002-02 | 2015Q2 | H.1 | Failure to Maintain Operator Licensing Examination Integrity |
05000275/FIN-2015002-03 | 2015Q2 | | Inadequate Design Control for High-Energy Line Break Vent Flow Path |
05000275/FIN-2015002-04 | 2015Q2 | H.5 | Technical Specification 3.3.4 Not Met Due to Inoperable Remote Shutdown System Function |
05000275/FIN-2015003-01 | 2015Q3 | H.6 | Failure to Document an Adequate Evaluation for a Change in Seismic Load Combination Methodology |
05000275/FIN-2015003-02 | 2015Q3 | H.12 | Failure to Secure a Locked High Radiation Area |