CBS Exemption Decision for Perry (Attachment)
ML24103A123
Person / Time
Site: Perry, 07200069  FirstEnergy icon.png
Issue date: 05/08/2024
From: Yoira Diaz-Sanabria
Storage and Transportation Licensing Branch
To:
Vistra Operations Company
Shared Package
ML24103A129 List:
References
NRC-2024-0082
Download: ML24103A123 (10)


Text

Attachment - Exemption

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 72 -69, and 50- 440; NRC-2024- 0082]

Vistra Operations Company LLC;

Perry Nuclear Power Plant, Unit 1;

Independent Spent Fuel Storage Installation;

I. Background

Vistra Operations Company LLC (VistraOps) is the holder of Facility Operating License

No. NPF-58, which authorizes operation of the Perry Nuclear Power Plant, Unit 1 (Perry) in

North Perry, Ohio, pursuant to part 50 of Title 10 of the Code of Federal Regulations (10 CFR),

Domestic Licensing of Production and Utilization Facilities. The license provides, among other

things, that the facility is subject to all rules, regulations, and orders of the U.S. Nuclear

Regulatory Commission (NRC) now or hereafter in effect.

Consistent with 10 CFR part 72, subpart K, General License for Storage of Spent Fuel

at Power Reactor Sites, a general license is issued for the storage of spent fuel in an

Independent Spent Fuel Storage Installation (ISFSI) at power reactor sites to persons

authorized to possess or operate nuclear power reactors under 10 CFR p art 50. VistraOps is

authorized to operate nuclear power reactors under 10 CFR p art 50 and holds a 10 CFR part 72

general license for storage of spent fuel at the Perry ISFSI. Under the terms of the general

license, VistraOps stores spent fuel at its Perry ISFSI using the HI-STORM Flood/Wind (F/W)

Multipurpose Canister (MPC) Storage System in accordance with Certificate of Compliance

(CoC) No. 1032, Amendment No. 5.

II. Request/Action

By a letter dated February 27, 2024 (Agencywide Documents Access and Management

System [ADAMS] ML24058A180), by Energy Harbor Nuclear Corporat ion 1 and supplemented

by VistraOps on March 22, 2024 (ML24082A132), VistraOps requested an exemption from the

requirements of 10 CFR §§ 72.212(a)(2), 72.212(b)(3), 72.212(b)(5)(i), 72.212(b)(11), and

72.214 that require Perry to comply with the terms, conditions, and specifications of the CoC

No. 1032, Amendment No. 5 (ML20163A701). If approved, the VistraOps exemption request

would accordingly allow Perry to load two Multi-Purpose Canisters (MPC) with an unapproved

variant basket design with continuous basket shims (CBS) (i.e., MPC CBS), in the HI-

STORM F/W MPC Storage System beginning in August, 2024, and thus, to load the systems in

a storage condition where the terms, conditions, and specifications in the CoC No. 1032,

Amendment No. 5 are not met.

VistraOps currently uses the HI-STORM F/W MPC Storage System under CoC No.

1032, Amendment No. 5, for dry storage of spent nuclear fuel at the Perry ISFSI. Holtec

International (Holtec), the designer and manufacturer of the HI-STORM F/W MPC Storage

System, developed a variant of the design with CBS for the MPC-89, known as MPC CBS.

Holtec performed a non-mechanistic tip -over analysis with favorable results and implemented

the CBS variant design under the provisions of 10 CFR 72.48, Changes, tests, and

experiments, which allows licensees to make changes to cask designs without a CoC

amendment under certain conditions (listed in 10 CFR 72.48(c)). After evaluating the specific

changes to the cask designs, the NRC determined that Holtec erred when it implemented the

1 Effective March 1, 2024, the facility operating license for Perry Nuclear Power Plant was transferred from Energy Harbor Nuclear Generation LLC (owner) and Energy Harbor Nuclear Corp. (operator) to Energy Harbor Nuclear Generation LLC (owner) and Vistra Operations Company LLC (ADAMS Accession No. ML24057A075). Upon completion of this license transfer, Vistra Operations Company LLC (VistraOps) assumed the responsibility for all licensing actions under NRC review at the time of the transfer and requested that the NRC continue its review of these actions (ADAMS Accession No. ML24054A498).

