MONTHYEARML24261C0092024-09-16016 September 2024 Kairos Power LLC - Charlotte Office Address ML24158A2322024-08-30030 August 2024 Letter to Kairos, Inc., Exemption and Final EA ML24200A1172024-07-19019 July 2024 Transmittal Letter for the Hermes 2 Safety Evaluation ML24155A0612024-06-0303 June 2024 Kairos Power LLC, Presentation Materials for the Kairos Power Meeting with the Nuclear Regulatory Commission on the Hermes Foundation Design ML24150A2442024-05-29029 May 2024 Kairos Power, LLC - Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes 2 Preliminary Safety Analysis Report, Chapters 2, 3, 5, 9, and 13 ML24150A2172024-05-28028 May 2024 Kairos Power, LLC - Request for Documents Related to Non-Power Security ML24144A0912024-05-23023 May 2024 Kairos Power, LLC - Submittal of the Hermes 2 Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor, Revision 1, and the Postulated Event Analysis Methodology Technical Report, Revi ML24138A2122024-05-16016 May 2024 Kairos Power LLC Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapters 3, 5, and 13 ML24136A2542024-05-15015 May 2024 Kairos Power LLC - Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 9 ML24135A3832024-05-14014 May 2024 Kairos Power, LLC - Transmittal of Response to NRC Request for Confirmation of Information for the Review of the Hermes 2 PSAR Chapter 5 ML24131A1262024-05-10010 May 2024 Kairos Power, LLC - Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes 2 Preliminary Safety Analysis Report Chapters 1, 4, 6-8, 10-12, 14, and 16-18 ML24101A0772024-04-23023 April 2024 Hermes 2 NPS Dea ML24101A0782024-04-23023 April 2024 Hermes 2 SHPO Dea ML24101A0722024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Johnson, J ML24113A1732024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hill, D ML24113A1702024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Bunch, J ML24113A1692024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Bryan, a ML24113A1682024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Barnes, B ML24113A1712024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Cernek, J ML24113A1722024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hicks, M ML24113A1742024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Hoskin, Jr., C ML24113A1752024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Johnson, L J ML24113A1762024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Morrow, R K ML24113A1782024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Rogers, L ML24113A1772024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Osceola, Jr. M W ML24113A1792024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Sylestine, R ML24113A1822024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Yargee, W ML24113A1802024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Wallace, G J ML24113A1812024-04-22022 April 2024 Tribal Letters for Dea Hermes 2-Yahola, ML24101A2172024-04-19019 April 2024 Letter to Kairos Power, LLC-Notice of Availability of the Draft Environmental Assessment for the Construction Permit for Hermes 2 Test Reactors ML24109A2952024-04-16016 April 2024 Kairos Power, LLC - Slides to Support April 22, 2024, Public Meeting About Hermes Physical Security ML24103A2422024-04-12012 April 2024 Kairos Power, LLC, Transmittal of Reponses to NRC Requests for Confirmation of Information for the Review of the Hermes 2 PSAR Chapter 5 ML24103A2452024-04-12012 April 2024 Kairos Power, LLC, Transmittal of Changes to Construction Permit Application - Financial Information Enclosure and PSAR Chapter 15 ML24206A0852024-03-20020 March 2024 NPS Section 106 Initiation Response - Hermes 2 ML24073A3182024-03-13013 March 2024 Kairos Power LLC, Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 13 and KP-TR-022 ML24072A2982024-03-12012 March 2024 Kairos Power LLC - Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapter 7 ML24065A1012024-03-0404 March 2024 Kairos Power LLC, Transmittal of Reponses to NRC Requests for Confirmatory Information for the Review of the Hermes 2 Environmental Report ML24039A1902024-02-0808 February 2024 Kairos Power LLC, Transmittal of Changes to Hermes 2 Construction Permit Application – PSAR Chapter 2 ML24032A1892024-02-0202 February 2024 Ltr Hon Glenna J Wallace Chief Eastern Shawnee Tribe of Oklahoma Re Hermes 2 ML24032A2002024-02-0202 February 2024 Ltr Libby Rogers, Principal Chief, Jena Band of Choctaw Indians Re Hermes 2 ML24032A1992024-02-0202 February 2024 Ltr Hon Wilson Yargee, Chief Alabama-Quassarte Tribal Town Re Hermes 2 ML24032A1982024-02-0202 February 2024 Ltr Hon Stephanie Yahola, Mekko Kialegee Tribal Town Re Hermes 2 ML24032A1972024-02-0202 February 2024 Ltr Hon Stephanie a Bryan Chairwoman Poarch Band of Creek Indians Re Hermes 2 ML24032A1962024-02-0202 February 2024 Ltr Hon Ryan K Morrow Town King Thlopthlocco Tribal Town Re Hermes 2 ML24032A1952024-02-0202 February 2024 Ltr Hon Rick Sylestine, Chairman, Alabama-Coushatta Tribe of Tx Re Hermes 2 ML24032A1942024-02-0202 February 2024 Ltr Hon Michell Hicks Principal Chief Eastern Band of Cherokee Indians Re Hermes 2 ML24032A1932024-02-0202 February 2024 Ltr Hon Marcellus W Osceola Jr Chairman Seminole Tribe of Fl Re Hermes 2 ML24032A1922024-02-0202 February 2024 Ltr Hon Lewis J Johnson Chief Seminole Nation of Oklahoma Re Hermes 2 ML24032A1912024-02-0202 February 2024 Ltr Hon Jonathan Cernek Chairman Coushatta Tribe of Louisiana Re Hermes 2 ML24032A1902024-02-0202 February 2024 Ltr Hon Joe Bunch Chief United Keetoowah Band of Cherokee Indians Re Hermes 2 2024-09-16
