Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat
ML041410258
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 05/24/2004
From: John Nakoski
NRC/NRR/DLPM/LPD2
To: Young D
Progress Energy Carolinas
Chernoff, M H, NRR/DLPM, 301-415-4041
References
TAC MC2909
Download: ML041410258 (5)


Text

May 24, 2004 Mr. Dale E. Young Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing and Regulatory Programs 15760 W. Power Line Street Crystal River, FL 34428-6708

SUBJECT:

CRYSTAL RIVER NUCLEAR GENERATING PLANT, UNIT 3 -

SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NO. MC2909)

Dear Mr. Young:

On April 29, 2003, the U.S. Nuclear Regulatory Commission (NRC) issued an Order modifying the operating license for the Crystal River Nuclear Generating Plant, Unit 3 to: (1) require compliance with a revised design basis threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.

Section III.A.1 of EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the Commission for review and approval no later than April 29, 2004. The Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.

By letter dated April 29, 2004, you submitted a supplemental response to the Order for the Crystal River Nuclear Generating Plant, Unit 3. During the acceptance review of your submittal by NRC staff, the need for additional information in Attachment E was identified. The need for additional information was discussed with Mr. Scott Young of your staff on May 11, 2004. Mr.

Young agreed to furnish the revised Attachment E.

The NRC staff will be reviewing your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.

Dale E. Young The NRC staff is currently reviewing your supplemental response and intends to complete the review of your revised plan by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302 cc: See next page Dale E. Young The NRC staff is currently reviewing your supplemental response and intends to complete the review of your revised plans by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302 cc: See next page DISTRIBUTION:

PUBLIC SPRT R/F J. Nakoski J. Peralta C. Hawes M. Chernoff P. Peduzzi OGC ACRS NRR/DLPM - PMs NRR/DLPM - SCs C. Bixler, RII ADAMS Accession Number: ML041410258 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR/SC SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/21/04 5/21/04 5/21/04 5/21/04 5/24/04 OFFICIAL RECORD COPY

Crystal River Nuclear Plant Unit 3 Florida Power Corporation cc:

Mr. R. Alexander Glenn Associate General Counsel (MAC-BT15A)

Florida Power Corporation P.O. Box 14042 St. Petersburg, Florida 33733-4042 Mr. Jon A. Franke Plant General Manager Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. Jim Mallay Framatome ANP 1911 North Ft. Myer Drive, Suite 705 Rosslyn, Virginia 22209 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Mr. Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Steven R. Carr Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, North Carolina 27602-1551 Chairman Board of County Commissioners Citrus County 110 North Apopka Avenue Inverness, Florida 34450-4245 Mr. Michael J. Annacone Engineering Manager Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. Daniel L. Roderick Director Site Operations Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708 Senior Resident Inspector Crystal River Unit 3 U.S. Nuclear Regulatory Commission 6745 N. Tallahassee Road Crystal River, Florida 34428 Mr. Richard L. Warden Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing

& Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708