2 CBS variant design under 10 CFR 72.48, as this is not the type of change allowed without a

CoC amendment. For this reason, the NRC issued three Severity Level IV violations to Holtec

(ML24016A190).

VistraOpss near-term loading campaign for the Perry ISFSI, in addition to other loadings

of non-CBS MPCs, also includes plans to load two MPC-89-CBS in the HI-STORM F/W MPC

Storage System in August 2024. While Holtec was required to submit a CoC amendment to the

NRC to seek approval of the CBS variant design, such a process will not be completed in time

to inform decisions for this near-term loading campaign. Therefore, VistraOps submitted this

exemption request in order to allow for the future loadings of the two MPC CBS canisters

beginning in August 2024 at the Perry ISFSI. This exemption is limited to the use of two

MPC CBS in the HI-STORM F/W MPC Storage System for the specific near-term planned

loading beginning in August 2024.

III. Discussion

Pursuant to 10 CFR 72.7, Specific exemptions, the Commission may, upon application

by any interested person or upon its own initiative, grant such exemptions from the

requirements of the regulations of 10 CFR part 72 as it determines are authorized by law and

will not endanger life or property or the common defense and security and are otherwise in the

public interest.

A. The Exemption is Authorized by Law

This exemption would allow VistraOps to load two MPC-89-CBS canisters in the HI-

STORM F/W MPC Storage System beginning in August 2024 at its Perry ISFSI in a storage

condition where the terms, conditions, and specifications in the CoC No. 10 32, Amendment No.

5, are not met. VistraOps is requesting an exemption from the provisions in 10 CFR p art 72 that

require the licensee to comply with the terms, conditions, and specifications of the CoC for the

3 approved cask model it uses. Section 72.7 allows the NRC to grant exemptions from the

requirements of 10 CFR part 72. This authority to grant exemptions is consistent with the Atomic

Energy Act of 1954, as amended, and is not otherwise inconsistent with NRCs regulations or

other applicable laws. Additionally, no other law proh ibits the activities that would be authorized

by the exemption. Therefore, the NRC concludes that there is no statutory prohibition on the

issuance of the requested exemption, and the NRC is authorized to grant the exemption by law.

B. The Exemption Will Not Endanger Life or Property or the Common Defense and

Security

This exemption would allow VistraOps to load two MPC-89-CBS in the HI-STORM F/W

MPC Storage System beginning in August 2024 at the Perry ISFSI in a storage condition where

the terms, conditions, and specifications in the CoC No. 1032, Amendment No.5 are not met. In

support of its exemption request, VistraOps asserts that issuance of the exemption would not

endanger life or property because a tip-over or handling event is administratively controlled, and

that the containment boundary would be maintained in such an event. VistraOps relies, in part,

on the approach in the NRCs Safety Determination Memorandum (ML24018A085). The NRC

issued this Safety Determination Memorandum to address whether, with respect to the

enforcement action against Holtec regarding this violation, there was any need to take an

immediate action for the cask systems that were already loaded with non-compliant basket

designs. The Safety Determination Memorandum documents a risk-informed approach

concluding that, during the design basis event of a non-mechanistic tip-over, the fuel in the

basket in the MPC CBS remains in a subcritical condition.

VistraOps also provided site-specific technical information, as supplemented, including

information explaining why the use of the approach in the NRCs Safety Determination

Memorandum is appropriate for determining the safe use of the CBS variant baskets at the

Perry ISFSI. Specifically, VistraOps described that the analysis of the tip -over design basis

4 event that is relied upon in the NRCs Safety Determination Memorandum, which demonstrates

that the MPC confinement barrier is maintained, is documented in the updated final safety

analysis report (UFSAR) for the HI-STORM F/W MPC Storage System CoC No. 1032,

Amendment No. 5 that is used at the Perry site. VistraOps also described its administrative

controls for handling of the HI-STORM F/W MPC Storage System at the Perry ISFSI to prevent

a tip-over or handling event. Those controls include ensuring that all lifts of the cask will be

conducted in accordance with Perry 's existing heavy load program. The f uel handling b uilding

crane at Perry was upgraded to single failure proof. Also, evaluations pursuant to 10 CFR