[Table view] |
Text
August 30, 2024
Mr. Peter Hastings Vice President, Regulatory Affairs and Quality Kairos Power LLC 707 W Tower Ave, Suite A Alameda, CA 94501
SUBJECT:
NOTIFICATION OF THE ISSUANCE OF THE FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNFICANT IMPACT FOR THE CONTRUCTION PERMIT REVIEW FOR THE KAIROS HERMES 2 TEST REACTOR FACILITY AND EXEMPTIONS FROM CERTAIN REQUIREMENTS IN 10 CFR PART 51
Dear Mr. Hastings:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing a construction permit (CP) application submitted by Kairos Power, LLC (Kairos) for two non-power test reactors referred to collectively as Hermes 2. The application was submitted by Kairos in a letter dated July 14, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23195A121), pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of Production and Utilization Facilities. The two CPs, if issued, would authorize the construction of the two Hermes 2 reactors on a 185-acre site located in Oak Ridge, TN, adjacent to the Hermes reactor, for which Kairos received a CP from the NRC dated December 14, 2023 (ML23338A258). The Hermes 2 reactors would demonstrate additional key elements of the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor Technology for possible future commercial deployment.
As part of the review of this CP application, the NRC prepared a draft environmental assessment (EA) and a draft finding of no significant impact (FONSI) that consider the environmental impacts associated with issuing the CPs. The draft EA and draft FONSI were issued for public comment on April 26, 2024, in the Federal Register (89 FR 32462). After consideration of public comments, the NRC made a determination that the proposed action would not significantly affect the quality of the human environment, and therefore, a FONSI is warranted and an environmental impact statement (EIS) will not be prepared. The final EA and FONSI are publicly available at ML24240A034. The final EA and FONSI also address the environmental impacts of granting the exemptions described below.
To support the issuance of the final EA and FONSI for the Hermes 2 test reactor facility, the NRC has granted exemptions from certain NRC requirements in 10 CFR Part 51 which require the NRC to prepare an EIS to support the issuance of a CP for a test facility. Specifically, the exemptions are from the requirements of 10 CFR 51.20, Criteria for and identification of licensing and regulatory actions requiring environmental impact statements, paragraph (b)(1);
10 CFR 51.25, Determination to prepare environmental impact statement or environmental P. Hastings
assessment; eligibility for categorical exclusion; and 10 CFR 51.75, Draft environmental impact statement - construction permit, early site permit, or combined license, paragraph (a).
Granting these exemptions was not in response to a request by Kairos. The NRC determined that exemptions from these requirements were necessary to issue a final EA and FONSI instead of an EIS to meet the staffs obligations under the National Environmental Policy Act of 1969 and the NRCs regulations for the environmental review of the Hermes 2 CP application.
These exemptions are effective on August 30, 2024. A copy of the exemptions is enclosed and has been forwarded to the Office of the Federal Register for publication.
If you have questions regarding this matter, please contact Cayetano Santos Jr., at (301) 415-7270 or via email at Cayetano.Santos@nrc.gov.
Sincerely, Joshua M. Digitally signed by Joshua M.
Borromeo Borromeo Date: 2024.08.30 08:05:27 -04'00'
Joshua Borromeo, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
Docket Nos.:
50-611 50-612
Enclosure:
As stated
cc: Distribution via GovDelivery Subscribers
PKG: ML24158A231 Letter: ML24158A232
Enclosure:
ML24158A234 NRR-106 OFFICE NRR/DANU/UAL1:PM NMSS/REFS/ERNRB:PM NRR/DANU/UAL1:LA NAME CSantos PDoub DGreene DATE 7/23/24 7/23/24 7/23/24 OFFICE NMSS/REFS/ERNRB:BC NRR/DANU/UAL1:BC OGC NAME DBarnhurst JBorromeo Aghosh Naber DATE 7/26/24 7/25/24 8/16/24 OFFICE NMSS/REFS/D NRR/DANU/D NRR/DANU/UAL:BC NAME CRegan JBowen JBorromeo DATE 8/23/24 8/22/24 8/30/24