50.59, Changes, tests and experiments, have been performed demonstrating that heavy load

lifts and the use of the HI-STORM F/W MPC Storage System are in compliance with Perrys

existing heavy load requirements. In addition, t ransportation of a loaded HI-STORM F/W MPC

Storage System into and out the fuel handling building is accomplished using a zero profile

transporter with Hilman rollers that provides support from underneath. The applicant stated that

transportation of a loaded HI-STORM storage cask between the fuel handling building and the

ISFSI is accomplished by the Holtec HI-TRAN, which meets the requirements of CoC No. 1032,

Amendment No. 5. VistraOps provided information from Perry Nuclear Power Plant 10 CFR

72.212 Evaluation Report," Revision 2, which evaluated the seismic stability of the transport of

the overpack and during stackup. VistraOps report concluded that both HI-STORM/HI-TRAC

Stackup and transfer of the loaded HI-STORM overpack by HI-TRAN remains kinematically

stable and does not overturn during a seismic event.

Additionally, VistraOps provided specific information from Perrys site evaluation from its

Perry Nuclear Power Plant 10 CFR 72.212 Evaluation Report, Revision 2, which states that

during the design basis event of a non-mechanistic tip-over, Perrys ISFSI would meet the

requirements in 10 CFR 72.106, Controlled area of an ISFSI or MRS [monitored retrievable

storage installation]. Specifically, VistraOps stated that section 12.2 of the UFSAR for the

5 HI-STORM F/W MPC Storage System shows that there are no accidents that significantly affect

the shielding analyses. In addition, the minimum distance from the ISFSI to the site boundary at

the Perry ISFSI is 428 meters, compared to the 100- meter distance in the UFSAR. In the highly

unlikely event of a tip-over, any potential fuel damage from a non-mechanistic tip-over event

would be localized, the confinement barrier would be maintained, and the storage cask shielding

material would remain intact. Coupled with the distance of the Perry ISFSI to the site area

boundary, VistraOps concluded that compliance with §§ 72.104, Criteria for radioactive

materials in effluents and direct radiation from an ISFSI or MRS, and 72.106 is not impacted by

approving this exemption request.

The NRC staff reviewed the information provided by VistraOps and concludes that

issuance of the exemption would not endanger life or property because the administrative

controls VistraOps has in place at the Perry ISFSI sufficiently minimize the possibility of a tip-

over or handling event, and that the containment boundary would be maintained if such an

event were to occur. The staff confirmed that the technical specifications for the CoC No. 1032,

Amendment No. 5, for the HI-STORM F/W MPC Storage System used at the Perry site contain

restrictions on lifting the transfer cask or storage cask when loaded with fuel. Specifically,

technical specification 5.2.c.2 authorizes lifting to any height as long as t he horizontal cross

beam and any lifting attachments used to connect the load to the lifting equipment are designed,

fabricated, operated, tested, inspected, and maintained in accordance with applicable sections

and guidance of NUREG-0612, Control of Heavy Loads at Nuclear Power Plants: Resolution of

Generic Technical Activity A-36, Section 5.1, including applicable stress limits from American

National Standards Institute N14.6, Radioactive Materials - Special Lifting Devices For

Shipping Containers Weighing 10 000 Pounds (4500 Kg) Or More. In addition, the staff

confirmed that the information provided by VistraOps regarding Revision 2 of the Perry Nuclear

Power Plant 10 CFR 72.212 Evaluation Report," demonstrates that the consequences of normal

6 and accident conditions would be within the regulatory limits of the 10 CFR 72.104 and 10 CFR

72.106. The staff also determined that the requested exemption is not related to any aspect of

the physical security or defense of the Perry ISFSI; therefore, granting the exemption would not

result in any potential impacts to common defense and security.

For these reasons, the NRC staff has determined that under the requested exemption,

the storage system will continue to meet the safety requirements of 10 CFR part 72 and the

offsite dose limits of 10 CFR part 20 and, therefore, will not endanger life or property or the

common defense and security.

C. The Exemption is Otherwise in the Public Interest

The proposed exemption would allow VistraOps to load two MPC-89-CBS in the HI-STORM

F/W MPC Storage System in August 2024, at the Perry ISFSI, even though the CBS variant

basket design is not part of the approved CoC No. 1032, Amendment No. 5. According to

VistraOps, the exemption is in the public interest because not being able to load fuel into the

two MPC-89-CBS baskets during the August 2024 loading campaigns would impact VistraOpss

ability at Perry to maintain full-core offload capability, consequently increasing risk and

challenges to continued safe reactor operation.

VistraOps stated that to delay the August 2024 loading of the two MPC CBS baskets

at Perry would impact the ability to maintain a healthy margin in the spent fuel pool in support of

a full-core discharge capability. VistraOps stated that not loading the two MPC-89-CBS spent

fuel canisters for storage on the ISFSI pad in August 2024, decreases the margin to full-core

offload to 555 open cells in the spent fuel pool. There are two refueling outages planned for

2025 and 2027 that would decrease the full-core offload margin to an insufficient number of

open fuel cells (a deficit of 25 open cells) due to the planned discharges of 288 and 292 fuel

bundles, respectively. That is, the Perry spent fuel pool would lose full-core offload in 2027 and

would not regain full-core offload, and margin to full -core offload, until the 2028 spent fuel

7 loading campaign. Having no full-core offload capability for over a year of operation at Perry is

an unnecessary risk to the operation of the plant, spent fuel pool inventory and operations. In

order to regain full-core offload prior to the 2028 spent fuel loading campaign, non-fuel

components stored in the pool would need to be relocated, which involves additional resources,

dose, and risk to perform the relocations.

For the reasons described by VistraOps in its exemption request, the NRC agrees that it

is in the public interest to grant the exemption. If the exemption is not granted, in order to

comply with the CoC, VistraOps would have to keep spent fuel in the spent fuel pool if it is not

permitted to be loaded into casks in the August 2024 spent fuel loading, thus impacting Perrys

ability to effectively manage the margin for full-core discharge capacity. As explained by

VistraOps, increased inventory of fuel in the spent fuel pool could result in the need for

relocation or movement of non-fuel components and, therefore, an increase in worker doses

and the potential for accidents that accompany increased movement of radioactive material.

Moreover, should spent fuel pool capacity be reached, the ability to refuel the operating reactor

unit is challenged, thus potentially impacting continued reactor operations.

Therefore, the staff concludes that approving the exemption is in the public interest.

Environmental Consideration

The NRC staff also considered whether there would be any significant environmental

impacts associated with the exemption. For this proposed action, the NRC staff performed an

environmental assessment pursuant to 10 CFR 51.30. The environmental assessment

concluded that the proposed action would not significantly impact the quality of the human

environment. The NRC staff concluded that the proposed action would not result in any changes

in the types or amounts of any radiological or non-radiological effluents that may be released

offsite, and there would be no significant increase in occupational or public radiation exposure

8 because of the proposed action. The environmental assessment and the f inding of no significant

impact was published on May 8, 2024 (89 FR 38926).

IV.Conclusion

Based on these considerations, the NRC has determined that, pursuant to 10 CFR 72.7,

the exemption is authorized by law, will not endanger life or property or the common defense

and security, and is otherwise in the public interest. Therefore, the NRC grants VistraOps an

exemption from the requirements of §§ 72.212(a)(2), 72.212(b)(3), 72.212(b)(5)(i),

72.212(b)(11), and 72.214 with respect to the loading of two HI-STORM F/W MPC Storage

System in MPC CBS beginning in August 2024.

This exemption is effective upon issuance.

Dated: May 8, 2024.

For the Nuclear Regulatory Commission.

/RA/

Yoira Diaz-Sanabria, Chief, Storage and Transportation Branch, Division of Fuel Management, Office of Nuclear Material Safety, and Safeguards.

9

ML24103A123 OFFICE NMSS/DFM NMSS/DFM NMSS/REFS NMSS/DFM NAME BWhite JGoodridge RSun TBoyce

DATE 4/15/2024 4/17/2024 4/16/2024 4/16/2024 OFFICE NMSS/DFM OGC/NLO NMSS/DFM

NAME HRodriguez ACoggins YDiaz-Sanabria DATE 4/15/2024 4/25/2024 5/8/2024